Attachment__12_00_00_01_-_Revised_Specifications_07-16-21_0003.pdf
PDF 2 MB Posted
- Attached to
- NGWSP NAVAJO CODE TALKERS SUBLATERAL Federal contract opportunity
- Solicitation number
- 140R4021R0009
About this file
This document provides specifications for a federal construction project solicitation related to the Navajo-Gallup Water Supply Project. The solicitation involves work on the Navajo Code Talkers Sublateral for Reaches 12.1 and 12.2, including installation of a water pipeline and related infrastructure.
The specifications require the contractor to perform work such as excavation, installation of steel and ductile iron water pipelines, directional drilling, manholes, valves, electrical systems, traffic control, erosion control, seeding and other site remediation. The contractor must also develop plans for environmental controls, safety, traffic control, SWPPP compliance and protection of existing utilities. Submittals are due ranging from 14 to 70 days after award, and the contractor must coordinate with various federal, state and tribal agencies during performance of the work.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo-Gallup Water Supply Project Amendment 003 San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Price Schedule Revised B - 1
SECTION B - SUPPLIES OR SERVICES AND PRICES
SAN JUAN LATERAL – NAVAJO CODE TALKERS SUBLATERAL
REACHES 12.1 & 12.2
NAVAJO-GALLUP WATER SUPPLY PROJECT - NEW MEXICO
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only a part of the Price Schedules.
(b) Offers are subject to terms and conditions of this solicitation.
(c) Quantities in the Price Schedules are estimated quantities for comparison of offers only.
Except as provided in contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against Government for overruns or underruns. Contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1-1.
(e) Definitions:
(1) CLIN – Contract Line Item Number.
PRICE SCHEDULE 1 (Reach 12.1)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1-1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
1-2 01 31 30 Contract Document Management System
For the lump sum of $
1-3 01 33 26 Electrical Drawings and Data For the lump sum of $
1-3a 01 55 20 Traffic Control Barriers 3,760 Lin Ft $ $
1-4 01 56 15 Protection of Existing Utilities For the lump sum of $
1-5 01 78 30 As-built and Final Drawings (All Reaches)
For the lump sum of $150,000
1-6 01 78 30 Operations and Maintenance (O&M) Manuals (All Reaches)
For the lump sum of $25,000
1-7 03 48 10 Precast Concrete Manhole Sections
For the lump sum of $
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 2
PRICE SCHEDULE 1 (Reach 12.1)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1-8 03 81 10 Concrete Removal 150 yd3 $ $
1-9 25 00 01 System Control and Monitoring For the lump sum of $
1-10 26 05 02 Complete Electrical System For the lump sum of $
1-11 26 05 33 2-inch HDPE Conduit 58,730 lin ft $ $
1-12 26 42 10 Submerged Galvanic Anode Cathodic Protection System for Welded Steel Tanks
For the lump sum of $
1-13 26 42 11 Bolted Tank Submerged Galvanic Anode Cathodic Protection System
For the lump sum of $
1-14 26 42 12 Buried Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems
For the lump sum of $
1-15 31 02 10 Water for Dust Abatement 5,600 M(1,000) gal
1-16 31 02 30 Dust Palliative 58,600 lin ft $ $
1-17 31 11 00 Clearing and Grubbing For the lump sum of $
1-18 31 14 10 Stripping, Stockpiling, and Placement
For the lump sum of $
1-19 31 23 11 Common Excavation for Structures
29,500 yd3 $ $
1-20 31 23 11 Backfill about Structures 16,600 yd3 $ $
1-21 31 23 11 Compacting Backfill about Structures
16,600 yd3 $ $
1-22 31 23 22 Mobilization of Trench Box For the lump sum of $
1-23 31 23 22 Use of Trench Box 2,580 lin ft $ $
1-24 31 31 30 Soil-Applied Herbicide 45,500 yd2 $ $
1-25 31 37 00 Riprap 77 yd3 $ $
1-26 32 15 10 Gravel Surfacing 5,600 yd3 $ $
1-27 32 15 10 Black Hat Tank Access Road Excavation
2,100 yd3 $ $
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 3
PRICE SCHEDULE 1 (Reach 12.1)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1-28 32 31 10 Chain Link Fence 1,065 lin ft $ $
1-29 32 92 20 Seeding and Soil Amendment 137 ac $ $
1-30 33 05 21 Bored Utility Crossing – Sta.
121048+60 to Sta. 121049+70
110 lin ft $ $
1-31 33 05 21 Bored Utility Crossing – Sta.
121068+17 to Sta. 121068+85
68 lin ft $ $
1-32 33 05 21 Bored Utility Crossing – Sta.
121502+90 to Sta. 121504+00
110 lin ft $ $
1-33 33 05 22 Horizontal Directional Drilling
– Sta. 121198+77
1,060 lin ft $ $
1-34 33 05 22 Horizontal Directional Drilling
– Sta. 121452+94
940 lin ft $ $
1-35 33 05 22 Horizontal Directional Drilling
– Sta. 121573+29
1,270 lin ft $ $
1-36 33 11 10 24-Inch Line Pipe 25,392 lin ft $ $
1-37 33 11 10 30-Inch Line Pipe 33,505 lin ft $ $
1-38 33 11 10 Repair Kits For the lump sum of $
1-39 33 11 10 Filling and Testing Pipe 1,900,000 gal $ $
1-40 33 12 10 3-Inch Diameter Air Valve Assemblies –Class 150
2 ea $ $
1-41 33 12 10 3-Inch Diameter Air Valve Assemblies – Class 300
18 ea $ $
1-42 33 12 10 6-Inch Diameter Blowoffs – Class 150
2 ea $ $
1-43 33 12 10 6-Inch Diameter Blowoffs – Class 250
17 ea $ $
1-44 33 12 10 24-Inch Sectionalizing Valve Assemblies – Class 250B
3 ea $ $
1-45 33 12 10 24-Inch Sectionalizing Valve Assemblies – Class 350B
1 ea $ $
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 4
PRICE SCHEDULE 1 (Reach 12.1)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1-46 33 12 10 Line Pipe Sampling Stations 4 ea $ $
1-47 33 16 00 Black Hat Tank For the lump sum of $
1-48 33 82 23 Fiber Optic Cable 62,000 lin ft $ $
1-49 35 21 95 Steel Manifold Piping For the lump sum of $
1-50 35 22 15 Valves and Equipment For the lump sum of $
1-50a 35 42 35 Wash Crossing Sta. 121205+48 For the lump sum of $
1-51 35 42 35 Wash Crossing Sta. 121388+34 For the lump sum of $
1-52 35 42 35 Wash Crossing Sta. 121466+07 For the lump sum of $
TOTAL FOR PRICE SCHEDULE 1(Reach 12.1) $_________________
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 5
PRICE SCHEDULE 2 (Reach 12.2)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
2-1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
2-2 01 31 30 Contract Document Management System
For the lump sum of $
2-3 01 33 26 Electrical Drawings and Data For the lump sum of $
2-3a 01 55 20 Traffic Control Barriers 1,575 lin ft $ $
2-4 01 56 1516 Protection of Existing Utilities For the lump sum of $
2-5 25 00 01 System Control and Monitoring For the lump sum of $
2-6 26 05 02 Complete Electrical System For the lump sum of $
2-7 26 05 33 2-inch HDPE Conduit 22,838 lin ft $ $
2-8 26 42 10 Submerged Galvanic Anode Cathodic Protection System for Welded Steel Tanks
For the lump sum of $
2-9 26 42 11 Bolted Tank Submerged Galvanic Anode Cathodic Protection System
For the lump sum of $
2-10 26 42 12 Buried Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems
For the lump sum of $
2-11 31 02 10 Water for Dust Abatement 2,400 M(1,000) gal
2-12 31 02 30 Dust Palliative 23,110 lin ft $ $
2-13 31 11 00 Clearing and Grubbing For the lump sum of $
2-14 31 14 10 Stripping, Stockpiling, and Placement
For the lump sum of $
2-15 31 23 11 Common Excavation for Structures
27 yd3 $ $
2-16 31 23 11 Backfill about Structures 238 yd3 $ $
2-17 31 23 11 Compacting Backfill about Structures
238 yd3 $ $
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 6
PRICE SCHEDULE 2 (Reach 12.2)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
2-18 31 23 22 Mobilization of Trench Box For the lump sum of $
2-19 31 23 22 Use of Trench Box 5,023 lin ft $ $
2-20 31 31 30 Soil-Applied Herbicide 19,530 yd2 $ $
2-21 32 15 10 Gravel Surfacing 660 yd3 $ $
2-22 32 15 10 McKinley Surge Tank Access Road Excavation
350 yd3 $ $
2-23 32 31 10 Chain Link Fence 202 lin ft $ $
2-24 32 92 20 Seeding and Soil Amendment 47 ac $ $
2-25 33 05 22 Horizontal Directional Drilling
– Sta. 122033+73
1,279 lin ft $ $
2-26 33 05 22 Horizontal Direction Drilling – Sta. 122159+75
1,045 lin ft $ $
2-27 33 05 22 Horizontal Directional Drilling
– Sta. 122220+20
1,876 lin ft $ $
2-28 33 05 22 Horizontal Directional Drilling
– Sta. 122260+13
1,962 lin ft $ $
2-29 33 05 23 Open Cut Railroad Crossing 115 lin ft $ $
2-30 33 11 10 24-Inch Line Pipe 21,323 lin ft $ $
2-31 33 11 10 Steep Line Pipe 1,159 lin ft $ $
2-32 33 11 10 Combined 24-Inch and 24DR32.5 HDPE Drain Pipe
100 lin ft $ $
2-33 33 11 10 Combined 24-Inch and 16DR32.5 HDPE Drain Pipe
723 lin ft $ $
2-34 33 11 10 Repair Kits For the lump sum of $
2-35 33 11 10 Filling and Testing Pipe 700,000 gal $ $
2-36 33 12 10 2-Inch Diameter Air Valve Assemblies – Class 150
11 ea $ $
2-37 33 12 10 2-Inch Diameter Air Valve Assemblies – Class 300
8 ea $ $
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 7
PRICE SCHEDULE 2 (Reach 12.2)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
