This is an NPS Constructability Checklist for the Stabilize Riverbank at MM20 project at Cuyahoga Valley National Park (PMIS CUVA 224822), dated March 18, 2026, completed using a Design-Build (DB) contract delivery method. The project involves riverbank stabilization work using both bioengineering and structural measures, including riprap placement, streambank stabilization, and vegetative treatments. The construction schedule is 730 calendar days and accounts for anticipated winter shutdown periods due to the project's location in northern Ohio and seasonal in-river work restrictions.

The checklist identifies multiple permitting and compliance requirements administered by federal and state agencies, including USACE Section 404/9/10 permits (513-684-6050), Ohio EPA 401 Water Quality Certification (330-963-1251), FEMA/Local Floodplain approval, USCG Notice to Mariners, and Ohio EPA General Construction Stormwater Permit. Environmental constraints include tree removal restrictions (October 15 to March 31) and Indiana bat habitat protections (November 15 to March 15 depending on location). The project requires archeological monitoring during construction at Towpath MM 20 South, NEPA compliance through Categorical Exclusion, and Section 106 consultation with SHPO. Critical construction considerations include trail closures, coordination with the Cuyahoga Valley Scenic Railroad, staging area finalization, utility coordination (particularly relocation of a fiberoptic line), material submittal approvals, and long-term maintenance planning for vegetative components with documented survival and growth period requirements.

View the file

Other files

File Type Posted
Sol_140P2026R0093_Amd_0002.pdf PDF
QA_Tracker_8_5_26_0002.pdf PDF
Sol_140P2026R0093_Amd_0001.pdf PDF
B08_140P2026R0093_CUVA_224822_Solicitation_0001.pdf PDF
25_ContractPriceSchedule.xlsx XLSX spreadsheet
01_2_2023_CUVA224822_MM20_BODR_Combined_Redacted1.pdf PDF
03_1_NPS_Sustainability_Checklist-1_Filliable.xlsx XLSX spreadsheet
10_NPS_Clean_Fill_Protocol-1.pdf PDF
17_WSOF_MM20_2024-08-19.docx DOCX document
24_Q_A_Tracker.xlsx XLSX spreadsheet
Sol_140P2026R0093.pdf PDF
03_NPS_Sustainability_Checklist-1.pdf PDF
15_2021_CUVA_MM20_Riverbank_Stab_PermittingAssessment_Form.xlsx XLSX spreadsheet
16_CUVA_WRD-Letter_MM20_SOF_memo_Aug2024.docx DOCX document
28_Wage_Determination_OH20260001.pdf PDF
01_1_2021_CUVA224822_Riverbank_Stab_BODR_Combined.pdf PDF
08_CUVA_Access_and_Staging_Maps_2.pdf PDF
09_CUVA_224822_Permit_Submittal_List.docx DOCX document
11_CUVA_224822_Closeout_OM_Requirements-1.pdf PDF
12_CUVA_224822_SubmittalList_RevEst-1.pdf PDF
14_CUVA224822_MM20_DD_Plan_Set-1.pdf PDF
19__PastPerf.docx DOCX document
20_Project_Experience_Questionnaire.docx DOCX document
21_Bid_Bond.pdf PDF
23_Construction_Contract_Administration.docx DOCX document
26_MM20_POR.pdf PDF
22_General_References.docx DOCX document
05_Division_01_Specifications_Redacted.pdf PDF
06_Division_02_Specifications_Redacted2.pdf PDF
07_2021_CUVA_224822_Survey_-_MM20-1.pdf PDF
13_PEPC_116064_CE_2023_05_22-1.pdf PDF
18__LmtOnSubconRpt.xlsx XLSX spreadsheet
27_CUVA_224822_Riverbank_Stabilization_DB-RFP.pdf PDF
02_CUVA_224822_App_SD_Prefer_Alt_Drawings-MM20-1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NPS Constructability Checklist National Park Service (NPS) - Denver Service Center (DSC) | 3-20-18

For instructions, see Instructions tab below.

Date: 3/18/2026 Project Title: Stabilize Riverbank at MM20 Park: Cuyahoga Valley Completed By: JDM

PMIS:

(Project Management

Information System)

CUVA 224822

DBB or DB:

(Design-Bid-Build

OR Design-Build)

DB

Item Number Project Issues SD Comments Schematic Design

DD or RFP Comments Design Development (DBB)

OR Request for Proposal (DB)

CD or RFP Resolution Construction Documents (DBB)

OR Request for Proposal (RFP)

PROJECT INTRODUCTION

ANY NON-TYPICAL CONTRACT LINE ITEMS OR

MISCELLANEOUS CONTRACT CONCERNS

Potential warranty on vegetative components of bank stabilization.

Information for any required warranties on vegetative components must be included in specifications.

Time periods pertaining to vegetation condition and survival are documented in Specification 32

92 00 Seeding, Sodding and Landscaping. This

Specification needs to be coordinated with

Specification 01 67 00 to be finalized between

NPS and Contractor.

RECOMMENDED CONTRACT LENGTH; SEASONAL

BREAKS IN CONTRACT; IDENTIFY CONTRACT TIMING

ISSUES THAT NEED TO BE ADDRESSED; IDENTIFY

SPECIFIC PHASING REQUIREMENTS

Contract length needs to account for seasonality of in-river work.

Construction period needs to account for anticipated winter shutdown periods.

Winter shutdown periods accounted for in 730 calendar day construction schedule (see RFP

Section 1.6 Schedule).

PERMITTING & COMPLIANCE

External Permit or Approval

LIST REQUIRED GOVERNMENT FURNISHED PERMITS

AND APPROVALS: List by Agency-Type: Example: USACE-

CWA404 NWP18. Include contact, and phone number.

- USACE CWA Section 404, Section 9 and 10;

513-684-6050

- FEMA/Local Floodplain, ohioma@dps.ohio.gov

- Ohio EPA 401 Water Quality Certification, 330-

963-1251

- USCG Notice to Mariners, 614-540-7700

- Ohio EPA General Construction Stormwater

Permit, 614-752-0782

Evaluated required permits and assign to

Government and Contractor. See Items 4 & 5.

See Items 4 & 5.

External Permit or Approval

LIST REQUIREMENTS FOR GOVERNMENT FURNISHED

PERMITS: Include inspections, meetings, close out requirements, and drawings.

Permitting and associated consultation has not been initiated. However, expected conditions may include:

- Tree removal shall only occur between October

15 and March 31.

- SWPPP compliance inspections.

Anticipated conditions for the USACE CWA

Section 404 permit have been identified.

Anticipated conditions for Government furnished permits are documented in RFP Section 2.3.1.

External Permit or Approval

LIST REQUIRED CONSTRUCTION CONTRACTOR

FURNISHED PERMITS AND APPROVALS

To be completed as part of Permit List.

USCG Notice to Mariners, 614-540-7700

Ohio EPA General Construction Stormwater

Permit, 614-752-0782

Contractor furnished permit requirements are documented in RFP Section 2.3.1

External Permit or Approval

DESCRIBE WHERE AND HOW PERMIT REQUIREMENTS

ARE INCLUDED IN DESIGN PACKAGE: For each permit, describe requirement, specification (section and paragraph) and/or drawing number.

It is anticipated that permit requirements will be addressed in specifications in the DD phase.

Multiple permits are required.

Design-Build Contractor-Furnished permits are addressed in RFP Section 2.2.3.

Internal Compliance

IDENTIFY COMPLIANCE REQUIREMENTS:

SHPO, NEPA, EA: List requirement, status, and date or expected date.

Pre-NEPA in progress. Completion of Pre-NEPA is anticipated in December 2021.

NEPA - Decision on NEPA pathway will be made by NPS.

Section 106 - To be completed as part of NEPA compliance (June 2022).

Section 7 Compliance - To be completed as part of NEPA compliance (June 2022).

NPS identified NEPA pathway as a Categorical

Exclusion.

Additional Compliance activities are in progress.

The Proposed Action is categorically excluded from further documentation under NEPA in accordance with 43 CFR 1508.4.

RFP Section 1.8 indicates that the Categorical

Exclusion will be provided to the Design-Build

Contractor upon completion.

Compliance requirements are documented in

RFP Section 2.3.1.

Internal Compliance

COMPLETE ALL APPROVALS: Director's, DAB, Congressional Funding issues, estimate within available funds? Adequate time to complete work within project and funding constraints?

NPS 77-1 and 77-2 - Statement of Findings to be completed following Pre-NEPA development

(February 2022).

Project is in compliance with both NPS 77-1 and

NPS 77-2 as documented in the Categorical

Exclusion (draft). The project is exempt from a

Statement of Findings.

No Further Action Required.

General

IDENTIFY REQUIRED SPECIAL INSPECTIONS: List inspecting or approving organization and reason required.

None identified as part of PAF. Not Applicable. Not Applicable.

STAGING AND MOBILIZATION

IDENTIFY AREAS FOR STAGING INCLUDING AREAS FOR

PRIME, SUBS, MATERIAL, AND PARKING; IDENTIFY

AREAS FOR CONSTRUCTION CAMP IF APPLICABLE:

List drawing number(s) showing staging area(s).

Preliminary staging areas have been identified and are being investigated under the compliance task order.

Staging areas must be finalized and communicated to Contractor.

Access and Staging Maps are included in the

RFP Attachments (RFP Section 5.0).

IDENTIFY TEMPORARY UTILITIES AVAILABLE FOR

CONSTRUCTION: List drawing number or specification section that identifies available utilities-electrical, phone, non-potable and potable water, sanitary-provider, meter needed, and responsible cost party.

Utilities per one-call shown on Schematic Design drawings.

Availability of temporary utilities needs to be communicated to the Contractor for possible

Field Office.

Temporary utilities are addressed in RFP Section

2.3.9. Specification Section 01 50 00 to be

finalized between NPS and the Contractor needs to be coordinated with RFP Section 2.3.9.

IDENTIFY CONSTRUCTION LOGISTICS: List drawing numbers that show traffic control, access restrictions, work hour restrictions, bridges, features, other.

Trail closure signage will be required. CVSR track access coordination will be required.

Otherwise, traffic control and other related needs are limited and are not shown in the Schematic

Design drawings. Work hours are anticipated to be limited to 8 AM to 5 PM.

Construction coordination requirements and limitations associated with trails and the scenic railroad need to be communicated to the

Contractor.

Trail closure and track access coordination requirements are addressed in RFP Section 2.3.1

Environmental and Sustainability Requirements and Section 2.3.10 Access.

IDENTIFY IMPACTS TO PARK AND VISITOR

OPERATIONS: List drawing number(s) or specification section(s) that identifies impacts (e.g. Visitor Impacts, Neighborhood-Urban Impacts, Detours, Closures).

Visitor impacts limited to temporary trail closures.

Not included in Schematic Design drawings.

To be developed and analyzed as part of Pre-

NEPA activities.

Construction coordination requirements and limitations associated with trails and the scenic railroad need to be communicated to the

Contractor.

Trail closure and track access coordination requirements are addressed in RFP Section 2.3.1

Environmental and Sustainability Requirements and Section 2.3.10 Access.

IDENTIFY SITE ACCESS ISSUES: List drawing number(s) or specification section(s) that identify issues (e.g. remote and road type constrained sites, weather closure restrictions, road and bridge load limits, road and tunnel height restrictions, crane and helicopter requirements).

Not included in Schematic Design drawings.

Staging areas must be finalized and communicated to Contractor.

Access and Staging Maps are included in the

RFP Attachments (RFP Section 5.0).

SUBMITTALS

LIST MATERIAL SUBMITTALS ON CRITICAL PATH;

FOR DESIGN-BUILD (DB), LIST MATERIAL SUBMITTALS

REQUIRING GOVERNMENT APPROVAL

None identified. Material submittals need to be identified.

As documented in RFP Section 2.3.4, Contractor is to complete the NPS Submittal List and

Review Estimate Template. Submittal procedures should be coordinated with

Specification Section 01 33 23 Submittal

Procedures and Section 01 67 00 Product

Requirements, to be finalized between NPS and

Contractor.

NPS Constructability Checklist, 3-20-18 | page 1 of 3

Item Number Project Issues SD Comments Schematic Design

DD or RFP Comments Design Development (DBB)

OR Request for Proposal (DB)

CD or RFP Resolution Construction Documents (DBB)

OR Request for Proposal (RFP)

LIST LONG LEAD ITEMS; MATERIAL AND EQUIPMENT

AVAILABILITY CONCERNS, SPECIAL DELIVERY

REQUIREMENTS

Current volatility in the steel market could lead to delays in obtaining steel beams for the soldier pile and lagging wall at the Peninsula site.

