04_Constructability_Checklist-1.pdf
PDF 135 KB Posted
- Attached to
- CUVA 224822
- Solicitation number
- 140P2026R0093
About this file
This is an NPS Constructability Checklist for the Stabilize Riverbank at MM20 project at Cuyahoga Valley National Park (PMIS CUVA 224822), dated March 18, 2026, completed using a Design-Build (DB) contract delivery method. The project involves riverbank stabilization work using both bioengineering and structural measures, including riprap placement, streambank stabilization, and vegetative treatments. The construction schedule is 730 calendar days and accounts for anticipated winter shutdown periods due to the project's location in northern Ohio and seasonal in-river work restrictions.
The checklist identifies multiple permitting and compliance requirements administered by federal and state agencies, including USACE Section 404/9/10 permits (513-684-6050), Ohio EPA 401 Water Quality Certification (330-963-1251), FEMA/Local Floodplain approval, USCG Notice to Mariners, and Ohio EPA General Construction Stormwater Permit. Environmental constraints include tree removal restrictions (October 15 to March 31) and Indiana bat habitat protections (November 15 to March 15 depending on location). The project requires archeological monitoring during construction at Towpath MM 20 South, NEPA compliance through Categorical Exclusion, and Section 106 consultation with SHPO. Critical construction considerations include trail closures, coordination with the Cuyahoga Valley Scenic Railroad, staging area finalization, utility coordination (particularly relocation of a fiberoptic line), material submittal approvals, and long-term maintenance planning for vegetative components with documented survival and growth period requirements.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NPS Constructability Checklist National Park Service (NPS) - Denver Service Center (DSC) | 3-20-18
For instructions, see Instructions tab below.
Date: 3/18/2026 Project Title: Stabilize Riverbank at MM20 Park: Cuyahoga Valley Completed By: JDM
PMIS:
(Project Management
Information System)
CUVA 224822
DBB or DB:
(Design-Bid-Build
OR Design-Build)
DB
Item Number Project Issues SD Comments Schematic Design
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
PROJECT INTRODUCTION
ANY NON-TYPICAL CONTRACT LINE ITEMS OR
MISCELLANEOUS CONTRACT CONCERNS
Potential warranty on vegetative components of bank stabilization.
Information for any required warranties on vegetative components must be included in specifications.
Time periods pertaining to vegetation condition and survival are documented in Specification 32
92 00 Seeding, Sodding and Landscaping. This
Specification needs to be coordinated with
Specification 01 67 00 to be finalized between
NPS and Contractor.
RECOMMENDED CONTRACT LENGTH; SEASONAL
BREAKS IN CONTRACT; IDENTIFY CONTRACT TIMING
ISSUES THAT NEED TO BE ADDRESSED; IDENTIFY
SPECIFIC PHASING REQUIREMENTS
Contract length needs to account for seasonality of in-river work.
Construction period needs to account for anticipated winter shutdown periods.
Winter shutdown periods accounted for in 730 calendar day construction schedule (see RFP
Section 1.6 Schedule).
PERMITTING & COMPLIANCE
External Permit or Approval
LIST REQUIRED GOVERNMENT FURNISHED PERMITS
AND APPROVALS: List by Agency-Type: Example: USACE-
CWA404 NWP18. Include contact, and phone number.
- USACE CWA Section 404, Section 9 and 10;
513-684-6050
- FEMA/Local Floodplain, ohioma@dps.ohio.gov
- Ohio EPA 401 Water Quality Certification, 330-
963-1251
- USCG Notice to Mariners, 614-540-7700
- Ohio EPA General Construction Stormwater
Permit, 614-752-0782
Evaluated required permits and assign to
Government and Contractor. See Items 4 & 5.
See Items 4 & 5.
External Permit or Approval
LIST REQUIREMENTS FOR GOVERNMENT FURNISHED
PERMITS: Include inspections, meetings, close out requirements, and drawings.
Permitting and associated consultation has not been initiated. However, expected conditions may include:
- Tree removal shall only occur between October
15 and March 31.
- SWPPP compliance inspections.
Anticipated conditions for the USACE CWA
Section 404 permit have been identified.
Anticipated conditions for Government furnished permits are documented in RFP Section 2.3.1.
External Permit or Approval
LIST REQUIRED CONSTRUCTION CONTRACTOR
FURNISHED PERMITS AND APPROVALS
To be completed as part of Permit List.
USCG Notice to Mariners, 614-540-7700
Ohio EPA General Construction Stormwater
Permit, 614-752-0782
Contractor furnished permit requirements are documented in RFP Section 2.3.1
External Permit or Approval
DESCRIBE WHERE AND HOW PERMIT REQUIREMENTS
ARE INCLUDED IN DESIGN PACKAGE: For each permit, describe requirement, specification (section and paragraph) and/or drawing number.
It is anticipated that permit requirements will be addressed in specifications in the DD phase.
Multiple permits are required.
Design-Build Contractor-Furnished permits are addressed in RFP Section 2.2.3.
Internal Compliance
IDENTIFY COMPLIANCE REQUIREMENTS:
SHPO, NEPA, EA: List requirement, status, and date or expected date.
Pre-NEPA in progress. Completion of Pre-NEPA is anticipated in December 2021.
NEPA - Decision on NEPA pathway will be made by NPS.
Section 106 - To be completed as part of NEPA compliance (June 2022).
Section 7 Compliance - To be completed as part of NEPA compliance (June 2022).
NPS identified NEPA pathway as a Categorical
Exclusion.
Additional Compliance activities are in progress.
The Proposed Action is categorically excluded from further documentation under NEPA in accordance with 43 CFR 1508.4.
RFP Section 1.8 indicates that the Categorical
Exclusion will be provided to the Design-Build
Contractor upon completion.
Compliance requirements are documented in
RFP Section 2.3.1.
Internal Compliance
COMPLETE ALL APPROVALS: Director's, DAB, Congressional Funding issues, estimate within available funds? Adequate time to complete work within project and funding constraints?
NPS 77-1 and 77-2 - Statement of Findings to be completed following Pre-NEPA development
(February 2022).
Project is in compliance with both NPS 77-1 and
NPS 77-2 as documented in the Categorical
Exclusion (draft). The project is exempt from a
Statement of Findings.
No Further Action Required.
General
IDENTIFY REQUIRED SPECIAL INSPECTIONS: List inspecting or approving organization and reason required.
None identified as part of PAF. Not Applicable. Not Applicable.
STAGING AND MOBILIZATION
IDENTIFY AREAS FOR STAGING INCLUDING AREAS FOR
PRIME, SUBS, MATERIAL, AND PARKING; IDENTIFY
AREAS FOR CONSTRUCTION CAMP IF APPLICABLE:
List drawing number(s) showing staging area(s).
Preliminary staging areas have been identified and are being investigated under the compliance task order.
Staging areas must be finalized and communicated to Contractor.
Access and Staging Maps are included in the
RFP Attachments (RFP Section 5.0).
IDENTIFY TEMPORARY UTILITIES AVAILABLE FOR
CONSTRUCTION: List drawing number or specification section that identifies available utilities-electrical, phone, non-potable and potable water, sanitary-provider, meter needed, and responsible cost party.
Utilities per one-call shown on Schematic Design drawings.
Availability of temporary utilities needs to be communicated to the Contractor for possible
Field Office.
Temporary utilities are addressed in RFP Section
2.3.9. Specification Section 01 50 00 to be
finalized between NPS and the Contractor needs to be coordinated with RFP Section 2.3.9.
IDENTIFY CONSTRUCTION LOGISTICS: List drawing numbers that show traffic control, access restrictions, work hour restrictions, bridges, features, other.