2-38 33 12 10 6-Inch Diameter Blowoffs – Class 150
7 ea $ $
2-39 33 12 10 6-Inch Diameter Blowoffs – Class 250
5 ea $ $
2-40 33 12 10 24-Inch Sectionalizing Valve Assemblies – Class 250B
2 ea $ $
2-41 33 12 10 Line Pipe Sampling Stations 1 ea $ $
2-42 33 16 00 McKinley Surge Tank For the lump sum of $
2-43 33 33 19 Baffled Outlet For the lump sum of $
2-44 33 42 30 24-Inch Diameter Corrugated Metal Culverts
40 lin ft $ $
2-45 33 82 23 Fiber Optic Cable 29,000 lin ft $ $
2-46 35 21 95 Steel Manifold Piping For the lump sum of $
2-47 35 22 15 Valves and Equipment For the lump sum of $
2-47a 35 42 35 Wash Crossing Sta. 122022+84 For the lump sum of $
2-48 35 42 35 Wash Crossing Sta. 122107+01 For the lump sum of $
TOTAL FOR PRICE SCHEDULE 2 (Reach 12.2) $_________________
END OF SECTION
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised B - 8
This page intentionally left blank.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Table of Contents
Revised 00 01 10 - 1
SECTION C - DESCRIPTION/SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 31 19 Project Management and Coordination 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 03 – CONCRETE
03 11 10 Concrete Forming 03 15 12 PVC Waterstops 03 15 18 Hydrophilic Waterstops 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 48 00 Plant-Precast Concrete Structures 03 48 10 Precast Concrete Manholes 03 63 00 Epoxy Grout 03 81 10 Concrete Removal
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 00 01 10 - 2
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 09 – FINISHES
09 96 20 Coatings
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10 14 26 Utility Markers
DIVISION 25 – INTEGRATED AUTOMATION
25 00 01 Control and Monitoring 25 08 10 Automation System Testing, Acceptance, and Training
DIVISION 26 - ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 20 Conductors and Cables 26 05 26 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 90 Wiring Checkout and Tests 26 21 12 Meter Socket 26 24 16 Panelboard 26 27 40 Wiring Devices 26 42 10 Submerged Galvanic Anode Cathodic Protection System for Welded Steel Tanks 26 42 11 Submerged Galvanic Anode Cathodic Protection System for Bolted Tank 26 42 12 Buried Galvanic Cathodic Protection and Corrosion Monitoring Systems
DIVISION 31 – EARTHWORK
31 02 10 Water for Dust Abatement 31 02 30 Dust Palliative 31 03 33 Removal of Water from Excavation 31 11 00 Clearing and Grubbing 31 14 10 Stripping, Stockpiling and Placement 31 23 02 Compacting Earth Materials 31 23 11 Earthwork for Structures 31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 23 70 Controlled Low Strength Material (CLSM) 31 24 18 Gravel Drain for Black Hat Tank 31 31 30 Soil-Applied Herbicide
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 00 01 10 - 3
31 32 36 HDPE Geomembrane for Black Hat Tank 31 37 00 Riprap
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 22 Asphalt Concrete Pavement 32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 91 60 Erosion Control Blanket 32 92 20 Seeding and Soil Amendment
DIVISION 33 – UTILITIES
33 05 21 Bored Utility Crossings 33 05 22 Horizontal Directional Drilling (HDD) 33 05 23 Open-Cut Railroad Crossings 33 11 10 Pipeline General Requirements 33 11 12 Steel Line Pipe 33 11 13 Ductile Iron Pipe 33 11 16 PVC Pressure Pipe 33 11 17 PVC Gravity Drain for Black Hat Tank 33 11 18 HDPE Pressure Pipe 33 11 30 Steel Manifold Piping for Line Pipe Installations 33 12 10 Valves and Equipment for Line Pipe Installations 33 16 00 Water Storage and Surge Tanks 33 16 50 Steel Tanks 33 16 51 Concrete Wire Wrapped Tank 33 16 52 Concrete Prestressed Tank 33 21 95 Metal Piping for Line Pipe Installations 33 33 19 Black Hat Tank Baffled Outlet 33 42 30 Corrugated Metal Pipe Culverts 33 82 23 Optical Fiber Communication Distribution Cabling
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 21 95 Steel Manifold Piping 35 22 15 Valves and Equipment 35 42 35 Bank Treatment
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Black Hat Tank Foundation Recommendations 51 00 20 Property Owner Contact Information – Pending 51 00 30 Tohlakai Pumping Plant – OIT Screens 51 00 40 NTUA – Markers 51 00 50 Railroad Agreement – Pending
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 00 01 10 - 4
DIVISION 52 – DRAWINGS
52 00 00 Drawings
DIVISION 53 – GEOLOGIC INVESTIGATIONS AND RECORDS
53 10 00 Geologic Investigations 53 20 00 Records of Geologic and Subsurface Investigations
END OF CONTENTS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Use of Site
Revised 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. Cleaning Manual-2012 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition. Available online at:
www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards in accordance with RSN 01 57 30-1.
2) Parking areas, temporary roads, and haul routes in accordance with RSN 01 57 30-1.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Concrete, CLSM and aggregate plants. Show sizes, rated capacities, and general features of aggregate processing plant including transporting, storing, screening, and washing facilities;
concrete batching and mixing plant; and concrete conveying, placing, and concrete washouts.
http://www.usbr.gov/mussels/prevention
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 14 10 - 2
6) Areas for processing, storing, and disposing of waste materials from construction operations.
7) Temporary fences.
b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to reseed disturbed areas in accordance with 32 92 20 – Seeding and Soil Amendment.
d. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
e. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. ROW or Easements as shown on drawings may be used for required construction facilities.
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
1. Prior to using land outside of ROW, obtain cultural and environmental approvals in accordance with Section 01 31 19 – Project Management and Coordination.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
D. Do not interfere with work of other contractors, Navajo Nation or Government in vicinity, or with reservations made by Government for use of such land.
E. Housing for construction personnel will not be permitted.
F. Natural Conditions:
1. Ambient Temperature Range: -45 to 40 degrees C.
2. Relative Humidity: 0 to 90 percent.
3. Altitude: 7,000 feet.
4. Wind:
a. Maximum sustained: 45 knots.
b. Maximum gust: 60 knots.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 14 10 - 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.
3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 14 10 - 4
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Submittals
Revised 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:
1. A - Action:
a. Government will respond as to adequacy of submittal.
b. Action submittals are considered to be “shop drawings” within terms of clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I - Informational:
a. Government will acknowledge receipt of Informational submittals.
b. Government may reject an Informational submittal when submittal does not satisfy contract requirements. Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational submittals are considered to be “shop drawings” within terms of clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractors or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Print Size: ANSI D size (22-inches by 34-inches).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified:
a. Computer drafted drawings:
1) In accordance with NIBS NCS.
2) Electronic file format: Compatible with AutoCAD, Version 2010 or later.
3) Compile using “eTransmit” utility in AUTOCAD.
b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.
5. Drawings Designated as “Government Format” in Specifications:
a. Computer drafted.
b. Government will provide electronic AutoCAD format template.
c. Title block and sheet format:
1) As shown on standard drawing 40-D-60004.
2) Government will supply template.
3) Government will supply specific title block information to be used.
6. Final Drawings:
a. Computer drafted.
b. Government will supply electronic AutoCAD format template.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 3
c. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
7. Electronic Files: On CD or DVD discs.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets:
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf on CD or DVD discs:
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
G. Photographs:
1. Digital files on CD or DVD in .jpeg or similar format.
H. Samples and Color Selection Submittals:
1. Label with complete manufacturer's product and color identification.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 4
2. Include type and quantity of materials specified in the referenced section in each “set” of samples.
3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
4. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.
6. Government will select architectural color and pattern after product approval.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A – List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A – List of Submittals.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28-days after receiving comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21-days for review of each submittal or resubmittal, unless otherwise specified.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 5
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time:
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract.
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR
52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Return of Submittals:
1. Action Submittals: One set of submittals required for action will be returned either approved, approved with comments, or not approved:
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
2. Informational Submittals: Government will acknowledge Informational submittals:
a. Informational submittals will not be returned when they satisfy contract requirements.
b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal or additional information may be requested.
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 6
1.07 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer, Bureau of Reclamation, Attn: UC-840, 125 South State St, Room 6107, Salt Lake City, UT 84138-1147.
2. Construction Engineer, Bureau of Reclamation, 1235 La Plata Hwy, Farmington, NM 87401.
3. Technical Service Center, Bureau of Reclamation, Attn: 86-68510, P.O. Box
25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
B. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A - List of Submittals:
1. Responsible codes starting with “86-6” are located in Technical Service Center.
Send these submittals to TSC address shown above.
C. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code but show “No. of sets to be sent to” in Table 01 33 00A - List of Submittals.
D. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.
E. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to CE unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 7
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
At least 28-days before use of Federal land
A CE CDMS
01 31 19-1 Project Management and Coordination
Written Summary Monthly once on-site construction begins
A CE CDMS
01 31 19-2 Project Management and Coordination
Off ROW Land Use Coordination
At least 4-months prior to use of land
A CE CDMS
01 31 19-3 Project Management and Coordination
Replacement of Key Personnel
At least 48-hours prior to changes
A CE CDMS
01 31 30-1 Contract Document Management System
Approval Data Within 7-days of Award
A CE 0 1 0
01 31 30-2 Contract Document Management System
Final Data Within 14-days of completion of work
A CE 0 2 2
01 32 10-1 Construction Program
Representative Information
Within 7-days after receipt of Notice of Award
I CE CDMS
01 32 10-2 Construction Program
Baseline Schedule Within 21-days after receipt of Notice to Proceed
A CE CDMS
01 32 10-3 Construction Program
Updated Schedule Reports
Monthly or with Progress Payments
A CE CDMS
01 32 10-4 Construction Program
Time Impact Analysis
Within 28-days after CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract
A CE CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 8
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
01 35 10-1 Safety Data Sheets
Complete LHM and SDS
At least 14-days before jobsite delivery of hazardous material
I CE CDMS
01 35 10-2 Safety Data Sheets
Updated LHM and SDS
At least 14-days before jobsite delivery of hazardous material not previously listed
I CE CDMS
01 35 20-1 Safety and Health
Safety Program At least 28-days before beginning onsite work
A CE CDMS
01 35 20-2 Safety and Health
Job Hazard Analyses (JHA) List
At least 28-days before beginning onsite work
A CE CDMS
01 35 20-3 Safety and Health
Monthly Accident Summary Report
First day of each month. See paragraph 3.8 of
RSHS.
A CE CDMS
01 35 20-4 Safety and Health
Documentation and Records
At least 28-days before beginning onsite work
A CE CDMS
01 35 20-5 Safety and Health
Covid-19 Notification
Submitted and accepted within 24-hours
A CE CDMS
01 35 20-6 Safety and Health
Employee Return to Work Documentation
Submitted and accepted within 24-hours
A CE CDMS
01 35 30-1 Contractor’s Onsite Safety Personnel
Resumes Qualifications
At least 14-days before beginning on-site construction
I CE CDMS
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
Once each week I CE CDMS
01 46 00-1 Quality Procedures
Contractor Quality Control Plan (QC)
At least 28-days before beginning onsite work
A CE CDMS
01 46 00-2 Quality Procedures
Contractor’s Daily Report
No later than the end of the following workday
I CE CDMS
01 46 00-3 Quality Procedures
Quality Control Supervisor (QCS) Resume
At least 28-days before beginning onsite work
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 9
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
01 46 00-4 Quality Procedures
Contractor’s Quality Testing Plan
At least 28-days before beginning onsite work
A CE CDMS
01 46 00-5 Quality Procedures
Summary of Monthly Test Results
Monthly with pay request
I CE CDMS
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
At least 42-days before testing is required
A CE CDMS
01 55 00-1 Vehicular Access and Parking
Initial Digital Recording
At least 21-days before beginning on-site work
A CE 0 1 0
01 55 00-2 Vehicular Access and Parking
Post Construction Digital Recording
At least 21-days before leaving site.
A CE 0 1 0
01 55 20-1 Traffic Control Information of Traffic Control Plan (TCP) and Permit Applications
At least 70-days before affecting public traffic
A CE CDMS
01 55 20-2 Traffic Control Approved
NMDOT
Permit(s)
At least 70-days before affecting public traffic
A CE CDMS
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28-days before start of onsite construction work
A CE CDMS
01 56 15-1 Protection of Existing Utilities
Utility Owner Acknowledgment
At least 28-days before start of onsite construction work
A CE CDMS
01 56 15-2 Protection of Existing Utilities
Utility Investigation
At least 28-days prior to submittal of 33 11 10-2 Pipe Laying Diagrams
I CE CDMS
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
At least 14-days before beginning on-site work
I CE CDMS
01 57 30-1 Water Pollution Control
Updated Stormwater Pollution Prevention Plan
(SWPPP)
At least 42-days before start of onsite construction work
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 10
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 42-days before delivery or storage of oil
A CE CDMS
01 57 50-1 Tree and Plant Protection
Protection Plan At least 28-days before beginning on-site work
A CE CDMS
01 57 90-1 Preservation of Historical and Archeological Data
Alternate Use Area or Borrow Area
At least 28-days before commencing on site construction work
01 71 20-1 Surveying Surveying Plan At least 28-days before beginning survey work
A CE CDMS
01 71 20-2 Surveying Resume At least 28-days before beginning survey work; At least 28-days before personnel change
I CE CDMS
01 71 20-3 Surveying Accuracy Check Results
At least 28-days before beginning survey work
I CE CDMS
01 71 20-4 Surveying Completed and Reduced Survey Notes
Within 2-days of completing and reducing notes
I CE CDMS
01 71 20-5 Surveying Original Field Survey Books
Weekly I CE CDMS
01 71 20-6 Surveying Quantity Survey Notes and Computations
Accompanying progress payment requests
I CE CDMS
01 71 20-7 Surveying Workday's Survey Notes
At conclusion of workday if requested by Government
I CE CDMS
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Within 7-days of waste disposal
I CE CDMS
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7-days of hazardous waste disposal
I CE CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 11
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28-days before beginning environmental assessment
I CE CDMS
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14-days of completion of work
I CE CDMS
01 78 30-1 Project Record Documents
As-built Drawings
Within 28-days of Government issued substantial completion of work
A CE
0 1 1
01 78 30-2 Project Record Documents
Final Drawings Within 14-days of approval of RSN 01 78 30-1
A CE CDMS
0 2 0
01 78 30-3 Project Record Documents
O&M Manuals Within 14-days of completion of project
A CE CDMS
0 1 0
03 15 12-1 PVC Waterstop Purchase Orders At least 28-days before placing concrete
A CE CDMS
03 15 12-2 PVC Waterstop Samples At least 28-days before placing concrete
A CE
0 0 1
03 15 12-3 PVC Waterstop Certification At least 28-days before placing concrete
A CE CDMS
03 15 12-4 PVC Waterstop Drawings At least 28-days before placing concrete
A CE CDMS
03 15 12-5 PVC Waterstop Instructions At least 28-days before placing concrete
A CE CDMS
03 15 18-1 Hydrophilic Waterstops
Product Data At least 28-days before placing concrete
A CE CDMS
03 15 18-2 Hydrophilic Waterstops
Certification At least 28-days before placing concrete
A CE CDMS
03 15 18-3 Hydrophilic Waterstops
Instructions At least 28-days before placing concrete
A CE
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 12
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
03 15 18-4 Hydrophilic Waterstops
Samples At least 28-days before placing concrete
A CE
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 28-days before placing concrete
A 86-68530 CDMS
03 30 00-1 Cast-In-Place Concrete
Approval Data At least 42-days before placing concrete
A 86-68530 CDMS
03 30 00-2 Cast-In-Place Concrete
Concrete Placement Schedule
At least 42-days before placing concrete
A CE CDMS
03 30 00-3 Cast-In-Place Concrete
Certifications 42-days before placing concrete
A 86-68530 CDMS
03 30 00-4 Cast-In-Place Concrete
Test Reports Within 7-days of completing tests
A 86-68530 CDMS
03 48 00-1 Plant-Precast Concrete Structures
Certificates At least 28-days before start of onsite construction work
A CE CDMS
03 48 00-2 Plant-Precast Concrete Structures
