This is a Permit Submittal List for the Cuyahoga Valley National Park (CUVA) riverbank stabilization project, identifying all required federal, state, and local permits and their submission requirements. The project, titled "Stabilize Riverbank at High Priority Areas along Towpath Trail and Valley Railway Project," falls within the USACE Buffalo District boundary and requires six permits managed by multiple agencies: the U.S. Army Corps of Engineers (USACE), U.S. Environmental Protection Agency (USEPA), U.S. Coast Guard (USCG), and Ohio EPA.
The permit submittal list details specific requirements for each authorization, with the Contractor responsible for submitting most applications by Winter 2026-2027. Key permits include: CWA Section 404 (wetlands), Section 9 and 10 Waters (riverine structures), Section 401 Water Quality Certification (Ohio EPA), National Pollution Discharge Elimination System General Stormwater Construction Permit (Ohio EPA), and Notice to Mariners (USCG). The National Park Service is designated as the Applicant for several permits. Required documentation includes cover letters, pre-application consultations, permit applications, plan submittals, Stormwater Pollution Prevention Plans, and Notice of Intent forms. Concurrent agency consultations required by Winter 2022-2023 include USFWS Section 7 Consultation, SHPO Section 106 Consultation, and NPS NEPA documentation. Primary contacts include USACE Regulatory at 513-684-6050 and Ohio EPA contacts for specific permit requirements. A pre-application meeting with USACE is suggested prior to formal submission.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Notes: The project is within the USACE Buffalo District boundary.
| Total number of Government Furnished Permit: |
| 0 |
Permit: CWA Section 404
| Agency: |
| USACE,USEPA |
| Number of copies of permit application packet needed: |
| 1 |
Filing Fee:
None
| Forms, Reports and other supporting documents required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Cover letter |
| Contractor |
| Winter 2026-2027 |
| 2) Nationwide Permit Pre-Construction Notification |
| Contractor |
| Winter 2026-2027 |
| 3) Individual Permit Application Form |
| Contractor |
| Winter 2026-2027 |
| 4) Plan Submittal |
| Contractor |
| Winter 2026-2027 |
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)
15)
| Concurrence letters from other agencies needed: |
| Responsible Party |
| Fin Date / Done? |
| 1) USFWS - Section 7 Consultation |
| NPS |
| Winter 2022-2023 |
| 2) SHPO - Section 106 Consultation |
| NPS |
| Winter 2022-2023 |
| 3) NPS - NEPA |
| NPS |
| Winter 2022-2023 |
| 4) Ohio EPA 401 Water Quality Certification |
| Contractor |
| Winter 2026-2027 |
5)
| Application(s) of other concurrently applied for permits required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Section 9 and 10 Waters |
| Contractor |
| Winter 2026-2027 |
2)
3)
4)
5)
Notes:
A request for a pre-application meeting is suggested.
Application Form 4345 or 6082 - Check with USACE Regulatory prior to submittal. Section 9/10 Waters authorization would occur concurrently. Applicant will be NPS.
Contact information: 513-684-6050; LRB.Ohio.RegActions@usace.army.mil. Documentation of NEPA compliance would be needed for Individual Permits.
An individual Section 401 Water Quality Certification would be needed if an individual Section 404 Permit is needed.
CUVA - Stabilize Riverbank at High Priority Areas along Towpath Trail and Valley Railway Project Permit Submittal List
National Park Service - Denver Service Center Permit Submittal List FORM, 12-2-16 | page 1 of 5
Permit: USACE, USCG
| Agency: |
| Section 9 and 10 Waters |
| Number of copies of permit application packet needed: |
| 1 |
Filing Fee:
| Forms, Reports and other supporting documents required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Cover letter |
| Contractor |
| Winter 2026-2027 |
| 2) Pre-Application Consultation |
| Contractor |
| Winter 2026-2027 |
| 3) Permit Application |
| Contractor |
| Winter 2026-2027 |
| 4) CZMA consistency determination |
| Contractor |
| Winter 2026-2027 |
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)
15)
| Concurrence letters from other agencies needed: |
| Responsible Party |
| Fin Date / Done? |
| 1) USFWS - Section 7 Consultation |
| NPS |
| Winter 2022-2023 |
| 2) SHPO - Section 106 Consultation |
| NPS |
| Winter 2022-2023 |
| 3) NPS - NEPA |
| NPS |
| Winter 2022-2023 |
| 4) Ohio EPA 401 Water Quality Certification |
| Contractor |
| Winter 2026-2027 |
5)
| Application(s) of other concurrently applied for permits required: |
| Responsible Party |
| Fin Date / Done? |
| 1) CWA Section 404 Permit |
| Contractor |
| Winter 2026-2027 |
2)
3)
4)
5)
Notes:
Contact information: 513-684-6050; LRB.Ohio.RegActions@usace.army.mil. Applicant will be NPS.
Permit: Section 401 Water Quality Certification
| Agency: |
| Ohio EPA |
| Number of copies of permit application packet needed: |
| 1 |
Filing Fee:
| Forms, Reports and other supporting documents required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Cover letter |
| Contractor |
| Winter 2026-2027 |
| 2) Pre-Certification Request |
| Contractor |
| Winter 2026-2027 |
| 3) Application/Formal request for certification |
| Contractor |
| Winter 2026-2027 |
4)
5)
6)
7)
8)
| Concurrence letters from other agencies needed: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
| Application(s) of other concurrently applied for permits required: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
Notes:
An individual Section 401 Water Quality Certification from Ohio EPA will be needed. An application form per ORC section 6111.30(A) will be needed and all requirements of the Clean Water Act Section 401 Certification Rule followed.
Contacts: Melanie Barbis, 330-963-1251; melanie.barbis@epa.ohio.go Applicant will be NPS.
Permit: Notice to Mariners
| Agency: |
| USCG |
| Number of copies of permit application packet needed: |
| 1 |
Filing Fee:
| Forms, Reports and other supporting documents required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Cover letter |
| Contractor |
| Fall 2026 |
| 2) Submittal of information to USCG District Office |
| Contractor |
| Fall 2026 |
3)
4)
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)
15)
| Concurrence letters from other agencies needed: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
| Application(s) of other concurrently applied for permits required: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
Notes:
Contact information - 614-540-7700
Permit: National Pollution Discharge Elimination System General Stormwater Construction Permit
| Agency: |
| Ohio EPA |
| Number of copies of permit application packet needed: |
| 1 |
Filing Fee:
| Forms, Reports and other supporting documents required: |
| Responsible Party |
| Fin Date / Done? |
| 1) Cover letter |
| Contractor |
| Fall 2026 |
| 2) Storm Water Pollution Prevention Plan |
| Contractor |
| Fall 2026 |
| 3) Notice of Intent |
| Contractor |
| Fall 2026 |
4)
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)
15)
| Concurrence letters from other agencies needed: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
| Application(s) of other concurrently applied for permits required: |
| Responsible Party |
| Fin Date / Done? |
1)
2)
3)
4)
5)
Notes:
If project disturbs 1 acre or more of ground, a construction storm water permit is needed. A stormwater pollution prevention plan and NOI would be needed. Each project site may be considered single and complete actions, or, if the projects are let together, may be classified as one action.
Submittal is made via Ohio EPA online STREAMS
Contact information: Michael Joseph, 614-752-0782; Michael.Joseph@epa.ohio.gov
File details come from the government source that posted it. Updated .