Trail closure signage will be required. CVSR track access coordination will be required.
Otherwise, traffic control and other related needs are limited and are not shown in the Schematic
Design drawings. Work hours are anticipated to be limited to 8 AM to 5 PM.
Construction coordination requirements and limitations associated with trails and the scenic railroad need to be communicated to the
Contractor.
Trail closure and track access coordination requirements are addressed in RFP Section 2.3.1
Environmental and Sustainability Requirements and Section 2.3.10 Access.
IDENTIFY IMPACTS TO PARK AND VISITOR
OPERATIONS: List drawing number(s) or specification section(s) that identifies impacts (e.g. Visitor Impacts, Neighborhood-Urban Impacts, Detours, Closures).
Visitor impacts limited to temporary trail closures.
Not included in Schematic Design drawings.
To be developed and analyzed as part of Pre-
NEPA activities.
Construction coordination requirements and limitations associated with trails and the scenic railroad need to be communicated to the
Contractor.
Trail closure and track access coordination requirements are addressed in RFP Section 2.3.1
Environmental and Sustainability Requirements and Section 2.3.10 Access.
IDENTIFY SITE ACCESS ISSUES: List drawing number(s) or specification section(s) that identify issues (e.g. remote and road type constrained sites, weather closure restrictions, road and bridge load limits, road and tunnel height restrictions, crane and helicopter requirements).
Not included in Schematic Design drawings.
Staging areas must be finalized and communicated to Contractor.
Access and Staging Maps are included in the
RFP Attachments (RFP Section 5.0).
SUBMITTALS
LIST MATERIAL SUBMITTALS ON CRITICAL PATH;
FOR DESIGN-BUILD (DB), LIST MATERIAL SUBMITTALS
REQUIRING GOVERNMENT APPROVAL
None identified. Material submittals need to be identified.
As documented in RFP Section 2.3.4, Contractor is to complete the NPS Submittal List and
Review Estimate Template. Submittal procedures should be coordinated with
Specification Section 01 33 23 Submittal
Procedures and Section 01 67 00 Product
Requirements, to be finalized between NPS and
Contractor.
NPS Constructability Checklist, 3-20-18 | page 1 of 3
Item Number Project Issues SD Comments Schematic Design
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
LIST LONG LEAD ITEMS; MATERIAL AND EQUIPMENT
AVAILABILITY CONCERNS, SPECIAL DELIVERY
REQUIREMENTS
Current volatility in the steel market could lead to delays in obtaining steel beams for the soldier pile and lagging wall at the Peninsula site.
Ongoing market volatility could lead to delays in obtaining steel beams for the soldier pile and lagging wall at the Peninsula site.
Contractor is responsible for products and materials. Specification Section 01 67 00 to be finalized between NPS and Contractor.
LIST OF SOLE SOURCE MATERIALS AND GOVERNMENT
FURNISHED MATERIALS OR EQUIPMENT
Not applicable. Not Applicable. Not Applicable.
SITE LAYOUT / RESOURCE PROTECTION
TYPES OF RESOURCE PROTECTION REQUIRED: List where and how requirements are included in design package.
Resource protection to be identified during pre-
NEPA activities as part of compliance task order.
To be included in specifications in DD phase.
Through NEPA activities several Park-specific resource protection needs have been identified.
Resource protection needs are documented in
RFP Section 2.3.1 Environmental and
Sustainability Requirements.
19 ACCURATE SURVEY DATA ON PLANS: BMs, TBMs, TOPO
Surveyed topography shown on Site Plan sheets
(Sheets C3, C7, C11, C13, C15, C17). Survey file states: “Coordinate System: Observations made with Ohio Department of Transportation virtual reference system to the Ohio State Plane
Coordinate System North Zone, NAD83 (2011) &
NAVD88 Datum between March 18 & April 1, 2021.”
Ongoing river erosion and geomorphological processes may result in changed conditions since
PD/SD survey was performed.
Per RFP Section 2.1.1 Scope of Work and
Project Summary/Requirements, Contractor is to perform and provide survey to confirm site conditions. See also Specification Section 02 21
13 Site Surveys.
Per RFP Section 2.3.17, all AutoCAD files are to be provided per Ohio State Plane Coordinate
System North Zone, NAD83 (2011) & NAVD88
Vertical Datum.
PRELIMINARY SITE INVESTIGATION COMPLETE,
EXISTING CONDITIONS VERIFIED AND INCLUDED IN
PACKAGE
Site reconnaissance was performed February 23-
24, 2021. The geotechnical exploration program was performed March 15-19, 2021. Investigation findings incorporated into Schematic Design submittal.
Not Applicable. Not Applicable.
CONSTRUCTION LIMITS CLEARLY SHOWN AND
DEFINED FOR BOTH ACCESS AND CONSTRUCTION: List where and how requirements are included in design package.
Schematic design-level construction limits shown on Site Plan sheets (Sheets C3, C7, C11, C13, C15, C17). Preliminary staging and access areas have been identified and are being investigated under the compliance task order.
Staging areas must be finalized and communicated to Contractor.
Access and Staging Maps are included in the
RFP Attachments (RFP Section 5.0).
SPECIAL SIGNAGE REQUIREMENTS: Describe and list where requirements are included in design package.
Trail closure signage will be required. It is anticipated that signage requirements will be addressed in specifications in the DD phase.
Temporary trail closures required for construction activities and public safety.
Specification Section 01 50 00 Temporary
Facilities and Controls to be finalized between
NPS and Contractor.
LIST WORK SAFETY CONCERNS, LOCATION, AND
NEEDS: Include Height, Weather, Animal, Aerial, Public
Accessibility, Security, Confined Space, Pathologic, Atmospheric, and others.
Weather, steep slopes (fall hazards), and riverine environment work conditions are concerns at all sites. Public accessibility and trail user safety is a concern at all Towpath sites and the Peninsula
Connector site. Track safety and access are concerns for CVSR site work.
Weather, steep slopes (fall hazards), and riverine environment work conditions are concerns at all sites. Public accessibility and trail user safety is a concern at all Towpath sites and the Peninsula
Connector site. Track safety and access are concerns for CVSR site work.
As documented in RFP Section 2.3.15
Temporary Controls, Contractor is responsible for safety, including safety specific to the riverine work environment and winter weather conditions.
Additionally, Specification Section 01 50 00
Temporary Facilities and Controls applies and is to be finalized between NPS and Contractor.
DEMOLITION
ALL EXISTING UTILITIES LOCATED AND ACCURATELY
SHOWN: Describe where shown.
Towpath MM 20 South utilities shown on Sheet
C15. Peninsula Connector utilities shown on
Sheet C17. No utilities identified at remaining
Towpath sites.
Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by
Contractor.
Contractor required to contact Ohio Utilities
Protection Service (OHIO811) per Specification
Section 02 21 13 Site Surveys.
TEMPORARY SYSTEMS REQUIRED: Identify for Park or
Public: Access, power, water, sanitary, covered access, exhibit relocation, movement assistance, accessibility.
No required temporary systems identified. Not Applicable. Not Applicable.
SALVAGE, RECYCLING, STORAGE, AND DISPOSAL
REQUIREMENTS: Who is removing salvageable equipment and where requirements are included in design package?
Not applicable (no salvageable equipment). Not Applicable. Not Applicable.
NOISE / DUST / SAFETY CONCERNS FOR PUBLIC OR
ENVIRONMENT: Describe where included in design package.
It is anticipated that noise / dust / safety requirements will be addressed in specifications in the DD phase.
Noise and dust are expected incidentals to project construction.
Noise and dust requirements are included in
Section 01 57 19.12 Noise and Acoustics
Management, and will be finalized between NPS and Contractor.