Shop Drawings Within 2-hours of test results
A TSC
86-68530
CDMS
03 48 00-3 Plant-Precast Concrete Structures
Product Data and Test Reports
At least 28-days before start of onsite construction work
A TSC
86-68530
CDMS
03 48 10-1 Precast Concrete Manholes
Approval Data At least 42-days before installing manholes
A 86-68530 CDMS
03 63 00-1 Epoxy Grout Approval Data At least 42-days before placing grout
A 86-68120 CDMS
03 81 10-1 Concrete Removal
Concrete Removal Plan
At least 42-days before removing concrete
A 86-68530 CDMS
05 50 00-1 Metal Fabrications
Approval Drawings
At least 42-days before beginning work
A 86-68120 CDMS
05 50 00-2 Metal Fabrications
Calculations and Product Data
At least 42-days before beginning work
A 86-68530 CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 13
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
09 96 20-1 Coatings Approval Data At least 42-days before beginning coating work
A 86-68540 CDMS
09 96 20-2 Coatings Final Approval Data
At least 42-days before beginning coating work
A 86-68540 CDMS
09 96 20-3 Coatings Paint Chip Samples
At least 42-days before beginning coating work
A 86-68540 0 1 1
09 96 20-4 Coatings Qualifications At least 42-days before beginning coating work
A 86-68540 CDMS
09 96 20-5 Coatings Quality Control Plan
At least 42-days before beginning coating work
A 86-68540 CDMS
09 96 20-6 Coatings Contractor Quality Testing Report
Weekly A 86-68540 CDMS
10 14 00-1 Signage Shop Drawings and Approval Data
At least 28-days before beginning work
A CE CDMS
10 14 26-1 Utility Markers Utility Marker Plan
At least 42-days before start of construction activities
A CE CDMS
25 00 01-1 Control and Monitoring
Resume - Monitoring and Control Systems Technical Specialist Work Summary
Within 30-days after Notice to Proceed
A 86-68430 CDMS
25 00 01-2 Control and Monitoring
Approval Drawings and Data
Within 150-days after Notice to Proceed, and at least 45-days prior to installation
A 86-68430 CDMS
25 00 01-3 Control and Monitoring
Software Development Documentation
Within 150-days after Notice to Proceed, and at least 45-days prior to installation
A 86-68430 CDMS
https://doimspp.sharepoint.com/sites/bor-FDR-Project-Integration/Shared%20Documents/General/USACE%20Response%20working%20files/DRAFT%20Final%20for%20USACE.docx?web=1
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 14
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
25 00 01-4 Control and Monitoring
Tohlakai Pumping Plant SCADA System Modifications
Within 150-days after Notice to Proceed, and at least 45-days prior to installation
A 86-68430 CDMS
25 00 01-5 Control and Monitoring
Design Coordination Meeting Agenda
Within 30-days after Notice to Proceed
A 86-68430 CDMS
25 00 01-6 Control and Monitoring
Check Prints At same time as equipment is shipped to the site
A 86-68430 CDMS
25 00 01-7 Control and Monitoring
Final Drawings, Documentation, and Operations and Maintenance Manuals
Within 14-days of completion of work
A 86-68430 CDMS
25 08 10-1 Automation System Testing, Acceptance, and Training
SPAT Procedure and Start Date
At least 42-days before beginning test
A 86-68430 CDMS
25 08 10-2 Automation System Testing, Acceptance, and Training
SPAT Test Report Not more than 28-days after test
I 86-68430 CDMS
25 08 10-3 Automation System Testing, Acceptance, and Training
OAT Procedure and Start Date
At least 42-days before beginning test
A 86-68430 CDMS
25 08 10-4 Automation System Testing, Acceptance, and Training
OAT Report Not more than 28-days after test
I 86-68430 CDMS
25 08 10-5 Automation System Testing, Acceptance, and Training
Training Plan No less than 42-days before first commissioning is scheduled to begin
I 86-68430 CDMS
26 05 20-1 Conductors and Cables
Approval Data Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 05 20-2 Conductors and Cables
Field Test Reports Not more than 30-days after test
I 86-68430 CDMS
26 05 26-1 Grounding and Bonding
Test Reports Not more than 30-days after test
I 86-68430 CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 15
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
26 05 33-1 Raceways and Boxes
Approval Drawings and Data
Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 05 33-2 Raceways and Boxes
Approval Drawings for Fiber Optic Cable Raceway and Vault Location
At least 60-days prior to installation
A 86-68430 CDMS
26 05 33-3 Raceways and Boxes
As-Built Drawings and Data
Within 14-days of completion of work
A 86-68430 CDMS
