This document is a Questions and Answers (Q&A) log for federal solicitation 140P2026R0093 issued by the National Park Service. The Q&A sheet addresses three clarifying questions submitted by potential offerors regarding evaluation criteria and submission requirements.

The responses confirm that: (1) Past Performance Questionnaires (PPQs) from prior federal pursuits are acceptable if they relate to the same projects being submitted and are no more than 12 months old from August 13, 2026; (2) Past Performance information should correspond to project examples submitted under Factor 2 (Technical Qualifications and Specialized Experience), rather than Factor 1 (Technical Approach); and (3) in Section L of the solicitation, Factor 4 is Safety. All three questions were answered in Amendment 2 to the solicitation. The document contains primarily empty rows in the table format, indicating these were the only substantive questions received during the solicitation period.

View the file

Other files

File Type Posted
Sol_140P2026R0093_Amd_0002.pdf PDF
Sol_140P2026R0093_Amd_0001.pdf PDF
B08_140P2026R0093_CUVA_224822_Solicitation_0001.pdf PDF
Sol_140P2026R0093.pdf PDF
03_NPS_Sustainability_Checklist-1.pdf PDF
15_2021_CUVA_MM20_Riverbank_Stab_PermittingAssessment_Form.xlsx XLSX spreadsheet
16_CUVA_WRD-Letter_MM20_SOF_memo_Aug2024.docx DOCX document
28_Wage_Determination_OH20260001.pdf PDF
25_ContractPriceSchedule.xlsx XLSX spreadsheet
01_2_2023_CUVA224822_MM20_BODR_Combined_Redacted1.pdf PDF
03_1_NPS_Sustainability_Checklist-1_Filliable.xlsx XLSX spreadsheet
10_NPS_Clean_Fill_Protocol-1.pdf PDF
17_WSOF_MM20_2024-08-19.docx DOCX document
24_Q_A_Tracker.xlsx XLSX spreadsheet
01_1_2021_CUVA224822_Riverbank_Stab_BODR_Combined.pdf PDF
04_Constructability_Checklist-1.pdf PDF
08_CUVA_Access_and_Staging_Maps_2.pdf PDF
09_CUVA_224822_Permit_Submittal_List.docx DOCX document
11_CUVA_224822_Closeout_OM_Requirements-1.pdf PDF
12_CUVA_224822_SubmittalList_RevEst-1.pdf PDF
14_CUVA224822_MM20_DD_Plan_Set-1.pdf PDF
19__PastPerf.docx DOCX document
20_Project_Experience_Questionnaire.docx DOCX document
21_Bid_Bond.pdf PDF
23_Construction_Contract_Administration.docx DOCX document
26_MM20_POR.pdf PDF
22_General_References.docx DOCX document
05_Division_01_Specifications_Redacted.pdf PDF
06_Division_02_Specifications_Redacted2.pdf PDF
07_2021_CUVA_224822_Survey_-_MM20-1.pdf PDF
13_PEPC_116064_CE_2023_05_22-1.pdf PDF
18__LmtOnSubconRpt.xlsx XLSX spreadsheet
27_CUVA_224822_Riverbank_Stabilization_DB-RFP.pdf PDF
02_CUVA_224822_App_SD_Prefer_Alt_Drawings-MM20-1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solcitation 140P2026R0093

Question No. Sheet or Reference Question Response Amendment

Answered

1 B08 - page 59 of 67

We note that the solicitation states, “If available, offerors may submit completed evaluations from the Contract Performance Assessment Reporting System (CPARS) in lieu of the Past Performance Questionnaire.” For projects where completed Past Performance Questionnaires (PPQs) have already been obtained for prior federal pursuits, will the National Park Service accept those previously completed and signed

PPQs in lieu of the attached Past Performance Questionnaire, provided they relate to the same projects being submitted for this solicitation? Or is it the Government’s expectation that a new questionnaire be completed using the attached form specifically for this procurement?

PPQs from past projects are acceptable as long as they are related to the same project and no more than 12 months old from August 13, 2026. 2

2 B08 - page 59 of 67

Under Factor 3, Past Performance, the solicitation states: "Submit Past Performance information for the same projects submitted under Factor 1 using the attached Past Performance Questionnaire." We noted that Factor 1 addresses the Technical Approach, while Factor 2, Technical Qualifications and Specialized Experience, requests submission of 3–5 relevant project examples. Can the Government confirm whether the

Past Performance Questionnaires should correspond to the project examples submitted under Factor 2 rather than Factor 1?

The Goverment confirms it should be factor 2 2

3 Section L In Section L. It currently has Key Personnel as Factor 4, where in Section M Factor 4 is Safety. Can NPS Confirm factor 4 Section L Factor 4 is Safety 2

Question No. Sheet or Reference Question Response Amendment

Answered

Sheet1

File details come from the government source that posted it. Updated .