CONSTRAINTS ON MEANS AND METHODS: Blasting, Burning, Tidal, Weather, Public Accessibility, Existing structures/features, Holidays and Seasonal, Permitting, other.
Tree removal shall only occur between October
15 and March 31. Additional permitting and Park-specific constraints to be identified during DD phase.
Environmental constraints such as tree cutting and species habitat have been identified in the
Categorical Exclusion.
For project areas affecting Indiana bat swarming habitat (near hibernacula), only cut trees between
November 15 and March 15. For project areas affecting the species' summer habitat between
October 15 and March 15. Known requirements such as tree removal and bat restrictions are documented in RFP Section 2.3.1.
HAZARDOUS MATERIAL CONSIDERATIONS DEMO
METHODS AND DISPOSAL STATE AND LOCAL
REQUIREMENTS: Describe hazardous materials being addressed, how, and where in design package.
None identified. Not Applicable. Not Applicable.
ARCHEOLOGICAL MONITORING REQUIREMENTS:
Describe what is needed and where in design package.
Identify who provides monitor.
To be determined during NEPA activities as part of Section 106 Consultation.
NPS to consult with SHPO and complete archeologic surveys as needed within the Area of
Potential Effect, and regarding potential temporary impacts to archeological sites within the Project Area.
Archeological monitoring is required during construction at Towpath MM 20 South.
Specification Section 01 35 13.22 Archeological
Protection and Section 01 35 91 Historic
Preservation Treatment Procedures are applicable, and will be finalized between NPS and Contractor.
CONSTRUCTION
MATERIAL, EQUIPMENT, LABOR AVAILABILITY FOR
REMOTE SITES: Describe issues and where included in design package.
While there may be some difficulty in accessing the individual sites, CUVA is located in close proximity to two metropolitan areas. There should not be any issues related to material, equipment or labor.
Not Applicable. Not Applicable.
SITE ACCESS RESTRICTIONS TO CONSTRUCTION
OPERATIONS IF DIFFERENT OR MORE SUBSTANTIAL
THAN ITEMS 12 AND 14
No additional restrictions identified. Not Applicable. Not Applicable.
ANTICIPATED WEATHER CONSIDERATIONS,
CONSTRUCTION SEASON, OPTIMUM TIME TO
ADVERTISE, RECOMMENDED CONTRACT LENGTH
A winter shutdown is anticipated given the project's location in northern Ohio. Timing and duration need to consider placing/planting of vegetative treatments.
Construction period needs to account for anticipated winter shutdown periods.
Winter shutdown periods accounted for in 730 calendar day construction schedule (see RFP
Section 1.6 Schedule).
PARK / CONCESSION IMPOSED RESTRICTIONS
INCLUDED IN DESIGN PACKAGE AND IMPACTS ON
SCHEDULE & COST
No additional restrictions identified. Not Applicable. Not Applicable.
DESCRIBE FULL SCOPE OF WORK FOR LOCAL UTILITY
COMPANIES AND CONSTRUCTION CONTRACTOR FOR
EACH UTILITY
Exposed fiberoptic line at MM 20 South will need to be relocated; instruction to be developed during DD phase. Contractor to confirm location and utility protection needs. Specifications to be developed in DD phase.
Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by
Contractor.
Utility disruption requirements are addressed in
Specification Section 01 50 00 Temporary
Facilities and Controls, and will be finalized between NPS and Contractor.
Contractor required to contact Ohio Utilities
Protection Service (OHIO811) per Specification
Section 02 21 13 Site Surveys.
NPS Constructability Checklist, 3-20-18 | page 2 of 3
Item Number Project Issues SD Comments Schematic Design
DD or RFP Comments Design Development (DBB)
OR Request for Proposal (DB)
CD or RFP Resolution Construction Documents (DBB)
OR Request for Proposal (RFP)
DESCRIBE DISRUPTION REQUIREMENTS FOR UTILITY
CONNECTIONS, CLOSURES, AND MAXIMUM
ALLOWABLE INTERRUPTIONS: Describe where addressed in design package.