Ongoing market volatility could lead to delays in obtaining steel beams for the soldier pile and lagging wall at the Peninsula site.

Contractor is responsible for products and materials. Specification Section 01 67 00 to be finalized between NPS and Contractor.

LIST OF SOLE SOURCE MATERIALS AND GOVERNMENT

FURNISHED MATERIALS OR EQUIPMENT

Not applicable. Not Applicable. Not Applicable.

SITE LAYOUT / RESOURCE PROTECTION

TYPES OF RESOURCE PROTECTION REQUIRED: List where and how requirements are included in design package.

Resource protection to be identified during pre-

NEPA activities as part of compliance task order.

To be included in specifications in DD phase.

Through NEPA activities several Park-specific resource protection needs have been identified.

Resource protection needs are documented in

RFP Section 2.3.1 Environmental and

Sustainability Requirements.

19 ACCURATE SURVEY DATA ON PLANS: BMs, TBMs, TOPO

Surveyed topography shown on Site Plan sheets

(Sheets C3, C7, C11, C13, C15, C17). Survey file states: “Coordinate System: Observations made with Ohio Department of Transportation virtual reference system to the Ohio State Plane

Coordinate System North Zone, NAD83 (2011) &

NAVD88 Datum between March 18 & April 1, 2021.”

Ongoing river erosion and geomorphological processes may result in changed conditions since

PD/SD survey was performed.

Per RFP Section 2.1.1 Scope of Work and

Project Summary/Requirements, Contractor is to perform and provide survey to confirm site conditions. See also Specification Section 02 21

13 Site Surveys.

Per RFP Section 2.3.17, all AutoCAD files are to be provided per Ohio State Plane Coordinate

System North Zone, NAD83 (2011) & NAVD88

Vertical Datum.

PRELIMINARY SITE INVESTIGATION COMPLETE,

EXISTING CONDITIONS VERIFIED AND INCLUDED IN

PACKAGE

Site reconnaissance was performed February 23-

24, 2021. The geotechnical exploration program was performed March 15-19, 2021. Investigation findings incorporated into Schematic Design submittal.

Not Applicable. Not Applicable.

CONSTRUCTION LIMITS CLEARLY SHOWN AND

DEFINED FOR BOTH ACCESS AND CONSTRUCTION: List where and how requirements are included in design package.

Schematic design-level construction limits shown on Site Plan sheets (Sheets C3, C7, C11, C13, C15, C17). Preliminary staging and access areas have been identified and are being investigated under the compliance task order.

Staging areas must be finalized and communicated to Contractor.

Access and Staging Maps are included in the

RFP Attachments (RFP Section 5.0).

SPECIAL SIGNAGE REQUIREMENTS: Describe and list where requirements are included in design package.

Trail closure signage will be required. It is anticipated that signage requirements will be addressed in specifications in the DD phase.

Temporary trail closures required for construction activities and public safety.

Specification Section 01 50 00 Temporary

Facilities and Controls to be finalized between

NPS and Contractor.

LIST WORK SAFETY CONCERNS, LOCATION, AND

NEEDS: Include Height, Weather, Animal, Aerial, Public

Accessibility, Security, Confined Space, Pathologic, Atmospheric, and others.

Weather, steep slopes (fall hazards), and riverine environment work conditions are concerns at all sites. Public accessibility and trail user safety is a concern at all Towpath sites and the Peninsula

Connector site. Track safety and access are concerns for CVSR site work.

Weather, steep slopes (fall hazards), and riverine environment work conditions are concerns at all sites. Public accessibility and trail user safety is a concern at all Towpath sites and the Peninsula

Connector site. Track safety and access are concerns for CVSR site work.

As documented in RFP Section 2.3.15

Temporary Controls, Contractor is responsible for safety, including safety specific to the riverine work environment and winter weather conditions.

Additionally, Specification Section 01 50 00

Temporary Facilities and Controls applies and is to be finalized between NPS and Contractor.

DEMOLITION

ALL EXISTING UTILITIES LOCATED AND ACCURATELY

SHOWN: Describe where shown.

Towpath MM 20 South utilities shown on Sheet

C15. Peninsula Connector utilities shown on

Sheet C17. No utilities identified at remaining

Towpath sites.

Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by

Contractor.

Contractor required to contact Ohio Utilities

Protection Service (OHIO811) per Specification

Section 02 21 13 Site Surveys.

TEMPORARY SYSTEMS REQUIRED: Identify for Park or

Public: Access, power, water, sanitary, covered access, exhibit relocation, movement assistance, accessibility.

No required temporary systems identified. Not Applicable. Not Applicable.

SALVAGE, RECYCLING, STORAGE, AND DISPOSAL

REQUIREMENTS: Who is removing salvageable equipment and where requirements are included in design package?

Not applicable (no salvageable equipment). Not Applicable. Not Applicable.

NOISE / DUST / SAFETY CONCERNS FOR PUBLIC OR

ENVIRONMENT: Describe where included in design package.

It is anticipated that noise / dust / safety requirements will be addressed in specifications in the DD phase.

Noise and dust are expected incidentals to project construction.

Noise and dust requirements are included in

Section 01 57 19.12 Noise and Acoustics

Management, and will be finalized between NPS and Contractor.

CONSTRAINTS ON MEANS AND METHODS: Blasting, Burning, Tidal, Weather, Public Accessibility, Existing structures/features, Holidays and Seasonal, Permitting, other.

Tree removal shall only occur between October

15 and March 31. Additional permitting and Park-specific constraints to be identified during DD phase.

Environmental constraints such as tree cutting and species habitat have been identified in the

Categorical Exclusion.

For project areas affecting Indiana bat swarming habitat (near hibernacula), only cut trees between

November 15 and March 15. For project areas affecting the species' summer habitat between

October 15 and March 15. Known requirements such as tree removal and bat restrictions are documented in RFP Section 2.3.1.

HAZARDOUS MATERIAL CONSIDERATIONS DEMO

METHODS AND DISPOSAL STATE AND LOCAL

REQUIREMENTS: Describe hazardous materials being addressed, how, and where in design package.

None identified. Not Applicable. Not Applicable.

ARCHEOLOGICAL MONITORING REQUIREMENTS:

Describe what is needed and where in design package.

Identify who provides monitor.

To be determined during NEPA activities as part of Section 106 Consultation.

NPS to consult with SHPO and complete archeologic surveys as needed within the Area of

Potential Effect, and regarding potential temporary impacts to archeological sites within the Project Area.

Archeological monitoring is required during construction at Towpath MM 20 South.

Specification Section 01 35 13.22 Archeological

Protection and Section 01 35 91 Historic

Preservation Treatment Procedures are applicable, and will be finalized between NPS and Contractor.

CONSTRUCTION

MATERIAL, EQUIPMENT, LABOR AVAILABILITY FOR

REMOTE SITES: Describe issues and where included in design package.

While there may be some difficulty in accessing the individual sites, CUVA is located in close proximity to two metropolitan areas. There should not be any issues related to material, equipment or labor.

Not Applicable. Not Applicable.

SITE ACCESS RESTRICTIONS TO CONSTRUCTION

OPERATIONS IF DIFFERENT OR MORE SUBSTANTIAL

THAN ITEMS 12 AND 14

No additional restrictions identified. Not Applicable. Not Applicable.

ANTICIPATED WEATHER CONSIDERATIONS,

CONSTRUCTION SEASON, OPTIMUM TIME TO

ADVERTISE, RECOMMENDED CONTRACT LENGTH

A winter shutdown is anticipated given the project's location in northern Ohio. Timing and duration need to consider placing/planting of vegetative treatments.

Construction period needs to account for anticipated winter shutdown periods.

Winter shutdown periods accounted for in 730 calendar day construction schedule (see RFP

Section 1.6 Schedule).

PARK / CONCESSION IMPOSED RESTRICTIONS

INCLUDED IN DESIGN PACKAGE AND IMPACTS ON

SCHEDULE & COST

No additional restrictions identified. Not Applicable. Not Applicable.

DESCRIBE FULL SCOPE OF WORK FOR LOCAL UTILITY

COMPANIES AND CONSTRUCTION CONTRACTOR FOR

EACH UTILITY

Exposed fiberoptic line at MM 20 South will need to be relocated; instruction to be developed during DD phase. Contractor to confirm location and utility protection needs. Specifications to be developed in DD phase.

Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by

Contractor.

Utility disruption requirements are addressed in

Specification Section 01 50 00 Temporary

Facilities and Controls, and will be finalized between NPS and Contractor.

Contractor required to contact Ohio Utilities

Protection Service (OHIO811) per Specification

Section 02 21 13 Site Surveys.

NPS Constructability Checklist, 3-20-18 | page 2 of 3

Item Number Project Issues SD Comments Schematic Design

DD or RFP Comments Design Development (DBB)

OR Request for Proposal (DB)

CD or RFP Resolution Construction Documents (DBB)

OR Request for Proposal (RFP)

DESCRIBE DISRUPTION REQUIREMENTS FOR UTILITY

CONNECTIONS, CLOSURES, AND MAXIMUM

ALLOWABLE INTERRUPTIONS: Describe where addressed in design package.

To be addressed in DD phase.

Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by

Contractor.

Utility disruption requirements are addressed in

Specification Section 01 50 00 Temporary

Facilities and Controls, and will be finalized between NPS and Contractor.

Contractor required to contact Ohio Utilities

Protection Service (OHIO811) per Specification

Section 02 21 13 Site Surveys.

SPECIFIC PHASING REQUIREMENTS: Detail what and where provided in design package.

Specific phasing not identified for Schematic

Design. Recommend constructing from upstream to downstream for sites in close proximity. Also, within each stabilization site work shall be performed from upstream to downstream.

Construction of tightly spaced sites should be constructed from upstream to downstream to reduce potential impacts from downstream disturbance.

Phasing requirements are included in RFP

Section 2.3.3 Construction Support.

DESCRIBE SPECIALIZED MATERIALS/INSTALLATION

METHODS CERTIFICATIONS/TRAINING REQUIREMENTS;

DETAIL GOVERNMENT REQUIRED SPECIALTY

SERVICES OR INSPECTIONS: List requirements.

None identified. Not Applicable. Not Applicable.

COORDINATION WITH PARK OR CONCESSIONAIRE ON

BENEFICIAL OCCUPANCY: Grand opening, fixed completion dates, etc.

No specific coordination needs identified. Not Applicable. Not Applicable.

ADJACENT or CONCURRENT CONTRACTS

COORDINATION / OVERLAPS ON CONCURRENT OR

FUTURE CONTRACTS

USACE Buffalo District river system enhancement projects have been identified by

NPS staff. The first project is between Boston

Mills Road and Vaughn Road and is anticipated to add 2-3 meander bends (bid Fall 2021/Winter

2022; construction Summer 2022). The second project is between Vaughn Road and Station

Road and is anticipated to include repairs due to the river lowering associated with the Brecksville

Dam removal. Future riverbank stabilization work anticipated at Switch 2 (upstream of Fitzwater site).

Not Applicable. Not Applicable.

41 VALUE ENGINEERING POTENTIAL None identified. Not Applicable. Not Applicable.

PROJECT CLOSEOUT

TRAINING REQUIREMENTS, CERTIFICATIONS

SPECIFIED

None identified. Not Applicable. Not Applicable.

43 OPERATION & MAINTENANCE (O&M) REQUIREMENTS

Growth period maintenance required for bioengineering measures. Periodic inspection and maintenance required for structural measures (i.e., wall at Peninsula).

Information for any required warranties on vegetative components must be included in specifications.

Time periods pertaining to vegetation condition and survival are documented in Specification 32

92 00 Seeding, Sodding and Landscaping. This

Specification needs to be coordinated with

Specification 01 67 00 to be finalized between

NPS and Contractor.

LIST PERMITS NEEDING CLOSURE AND POINTS OF

CONTACT: Describe requirement; include specification and/or drawing location for each.

To be determined following initiation of permitting.

See Items 5 and 7. See Items 5 and 7.

45 POST CONSTRUCTION REQUIREMENTS See Item 43 and 46. See Items 43 and 46. See Items 43 and 46.

LIST LONG TERM MAINTENANCE NEEDS AND LOCATION

IN THE DESIGN PACKAGE.

Replace riprap and streambank stabilization measures as needed. Seal concrete facing and cleanout wall drain pipes during scheduled maintenance.

Bioengineering and structural measures will require operation and maintenance plans.

Contractor required to prepare and submit

Operations & Maintenance data as described in

RFP Section 2.3.17 Project Close-out.

NPS Constructability Checklist, 3-20-18 | page 3 of 3