140R4021R0009_Clarification_Questions_-_Round__5_2SEP21_0010.docx

DOCX document 69 KB Posted

Attached to
NGWSP NAVAJO CODE TALKERS SUBLATERAL
Solicitation number
140R4021R0009
Issued by

About this file

This document contains clarification questions and responses related to a solicitation for the Navajo-Gallup Water Supply Project Navajo Code Talkers Sublateral Reaches 12.1 & 12.2. The solicitation is seeking construction services for pipeline installation along Reaches 12.1 and 12.2 of the Navajo Code Talkers Sublateral. The responses clarify that the schedule in the solicitation represents the baseline costs for materials that could be subject to economic price adjustments under the contract. They also confirm that fiber optic conduit is to be pulled into the pipeline following horizontal directional drilling but that the fiber optic cable itself will not be installed until afterwards to reduce the risk of damage. The Department of the Interior Bureau of Reclamation is the contracting agency.

View the file

Other files

File Type Posted
Attachment__21_00_00_01_-_Specifications_09012021_0010.pdf PDF
Attachment__22_00_00_02_-_Drawings_09012021_0010.pdf PDF
Sol_140R4021R0009_Amd_0010.pdf PDF
140R4021R0009-0010_Amendment_2SEP21_0010.pdf PDF
Round__4_Attachment_-_KINDER_MORGAN_STIPULATIONS_0009.pdf PDF
Sol_140R4021R0009_Amd_0009.pdf PDF
Sol_140R4021R0009_Amd_0008.pdf PDF
140R4021R0009-0008_Amendment_18AUG21_0008.pdf PDF
Attachment__19_00_00_01_-_Specifications_08162021_0008.pdf PDF
140R4021R0009_Clarification_Questions_-_Round__4_18AUG21_0008.docx DOCX document
Attachment__20_00_00_02_-_Drawings_16AUG21_0008.pdf PDF
Attachment__17_03_00_00_02_Drawings_Revised_0007.pdf PDF
140R4021R0009_Clarification_Questions_-_Round__3_11AUG21_0007.docx DOCX document
Sol_140R4021R0009_Amd_0007.pdf PDF
140R4021R0009-0007_Amendment_11AUG21_0007.pdf PDF
Attachment__18_04_00_00_02A_Dwgs_Geology_0007.pdf PDF
Attachment__16_00_00_01_-_Revised_Specifications_Amd_0007_08092021_0007.pdf PDF
Attachment__14_03_00_00_01_-_Revised_Specifications_FINAL_08-02-21_0006.pdf PDF
140R4021R0009_Clarification_Questions_-_Round__2_3AUG21_0006.docx DOCX document
140R4021R0009-0006_Amendment_3AUG21_0006.pdf PDF
Sol_140R4021R0009_Amd_0006.pdf PDF
Attachment__15_04_00_00_02_-_Revised_Drawings_080221_11x17_0006.pdf PDF
Sol_140R4021R0009_Amd_0005.pdf PDF
140R4021R0009_Clarification_Questions_-_Round__1_28JUL21_0005.docx DOCX document
Sol_140R4021R0009_Amd_0004.pdf PDF
Sol_140R4021R0009_Amd_0003.pdf PDF
Attachment__13_027_1695-D-60129_Rev_4_11x17_07-16-21_0003.pdf PDF
Attachment__12_00_00_01_-_Revised_Specifications_07-16-21_0003.pdf PDF
140R4021R0009-0003_Amendment_19JUL21_0003.pdf PDF
Sol_140R4021R0009_Amd_0002.pdf PDF
Attachment__2_Dwgs_06-16-2021_0001.pdf PDF
Sol_140R4021R0009_Amd_0001.pdf PDF
Attachment__7_WD_NM20210024_(Building).pdf PDF
140R4021R0009_RFP_Code_Talker_24JUN21.pdf PDF
Sol_140R4021R0009.pdf PDF
Attachment__5_00_00_02_Drawings_061-132_11x17_05-17-2021.pdf PDF
Attachment__8_Past_Performance_Questionnaire.pdf PDF
Attachment__10_Key_Personnel_Form.docx DOCX document
Attachment__4_00_00_02_Drawings_001-060_11x17_06-16-2021.pdf PDF
Attachment__6_WD_NM20210011_(Heavy).pdf PDF
Attachment__3_00_00_02A_Drawings_Geology_and_Logs_11x17_09-23-2020.pdf PDF
Attachment__2_Dwgs_06-16-2021.pdf PDF
Attachment__11_Subcontracting_Plan_Template.docx DOCX document
Attachment__9_Experience_Form.docx DOCX document
Attachment__1_00_00_01_-_Specification_06-16-2021.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140R4021R0009 Clarification Questions (Round #5)

1. Section I, I.7 52.216-4 Economic Price Adjustment – Labor and Material, paragraph (a) notes “The Contractor shall notify the Contracting Officer, at any time during contract performance, the rate of pay for labor (including fringe benefits) or the unit prices for material shown in the Schedule either increase or decrease”. In Section L.15 WBR 1452.215-81 Proposal Instructions, Section (m) Volume II, (n) Master Plan 6: Cost/Price, Pricing Proposal, section 4), includes item 8 (page 93 of 101 in RFP) – Unit Price and Basis of Estimate for items that would apply to the Economic Pricing Adjustment (EPA) Clause, to include the breakdown of the schedule B CLIN (e.g., price per linear foot of pipe raw material). Is item 8 as referenced in 1452.215-81 the “Schedule” (emphasis added) referenced in I.7 52.216-4?

Reclamation Response: The schedule is a general reference to schedule B CLINs/items (price schedule) that are also present in FAR Clause 52.216-4. If the material is used in a schedule B CLIN it could be considered under EPA for an adjustment if it met the stipulations in the clause for adjustment. See general list from FAR 52.216-4 from the solicitation below;

1) Concrete

2) Steel

3) Lumber

4) PVC pipe (including HDPE products)

5) Ductile Iron Pipe (DIP).

2. Are the unit costs for materials, turned in as Item 8 in the Cost/Pricing proposal submission, the baseline to be used for determining the EPA in the contract? For clarity, are the material costs that are used to generate the unit prices in schedule B CLIN’s/items the baseline for future EPA?

Reclamation Response: Yes, your proposal price is the baseline. Generally, it is referenced to whatever indices are used to determine the price and see what the index base price was on that date/time period. The calculation is then determined from there. The final details are usually agreed to directly prior to award.

3. Amendment 8, Question 30, the answer states: 2” conduit for fiber optic cable is to be pulled following the HDD installation. This may be a typo and the word should be “with” instead of “following”. If the GOV intends for the 2” conduit to follow the HDD installation, it will mean the work will require a second HDD for the 2” conduit. Please confirm the GOV intentions for this 2” conduit.

Reclamation Response: Fiber optic conduit shall be pulled with the HDD pipe, with a pull-string or other method employed to facilitate installation of the fiber optic cable afterwards. The fiber optic cable shall not be installed during the HDD installation, due to the higher possibility of damage.