To be addressed in DD phase.
Known utilities identified in SD drawings. Known and/or unknown utilities may be encountered by
Contractor.
Utility disruption requirements are addressed in
Specification Section 01 50 00 Temporary
Facilities and Controls, and will be finalized between NPS and Contractor.
Contractor required to contact Ohio Utilities
Protection Service (OHIO811) per Specification
Section 02 21 13 Site Surveys.
SPECIFIC PHASING REQUIREMENTS: Detail what and where provided in design package.
Specific phasing not identified for Schematic
Design. Recommend constructing from upstream to downstream for sites in close proximity. Also, within each stabilization site work shall be performed from upstream to downstream.
Construction of tightly spaced sites should be constructed from upstream to downstream to reduce potential impacts from downstream disturbance.
Phasing requirements are included in RFP
Section 2.3.3 Construction Support.
DESCRIBE SPECIALIZED MATERIALS/INSTALLATION
METHODS CERTIFICATIONS/TRAINING REQUIREMENTS;
DETAIL GOVERNMENT REQUIRED SPECIALTY
SERVICES OR INSPECTIONS: List requirements.
None identified. Not Applicable. Not Applicable.
COORDINATION WITH PARK OR CONCESSIONAIRE ON
BENEFICIAL OCCUPANCY: Grand opening, fixed completion dates, etc.
No specific coordination needs identified. Not Applicable. Not Applicable.
ADJACENT or CONCURRENT CONTRACTS
COORDINATION / OVERLAPS ON CONCURRENT OR
FUTURE CONTRACTS
USACE Buffalo District river system enhancement projects have been identified by
NPS staff. The first project is between Boston
Mills Road and Vaughn Road and is anticipated to add 2-3 meander bends (bid Fall 2021/Winter
2022; construction Summer 2022). The second project is between Vaughn Road and Station
Road and is anticipated to include repairs due to the river lowering associated with the Brecksville
Dam removal. Future riverbank stabilization work anticipated at Switch 2 (upstream of Fitzwater site).
Not Applicable. Not Applicable.
41 VALUE ENGINEERING POTENTIAL None identified. Not Applicable. Not Applicable.
PROJECT CLOSEOUT
TRAINING REQUIREMENTS, CERTIFICATIONS
SPECIFIED
None identified. Not Applicable. Not Applicable.
43 OPERATION & MAINTENANCE (O&M) REQUIREMENTS
Growth period maintenance required for bioengineering measures. Periodic inspection and maintenance required for structural measures (i.e., wall at Peninsula).
Information for any required warranties on vegetative components must be included in specifications.
Time periods pertaining to vegetation condition and survival are documented in Specification 32
92 00 Seeding, Sodding and Landscaping. This
Specification needs to be coordinated with
Specification 01 67 00 to be finalized between
NPS and Contractor.
LIST PERMITS NEEDING CLOSURE AND POINTS OF
CONTACT: Describe requirement; include specification and/or drawing location for each.
To be determined following initiation of permitting.
See Items 5 and 7. See Items 5 and 7.
45 POST CONSTRUCTION REQUIREMENTS See Item 43 and 46. See Items 43 and 46. See Items 43 and 46.
LIST LONG TERM MAINTENANCE NEEDS AND LOCATION
IN THE DESIGN PACKAGE.
Replace riprap and streambank stabilization measures as needed. Seal concrete facing and cleanout wall drain pipes during scheduled maintenance.
Bioengineering and structural measures will require operation and maintenance plans.
Contractor required to prepare and submit
Operations & Maintenance data as described in
RFP Section 2.3.17 Project Close-out.
NPS Constructability Checklist, 3-20-18 | page 3 of 3
File details come from the government source that posted it. Updated .