26 21 12-1 Meter Socket Approval Data Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 24 16-1 Panelboard Approval Data Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 24 16-2 Panelboard Approval Drawings
Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 24 16-3 Panelboard Panelboard Schedule and Circuit Directory
Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 27 40-1 Wiring Devices Approval Data Within 42-days after Notice to Proceed
A 86-68430 CDMS
26 42 10-1 Submerged Galvanic Anode Cathodic Protection System for Welded Steel Tanks
Certification and Data
At least 42-days before procuring materials
A 86-68540 CDMS
26 42 10-2 Submerged Galvanic Anode Cathodic Protection System for Welded Steel Tanks
Final Data At least 42-days before procuring materials
A 86-68540 CDMS
26 42 11-1 Submerged Galvanic Anode Cathodic Protection System for Bolted Tanks
Certification, Design, and Manufacturer’s Data
At least 42-days before procuring materials
A 86-68540 CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 16
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
26 42 11-2 Submerged Galvanic Anode Cathodic Protection System for Bolted Tanks
Final Data Within 7-days of final testing
A 86-68540 CDMS
26 42 12-1 Buried Galvanic Cathodic Protection and Corrosion Monitoring Systems
Certification and Data
At least 42-days before procuring materials
A 86-68540 CDMS
26 42 12-2 Buried Galvanic Cathodic Protection and Corrosion Monitoring Systems
Final Data Within 7-days of final testing
A 86-68540 CDMS
31 02 10-1 Water for Dust Abatement
Meter Calibration At least 42-days before beginning onsite work
A CE CDMS
31 02 30-1 Dust Palliative Proposed Application Area for Dust Palliative
At least 42-days before beginning onsite work
A CE CDMS
31 03 33-1 Removal of Water from Excavation
Removal of Water Plan
At least 28-days before beginning onsite work
A CE CDMS
31 23 02-1 Compacting Earth Materials
Test Results Within 7-days after completion of tests
I CE CDMS
31 23 11-1 Earthwork for Structures
Processing Plan for Expansive Soils
At least 42-days before beginning onsite work
A 86-68314 CDMS
31 23 11-2 Earthwork for Structures
Test Results Within 7-days after completion of tests
I 86-68314 CDMS
31 23 22-1 Pipe Trench Earthwork
Cultural Site Trench Box Design
At least 28-days before start of onsite construction work
A CE CDMS
31 23 70-1 Controlled Low Strength Material
(CLSM)
Approval Data for CLSM Produced without Native Soil
At least 42-days before placing
A 86-68530 CDMS
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 17
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
31 23 70-2 Controlled Low Strength Material
(CLSM)
Approval Data for CLSM Produced with Native Soil
Within 7-days of testing
A CE CDMS
31 23 70-3 Controlled Low Strength Material
(CLSM)
Quality Control Test Results
At least 42-days before placing
A CE CDMS
31 24 18-1 Gravel Drain for Black Hat Tank
Laboratory Test Results
At least 42-days before placing
A CE CDMS
31 31 30-1 Soil-Applied Herbicide
Use Plan At least 28-days before placing
A CE CDMS
31 31 30-2 Soil-Applied Herbicide
Applier Certification
At least 28-days prior to beginning work
A CE CDMS
31 32 36-1 HDPE
Geomembrane for Black Hat Tank
Certification At least 28-days prior to beginning work
A CE CDMS
31 32 36-2 HDPE
Geomembrane for Black Hat Tank
Pre-Construction At least 28-days prior to beginning work
A CE CDMS
31 32 36-3 HDPE
Geomembrane for Black Hat Tank
Construction At least 28-days prior to beginning work
A CE CDMS
31 37 00-1 Riprap Approval Data and Test Results
At least 42-days before placing lining
A CE CDMS
32 12 22-1 Asphalt Concrete Pavement
Job Mix Formula
(JMF)
At least 42-days before placing surfacing
A CE CDMS
32 15 10-1 Gravel Surfacing Gravel Certification
At least 14-days before placing surfacing
A CE CDMS
32 15 10-2 Gravel Surfacing Geofabric Installation
At least 42-days before placing surfacing
A CE CDMS
32 15 10-3 Gravel Surfacing Geofabric Certification
At least 42-days before placing surfacing
San Juan Lateral – Navajo Code Talkers Sublateral – Reaches 12.1 & 12.2 Solicitation No. 140R4021R0009
Revised 01 33 00 - 18
Table 01 33 00A – List of Submittals *Submittal Types: A - Action, I - Information **CO indicates Contracting Officer, CE indicates Construction Engineer, and TSC indicates Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No of sets to be sent to **
CO CE TSC
32 31 10-1…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .