This document is a Pre-Construction Checklist for a VA (Veterans Affairs) construction project. It outlines critical administrative and procedural requirements for the contractor, including key responsibilities and guidelines for project execution. The checklist covers multiple important areas such as contract authority, progress scheduling, payment requests, safety protocols, change management, subcontractor approvals, and labor standards.

Specific requirements include submitting a detailed cost schedule and progress chart within 10 calendar days of the Notice to Proceed, providing monthly payment invoices to Austin, Texas, maintaining daily logs documenting workforce, and adhering to strict change order protocols. The document emphasizes that only the Contracting Officer can authorize contract changes, with proposals over $1,000 requiring detailed itemization of labor, material costs, subcontractors, and overhead/profit percentages. The VA Project Manager is designated for technical supervision, and the VA Safety Officer has authority to halt work for serious safety violations.

View the file

Other files

File Type Posted
S06 36C25226B0001 0003.docx DOCX document
S06 36C25226B0001 0002.docx DOCX document
32 05 23 - Cement and Concrete for Exterior Improvements.pdf PDF
03 30 00 - Cast-In-Place Concrete.pdf PDF
P09 578-15-008 SOW 2026 R2 120125.docx DOCX document
1i. Hines Parking Designations.pdf PDF
2 Hines VA Campus Site Plan.pdf PDF
3 Infection Control Risk Assessement.pdf PDF
6 578-15-008 Specifications 112825.pdf PDF
8h. Building 228 Signage Legend.pdf PDF
11 Building 217 Signage Drawings-1.pdf PDF
13 Building 217 Signage Drawings-3.pdf PDF
25 Building 200 Signage Drawings-8.pdf PDF
26 Building 200 Signage Drawings-9.pdf PDF
34 Bldgs 16-18 Drawings.pdf PDF
35 Bldgs 20-48 Drawings.pdf PDF
37 CBOCs Drawings.pdf PDF
1d. Safety and Health During Construction Activities V2.pdf PDF
4 Interim Life Safety Measures.pdf PDF
5 Pre-construction Risk Assessment.pdf PDF
7 General Sheets of Drawings.pdf PDF
10 Buildings 12 128 Drawings.pdf PDF
14 Building 221 Signage Drawings.pdf PDF
17 Exterior Site Signage Drawings.pdf PDF
20 Building 200 Signage Drawings-3.pdf PDF
21 Building 200 Signage Drawings-4.pdf PDF
22 Building 200 Signage Drawings-5.pdf PDF
28 Bldg 1 Signage Drawings-2.pdf PDF
29 Bldg 1 Signage Drawings-3.pdf PDF
31 Bldg 1 Signage Drawings-5.pdf PDF
32 Bldg 1 Signage Drawings-6.pdf PDF
S02 Solicitation 36C25226B0001 Final.docx DOCX document
1a. Hines VA Campus Site Plan.pdf PDF
1b. Hines Underground Utility Plan.pdf PDF
1g. Above Ceiling Entry and Wall Construction Permits.pdf PDF
1h. Contractor Badging - Fingerprint Request Form 2025.pdf PDF
1m. Infection Control Barrier Sample.pdf PDF
1n. Hines COVID-19 Guidelines.pdf PDF
1o. No Smoking Policy 10-1-19.pdf PDF
1p. Emergency Contact List - Template.pdf PDF
8a. Building 12 Signage Legend.pdf PDF
8e. Building 200 Signage Legend.pdf PDF
8g. Building 221 Signage Legend.pdf PDF
12 Building 217 Signage Drawings-2.pdf PDF
18 Building 200 Signage Drawings-1.pdf PDF
23 Building 200 Signage Drawings-6.pdf PDF
24 Building 200 Signage Drawings-7.pdf PDF
30 Bldg 1 Signage Drawings-4.pdf PDF
38 Bldgs 100-Hoffman Drawings.pdf PDF
P07 WAGE DETERMINATION COOK IL20250009 11-2025.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-CONSTRUCTION CHECKLIST

PROJECT: __________________________________________________

DATE: ____________________ CONTRACT: _____________________

1. AUTHORITY OF GOVERNMENT PERSONNEL.

☐ a. The Contracting Officer is the only person authorized to bind the U.S.

Government, and then only to the extent of the authority invested in him/her by the appointment.

☐ b. The VA Project Manager is designated as the Contracting Officer's representative for the purpose of technical supervision and acceptance. The VA Project Manager is responsible for the inspection of the work called for in the contract schedules, including related specifications and contract terms regarding on-site work requirements. Pursuant to the delegation of authority (attached), the Project Manager does not have the authority to make changes to the contract in amount or time.

☐ c. The VA Project Manager for this project is _________________

☐ d. No other office or individual has the authority to act in any manner on behalf of the U.S. Government in the performance of this contract. The VA Project Manager will refer any changes or questions regarding this contract to the Contracting Officer.

2. CONTRACT PROGRESS SCHEDULES AND REPORTS:

☐ a. The Contractor shall submit a schedule of cost to the Contracting Officer within 10 calendar days after date of receipt of the Notice to Proceed.

The approved cost schedule will be one of the bases for determining progress payments for work completed. In accordance with FAR 52.236-1, Performance of Work by the Contractor, the schedule must indicate what portion(s) of the work the contractor intends to perform with his/her own workforce to meet the 15% requirement.

☐ b. The Contractor shall submit a progress chart, with in l O calendar days after issuance of a Notice to Proceed, which indicates the anticipated installation of work versus the elapsed contract time, which shall be represented in the form of a bar graph. The starting date of the schedule shall be the date of the Notice to Proceed and the ending date shall be the original contract completion date.

☐ c. Submittals, samples, and shop drawings. Project Engineer will explain distribution procedures

3. PAYMENT REQUESTS:

☐ a. Payments shall be made monthly by the VA according to the value of completed work from the Contractor's approved Schedule of Costs. All invoices should be submitted to Austin Texas as outlined in the contract. In accordance with the Prompt Payment Act, the fourteen (14) day timeframe for payment shall commence on the date a proper invoice is received by the CO. Included with the pay request shall be the payroll sheets for the Contractor and Subcontractors.

4. PROTECTION OF SURROUNDING AREA:

☐ a. In performing this contract, the Contractor shall provide for protecting the lives and health of employees and other persons, preventing damage to property, materials, supplies, equipment and avoiding work interruptions.

☐ b. Any damage caused by the Contractor or his personnel will be restored and repaired at the expense of the Contractor.

5. DAILY LOGS:

☐ a. The Contractor shall provide the VA Project Manager with daily logs.

Project Engineer will explain frequency. The daily log shall identify the number of laborers, supervisors and each branch of work and will be used to verify payrolls submitted.

2. SAFETY:

☐ a. The VA Safety Officer has the authority to stop work if a serious safety violation is being committed.

3. CHANGES:

☐ a. The Contracting Officer (CO), from information furnished by the COR may, by a written order, make changes to the drawings and/or specifications that are within the general scope of the contract. No other person is authorized to make revisions, changes, or deletions from the contract.

☐ b. Proposals for changes in work shall be submitted to the Contracting Officer according to VA requirements. Proposals more than $1,000 must include:

1. Itemized breakdown of labor and material costs.

2. List of subcontractors performing the work.

3. Overhead & Profit percentages.

☐ c. Change Orders (Proceed Orders): There may be some instances (as described in Clause 52.343-4 of the General Conditions) where the need to proceed with a change in work is necessary. In these cases, written authorization will be issued by the Contracting Officer (CO) to proceed with the work. An equitable adjustment will be negotiated within 30 calendar days.

4. SUBCONTRACTORS:

☐ a. The Contractor shall submit a list of subcontractors which will include names and addresses and the nature of work involved (SF 1413). The Contracting Officer reserves the right to disapprove any proposed

Subcontractor who has had prior record of unsatisfactory work at this site, or any Federal or non-Federal Agency.

9. LABOR STANDARDS PROVISONS AND PAYROLLS:

☐ a. A copy of the rates and wages shall be posted by the Contractor in a prominent place at the work site.

☐ b. Apprentices will be permitted to work only under a Bona Fide apprenticeship program. Concurrent with or prior to the first payroll listing, certificates of apprenticeship from a recognized council shall be submitted to the Contracting Officer.

10. CORRESPONDENCE:

a. All correspondence from the Contractor shall bear:

☐ (1) Contract Number

☐ (2) Project Title

☐ (3) Project Name

11. OTHER TOPICS SPECIFIC TO THIS PROJECT:

{Signature of Contracting Officer, (CO) Date

Signature of Project Manager, (COR) Date

Signature of Contractor Date: