This document contains questions and answers regarding a solicitation to correct critical safety hazards and rehabilitate the Ahwahnee Hotel National Historic Landmark in Yosemite National Park. Key details include that the work involves seismic strengthening of chimneys, structural repairs, window repairs, attic fireproofing, and replacement of deteriorated concrete terraces. The bid due date was extended to June 10th, 2022 and questions were accepted through May 27th. The work will take place over an 8-week hotel closure period starting January 2nd, 2023. The National Park Service aims to award optional line item 17 for attic fireproofing at least 90 days before the closure.
View the file
Other files
Show 40 more
Latest 50 of 64 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
YOSE 159410B 140P2022R0017
Questions Answers Amendment Document revisions in
Addendum 3 1 Please advise if the Government is going to extend the due date. We believe more time is needed given that the site visit is close to the due date.
Yes, the proposal due date will be extended until May 27 May 20 June 10th 5
2 Subfactor 1A: Please confirm that we can submit project experience for a subcontractor Project experience can be submitted for a subcontractor, but it would be more appropriate to submit it under Subfactor 1B, Key personnel and project team experience.
Project experience can be submitted for a subcontractor, but it would be more appropriate to submit it under Subfactor 1B, Key personnel and project team experience.
3 Subfactor 1B: Please advise if an induvial can perform multiple roles. Yes, an individual can perform multiple roles as long as they still meet all qualifications and requirements in accordance with the contract.
4 Subfactor 1B: Please clarify how many separate key personnel are need on‐site. There are five key personnel specified in the solicitation. There is no requirement on the number of individuals required to fulfill these roles. Also reference the response to question 3.
5 Subfactor 1B: Please advise if key personnel need to be employees of the Offeror. For example Can the Historic Preservation Specialist be a subcontractor/subconsultant or independent contractor?
Key personnel do not have to be employees of the offeror/prime contractor. It is up to the offeror to determine how to staff their project team while meeting contractual requirements.
6 Subfactor 1B: Please advise if there is a page limit for the resumes. There is no page limit for resumes specifically, but offerors must comply with the size limits for the overall proposal as specified in D. SUBMISSION REQUIREMENTS section of the INSTRUCTIONS FOR
THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION
7 Factor 3: The Government states In your accompanying narrative, explain schedule logic, critical path activities, and key considerations and constraints. Please clarify if the Government wants a narrative submitted in Factor 3 along with the Gantt Chart or if the narrative should be included in Factor 2‐Approach.
Please reference D. SUBMISSION REQUIREMENTS section of the INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION. The Factor 3 narrative includes explanation of schedule logic, critical path activities, and key considerations and constraints related to the schedule being provided. The Factor 2 narrative must describe your technical approach to the following:
•Submit a wri en detailed technical approach for performing this construc on project. Address the successful execution of the project while protecting the parks resources, maintaining park operations, and minimizing impacts to Park visitors. Consider any unique considerations relating to project scope, and creative and innovative ideas to execute the project in an expeditious manner. Demonstrate a clear understanding of the project scope and offer realistic strategies and methods for addressing the overall project scope.
•Describe your phasing and sequencing of work showing interrela onships of the major elements required for this project.
•Submit a wri en narra ve explaining how your proposed schedule (Factor 3) will be accomplished in relationship to your submitted technical approach.
8 Past Performance: Please advise if we can submit previously completed PPQs in lieu of requesting new ones. Yes, as long as you comply with the instructions provided in the Past Performance section of the INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE
SELECTION.
9 Can you please provide contacts for lodging? Lodging inside the park is operated by the park concessioner, Yosemite Hospitality. Yosemite Hospitality is not required to provide lodging to contractors associated with this project, but may do so at their discretion. Contractors should contact Yosemite Hospitality directly to inquire about availability, pricing, etc.
For inquiries, contact:
Erin Callahan, Yosemite Hospitality Executive Assistant callahan‐erin@aramark.com
10 On other RFPs the NPS has written "'Substantially Completed' is considered complete enough to determine performance on all phases." Will the NPS allow substantially completed projects within the past 10 years?
Yes 5
11 Key trades are referenced under Subfactor 1A Project Experience. Are bidders expected to submit subcontractor projects in this Factor? If so, please consider increasing the maximum number of projects to 10 relevant projects.
10 relevant projects is acceptable. 5
12 Please allow the roles of Superintendent and On‐Site Safety Specialist to be performed by the same individual (dual‐hatted). Reference response to Question #3 above ‐ an individual can perform multiple roles as long as they still meet all qualifications and requirements in accordance with the contract.
13 Please clarify which Key Personnel Positions are required to be full time on site. It is up to the offeror to determine how to staff their project team while meeting contractual requirements. The contractor's designated Jobsite Superintendent, Safety Manager, and Quality Control Supervisor shall be on the project site whenever contract work is in progress as required by the contract.
14 Please provide a page limit for the resumes. Reference response to Question #6 above. There is no page limit for resumes specifically, but offerors must comply with the size limits for the overall proposal as specified in D. SUBMISSION REQUIREMENTS section of the INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER
INFORMATION – COMPETITIVE SOURCE SELECTION
15 Please confirm which key positions can be performed by subcontract personnel. Reference response to Question #5 above. Key personnel do not have to be employees of the offeror/prime contractor. It is up to the offeror to determine how to staff their project team while meeting contractual requirements.
16 Please confirm the Historic Preservation Specialist can be performed by subcontractor. Reference response to Questions #15 and #5 above. 5 17 Please clarify is the on‐site superintendent can also be assign the duty of the Quality Control Supervisor. Reference response to Question #3 above ‐ an individual can perform multiple roles as long as they still meet all qualifications and requirements in accordance with the contract.
18 Is the required narrative explaining how our proposed schedule will be accomplished in relationship to our submitted technical approach included in the 3‐page limit? Please consider allowing this supplemental narrative to stand outside the 3‐ page limit and/or consider increasing the page limit of Factor 2.
Disregard the page limit for Factor 2. Our expectation is the narrative is succinct and pertinent to Factor 2 and in support of Factor 3.
19 Please provide a page limit for the schedule narrative required in Factor 3. Narrative to be included in response for Factor 2. See response above. 5 20 Please provide a page limit for the safety narrative required in Factor 4. There is no page limit specifically for Factor 4 (safety), but offerors must comply with the size limits for the overall proposal as specified in D. SUBMISSION REQUIREMENTS section of the INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION.
21 The instructions state to provide the resume of the Safety Manager. The resume of the Safety Manager is also requested in Subfactor 1B Key Personnel. Please confirm that the resume is also to be included in Factor 4 and that it will not count towards the page limit.
Identify and reference Safety Manager in Factor 4, but include resume in subfactor 1B. 5
22 For Volume I, please provide Small Business Participation documentation form. Included on Original solicitation Attachment 9 5 23 Many of our government projects have already been assessed through existing Past Performance Questionnaires. May we submit previous PPQs with our proposal in lieu of requesting a new Past Performance Questionnaires?
Yes, refer to Past Performance section of E. VOLUME I, TECHNICAL PROPOSAL – FORMAT, ORGANIZATION, CONTENTS section of the INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION in the solicitation.
24 Para 1.10.C Additional Reports references the "Asbestos survey report dated OCT 22, 1990 " Please provide. Included on Amendment 1 Attachment 16 5 25 The level of detail in the drawings is leading to a large number of questions. Please provide an extension to allow additional time to develop questions as our review of the documents progresses. Please provide a question time extension to submit additional question to May 20. This will result in a clearer understanding of the project requirements, reducing perceived risk and contingencies
Extension for questions to May 27th. 5
26 Due to the timing of the site visit and the level of detail in the design documents, please provide an extension to the submission deadline to June 10th. This additional time will allow the bidders to solicit additional subcontractor pricing, and work with the various subcontractors to provide more competitive proposals, ultimately resulting in a better value to the
NPS
Proposal extension to June 10th is acceptable. 5
27 Summary of Work 1.1C4 says to provide epoxy floor coating @ dry storage room, please provide specification for epoxy floor coatings
ARG: Refer to Section 09 67 23 Resinous Flooring (same floor coating as in the main kitchen). 6
28 The Wood window specification references 08 80 00 Glazing for window glazing which is not included with the RFP specifications. Please provide
ARG: 08 52 00 Item 1.2. B. 2 reference to 08 80 00 deleted. Glazing specification is within 08 52 00. 6 Spec section 08 52 00
29 Please provide Asphalt Roof Specification for new asphalt roofing ARG: Section 07 31 10 added for the Maintenance Shop roof, included in Addendum 3. 6 Spec section 07 31 10
30 Please confirm there are no new storefront window/door assemblies. KN1 on A5.0‐5.3 call out (N) Storefront windows, but do not indicate where they are, and there are not aluminum storefront specifications or schedules provided.
ARG: Confirmed no aluminum storefront in Kitchen. Office 012 enclosure was changed to stud framed wall and details shown in Details 2/A5.2 and 9, 12/A9.4.
6 Revised sheets A5.0‐5.3
31 Please provide specifications for NEW Copper Gutter & Downspouts ARG: Section 07 62 20 added to Specifications, included in Addendum 3. 6 Spec section 07 62 20 32 Please confirm that the Proposed temporary 6" sewer line, noted as "TS" on sheet C6.1, is not part the scope of this RFP and is shown for coordination purposes only.
PPE: Correct. Temporary sewer line is shown for reference only.
ARG: It is part of the Temp Kicthen project.
33 Please confirm whether the scope to expose and connection of proposed 6" sewer service to existing 6" Sewer per detail 1/6.1 is with this contract, or the separate temporary kitchen project
PPE: This work is part of this contract. 6
34 Please confirm whether the installation of the 6" SDR 35 sanitary sewer service per detail 1/C6.2 is part of this contract, or the separate temporary kitchen project?
PPE: This work is part of this contract. 6
35 Are there as‐builts drawings available for the existing roofing systems that are to be removed and reinstalled? There are no as‐built drawings of this work. 6 36 Demo Key Note 9 on A1.6 points to four separate objects with the note "typ". The key not 9 says "Not Used" Please clarify if this is a mislabeled keynote or what the purposes of this note is?
ARG: 2 Keynote 9 on A1.6 has been deleted in Addendum 3. 6 Revised sheet A1.6
37 A2.1, Slab Plan 4Slab Plan note 4 says to provide 2" Foam‐in insulation under existing & new slabs. Please confirm limits of spray foam insulation scope of work. Is it intended in work areas only, or the entire underslab of the building within the crawlspace?
ARG: Foam‐in insulation scope is limited to underside of the Kitchen floor slab and not the entire building.
38 Sheet note 3 on S1.0 indicates that the existing footing depth is unknown and directs the contractor to underpin footings with less than 6” embedment. Since this is unquantifiable scope, please provide an assumed quantity of footings that will require underpinning for bidding purposes.
DEG: Existing footing depths are unknown. Estimate underpinning at two footings, K4‐KD and KE.
Footing at K4‐KD and KE may need underpinning or replacement, 3’ square x 16” 5 #5 EW bottom.
39 General Note 5 on S0.0 indicates that it is the contractor's responsibility for all excavation procedures, including underpinning & protection of existing construction. Please confirm that any underpinning of existing footings would only occur in areas of excavation below the Kitchen.
DEG: Underpinning of footings only envisioned in Kitchen to suit slope to drain rat proofing.
40 Please confirm the existing conditions in the crawlspaces is bare soil/dirt and there is no existing concrete rat slab to be demolished.
ARG: The existing condition in the crawlspace is bare soil/dirt. Refer to keynote 1 on Sheet A1.0, misc.
debris shall be removed prior to installation of new rat slab.
41 Please confirm the existing conditions in the crawlspaces is bare soil/dirt and there is no existing concrete rat slab to be demolished.
ARG: See above. 6
42 Please clarify the feeder for new Panel ‘M’ located in the porte cochere/maintenance shop. Is the panel to replace an existing panel and we are to re‐connect the existing feeder/existing branch circuits, or does the panel require a new feeder?
If the panel requires a new feeder, please specify the feeder size and point of origin.
OMM: The panel requires a new 100A feeder and all branch circuits are new as shown on plans.
Please provide new feeder as (4)#2 + (1)#8G in 1.25” conduit from new Panel K1 at East side of Kitchen. Revise Panel M bussing and main breaker to be 100A (in lieu of 225A shown) and provide a 100A/3P sub‐feed breaker in Panel K1 at space K1‐37/39/41.
43 The general electrical notes refer to Food Services (FS Series) plans for related and required electrical work however these "FS" drawings are not provided as part of the RFP package, please clarify and/or provide this drawing package.
The concessioner's foodservice drawings are provided for reference. ARG: FS sheets are only identified for reference and do not contain any work included in this project.
44 New sand Interceptor shown in detail 4/C7.1 to be 1.2' from face of Ahwahnee hotel foundation, the structural plans on S1.0 dimension the <N> sump 10' away from the hotel foundation. Please clarify location of new sump pit.
PPE: Structural drawings have removed the new sump pit from their plans in Addendum 3. Their plans were illustrating a previous design. The current design does not require a new sump pit to be constructed. Rather a sand interceptor is proposed to be installed outside the existing sump pit to filter the drainage captured from the crawl space trench drain. The design illustrated on Detail 4, Sheet C7.1 is correct.
6 Revised sheet C7.1 and S1.0
45 Detail 6 on Drawing S6.0 shows new concrete sump pit slab and wall thickness but does not provide overall dimmensions or elevations or plan view size of new sump pit.
DEG: The new sump was part of an early design and has been deleted from sheets S1.0 plan and Detail 6/S6.0 deleted in Addendum 3.
6 Revised sheet S6.0
46 Detail 6 on Drawing S6.0 Does not provide a cover type, size or detail for the sump pit. Please provide. PPE: See response to comment 44. The proposed sump pump illustrated on the structural plans has been removed in Addendum 3.
6 Revised sheet S6.0
47 General terrace plan notes indicate that contractor is responsible for concrete spall & crack repairs to existing west loggia, but the west loggia is not outlined within the "Area of Work". Please provide quantity for basis of pricing or detailed photos of existing conditions to quantify the extent of this scope.
ARG: Photos of existing conditions at the west loggia are included with this response. Assume infill of 20 spalls averaging 1‐2" in diameter. See revised Spec Section 03 01 00 in Addendum 3 for clarification of treatment.
6 Photos and revised Section 03 01 00
48 General Terrace plan note C. says to apply Wax coating to all concrete surfaces. Please confirm where this wax coating is to be applied as the new stamped concrete terraces call out a clear coat sealer.
ARG: General Terrace Plan Notes only apply to the historic west loggia as stated in first sentence of these notes.
49 Key Note 41 indicates a high heat safety glass view in window in the kitchen partition and refers to FS DWG for details ‐ No "FS" drawings were provided with the current RFP or amendments. Please provide specification / requirement for high heat safety glass.
The concessioner's foodservice drawings are provided for reference. ARG: High heat safety glass specification included in Addedum 3.
6 Revised sheet A3.14 and added Section 08 88 13
50 Photos from the site visit walk through show furniture & storage racks full of supplies in the attic spaces. Please confirm the government will remove any stored items from spaces prior to the work associated with the attic cementitious fireproofing.
Yes, the concessionaire will move all stored items out of the attic space to accommodate installation of fireproofing.
51 Key Note 50 indicates the contractor is responsible to "replace damaged/missing insulation as required". This is an quantifiable scope for bidding purposes, please provide assumed quantity of batt insulation and R‐Value of insulation required.
ARG: Assume full replacement of batt insulation in kitchen attic. R‐Value is to match existing to remain.
52 It is unclear how many chimneys are to be repaired & repointed on the main building under CLIN 10 Option C. Hotel roof plan on A2.13 outline what appears to be (2) chimneys within the area of work. Please confirm these (2) chimneys are the extent of the chimney seismic upgrades associated with details on S1.11 & A8.3.
ARG: Keynote 17 and Area of Work defined on A2.13 is showing scope of fireproofing repair. Refer to Keynote 18 on A0.2 and Detail 7 on S2.2, etc. Total of 7 chimneys to be structurally strengthened and waterproofed including 2 cottage chimneys.
53 Chimney Partial Plan Sections on S1.11 have a note to replace parging & waterproofing and to Refer to Item no. 116 ‐ Please clariify where "ITEM NO. 116" reference located within the RFP.
DEG: Note deleted and replaced with “SAD Details 3 and 6 on A8.4.” in Addendum 3. 6 Revised sheet A8.4
54 Window Repair legend on A7.0 indicates the contractor is responsible for replacement of cracked, broken or missing glazing.
Please provide an assumed quantify or percentage of broken or missing glazed panels for pricing purposes
ARG: Information added to revised A7.0 in Addendum 3. 6 Revised sheet A7.0
55 Window Repair legend on A7.0 indicates the contractor is responsible for replacement of cracked, broken or missing putty.
This scope is unquantifiable, please provide assumed quantity or % of pieces that need repair or replacement
ARG: Windows have wood stops, not putty. Sheet A7.0 has been revised in Addendum 3. 6 Revised sheet A7.0
56 Please confirm that the Window repair legend on A7.0 and A7.1 apply only to the windows identified on their respective sheets
ARG: Repair levels on A7.0 window repair legend on A7.0 have been revised to be the same as repair levels on A7.1 for clarity.
6 Revised sheet A7.0
57 Please confirm that the windows identified on A7.0 have putty stops whereas the A7.1 windows have wood stops. ARG: The windows on A7.0 also have wood stops. Revised sheet included in Addendum 3. 6 Revised sheet A7.0
58 Please provide missing detail 2/S2.4 called out on S2.1 for shear wall footing details DEG: See 2/S6.2 instead. Sheet S2.1 revised in Addendum 3. 6 Revised sheet S2.1 59 There are no dimensioned elevations showing the height of the crawl space, height of new footing or floor to floor elevations to calculate height of new south wing shear wall. Please provide shearwall elevation dimmensions S2.1 or missing drawings.
DEG: Dimensions added to S2.1 in Addendum 3. 6 Revised sheet S2.1
60 Please confirm that there is not additional scope of work associated with the crawlspace outside of the excavation for shear wall & footings at the south wing. IE, no grading, drainage or rat slab in south wing crawlspace.
ARG: Confirmed no grading, drainage or rat slab scope in South Wing crawl space. 6
61 Detail5/A8.3 has a detail to "mechanically fasten large cracks, typical" ‐ Pease provide quantity of this repair. It's only shown in this detail associated with the T3 dutchman repair and not called out anywhere on the exterior elevations.
ARG: This detail is only used on A3.6 at one crack location (legend item T3), assume 3 pins. 6
62 Detail 5/A8.3 also makes note to repoint adj stone joint where required. Please confirm the repoint work is only associated within the immediate area of work related to the dutchman repairs.
ARG: Confirmed repoint work in Detail 5/A8.3 pertains to only the Dutchman repair adjacent. 6
63 Please clarify which CLIN the exterior site work should be include in. ARG: CLIN 1 for Kitchen associated site work; CLIN 14 Bid Option G for Terrace concrete replacement associated site work and CLIN 15 Bid option H for Maintenance Shed associated site work.
64 The south wall shear wall structural drawings do not provide elevations of footing or floor to floor heights of the building, nor do the architectural drawings. There is not enough information provided to calculate the volume of concrete without the elevations.
ARG: See answer to question 59 above. 6
65 IV Structural Steel Note 6 calls for "Tenmec Paint" for structural steel. No specification for high performance coatings specifications were provide, please provide specified coating requirements for shop primed structural steel.
DEG: Shop primer two coats Tnemec Universal Primer AK02. Kitchen floor to receive intumescent paint fireproof coating.
ARG: Intumescent Paint Section 07 81 23 added in Addendum 3.
6 Revised section 09 91 23
66 Please proved which paint finish type is required for the exposed structural steel in the kitchen mezzanine. ARG: Existing structural steel requires cementitious fireproofing repair.
DEG: New structural steel in kitchen mezzanine should be shop primed with two coats Tnemec Universal Primer AK02 and also receive fireproofing.
67 Please confrim the structural steel in the kitchen floor required no additional paint beside other than shop primed. DEG: Also apply Intumescent paint coating.
ARG: See Addendum 3 Spec Section 07 81 23.
68 Structural steel specifications Paragraph AA. indicate to shop prime all structural steel with "Tnemec Paint suitable for partially exposed structural steel. Please confirm what specific type of Tnemec paint coatings are required.
DEG: Tnemec AK02 Universal Primer. 6
69 Please confirm if new structural steel in the crawl space require field applied cementitious fireproofing or intumescent paint coatings.
ARG: Apply intumescent coating to new structural steel in crawl space. See Addendum 3 Spec Section 07 81 23.
6 Section 07 81 23
70 Please clarify if new structural steel & bracing in the attic space required to be coated in cementitious fireproofing. The drawings and specifications only indicate repairs and additional fireproofing to existing steel in the attic.
DEG: New steel in the attic to be shop primed and coated with cementitious fireproofing. 6
71 Sheet S0.0, section VI. Structural Steel, note 6 calls for non‐galvanized steel to be shop primed and painted with Tnemec paint. Section 09 91 23; 3.10.B of the specification calls for Steel to receive an Alkyd primer with 2‐coats of Interior Latex paint but does not specify where this is to be applied. Please clarify the finish application for all interior structural steel.
Further, please confirm that none of the new structural steel is to receive cementitious fireproofing. Specification section 07 81 16 for Cementitious Fireproofing is applicable only to existing structural steel.
ARG: Only exposed structural steel in Kitchen and Dining room requires finish paint. Section 09 91 23 applies to Keynote 12 on A3.12, A3.13, A3.14 and Detail 11/S6.3 exposed steel members including anchors. Section 07 81 16 Cementious Fireprooofing also applies to new structural steel brace frame in mezzanine and attic spaces.
6 Revised S0.0 and Spec sections 09 91 23 and 07 81 16 in Addendum 3
72 1.10 Additional Reports – Section B Please provide an assessment report entitled report Exterior Wood Columns at the Ahwahnee Hotel, dated 25 March 2020.
According to Section 011100 Additional Reports‐Summary of Work it has been prepared by Architectural Resources Group.
Report provided in Amendment No. 1 6
73 Will there be an opportunity to examine a specific part of the hotel before the bid deadline? No, there will not be an additional site walk prior to June 6. 6 74 Will there be a laydown area and a designated place for a storage container? ARG: Refer to drawing sheets T6.a and T6.b Logistics Plans. 6 75 Section 01 11 00 Summary of work
1.7 Special Construction Requirements – Section B
How much anticipated area is the general contractor responsibility of plowing of access roads to and within the project?
The Park and concessionaire will be responsible for snow removal at access roads, service yard, and hotel grounds.
76 I understand the on‐site work hours Monday through Friday, 8:30 am to 5:30 pm.
Will there be an opportunity to work 4/10 schedule? An employee works four 10‐hour days.
During the closure, yes a 4/10 schedule is acceptable. A 4/10 schedule will not be allowed while the hotel is in operation outside of the closure period.
77 Are existing exterior wood columns stained of natural finish? ARG: Yes, stained. 6 78 Section 06 01 40 Maintenance of Historic Woodwork
3.4 Dutchman Repair
How many dutchman repairs are needed throughout the project.
ARG: Per the General Notes on sheets A3.1‐A3.4 and A3.6 assume 5 locations with each location approximately 20 square inches in size.
79 Section 06 01 40 Maintenance of Historic Woodwork
3.5 Wood Preservative Treatment
Is the wood preservative treatment applied to all existing wood?
ARG: Wood preservative should be applied to all non‐painted exterior historic woodwork per the General Notes on sheets A3.1‐A3.4 and A3.6. This includes the exterior wood columns, wood rafter tails, wood soffits, and wood infill panels of the Dining Wing and Presidential Suite.
80 Please confirm that the furnish and installation of all required cooler lighting shown on drawings E4.1 & E4.2 is inclusive of the Food Service package and is not part of this contract
OMM: The cooler fixtures come with the cooler. So those are not expected to be provided and installed by the electrician.
81 Please confirm that the furnish and installation of all required hoods (46, 112 & 135) shown on drawing M3.1 is inclusive of the Food Service package and is not part of this contract
ARG: Furnishing and installation of hoods is not part of this contract. 6
82 Please confirm that the furnish and installation of all kitchen equipment shown on drawings E4.1 & E4.2 is inclusive of the Food Service package and is not part of this contract
ARG: Furnishing and installation of kitchen equipment is not part of this contract. 6
83 Please verify design‐build cooler per keynote 16/A2.2 is shown for reference only and is NIC. ARG: Keynote 16 on A2.2 was revised in Addendum 1. 6 84 Please provide a specification for the aluminum storefront system at the Kitchen office per remark, room 012, Kitchen Finish
Schedule per sheet A7.2.
ARG: See Item 30 response above. 6
85 Please provide a specification for the ACT at room 012 ceiling per the Kitchen Finish Schedule per sheet A7.2 ARG: Room 012 should have a painted gypboard ceiling. Finish schedule revised in Addendum 3. 6 Revised sheet A7.2
86 Windows 013 and 013A are shown on the window schedule per sheet A7.0 to be painted wood. The Kitchen Finish Schedule per sheet A7.2 calls for aluminum storefront. The interior elevations for the office per sheet A5.2 appear to match the window schedule most closely. Please clarify. If aluminum, please provide a specification for the aluminum storefront system
ARG: Windows 013 and 013A are wood windows. Finish schedule revised in Addendum 3. 6 Revised sheet A7.2
87 Are there As‐built drawings showing the existing structural framing below the kitchen slab to determine extent of demolition and shoring required?
No as‐built drawings are available. Refer to A1.1 and S1.1 for extent of Kitchen floor slab demolition.
The historic structures report, the seismic evaluation report, and construction documents are the best sources for that information.
88 Please confirm that the furnish and installation of all kitchen equipment shown on the kitchen equipment connection schedule drawing P0.2 is inclusive of the Food Service package and is not part of this contract
ARG: Furnishing and installation of kitchen equipment is not part of this contract. The contract does include coordination and connection to kitchen equipment.
89 Please provide a coring size for the vertical coring per 9/S6.5 DEG: Recommend 1 inch round core. 6 90 Please provide a coring size for the vertical coring per 7/S2.2 DEG: See comment 89. 6 91 Is relocation of the existing Unistrut fan hood support per keynote 33/A3.13 to be relocated via this contract, or is that part of the food services equipment contract?
ARG: Unistrut hood hangers and installation coordination are part of this contract. Furnishing and installation of the hoods is not part of this contract.
92 Please provide detailing of the epoxy dowels at Kitchen shearwall footings per 1&3/S2.0 (size of dowel, embedment depth). DEG: Embedment length as recommended by epoxy manufacturer to develop bar. 6
93 Please confirm there are two rows of horizontal #4 ties doweled into the vertical face of the existing footing at 6” oc. DEG: We assume the question is in regards to 11/S6.0. If so, yes, two rows of dowels. 6
94 Keynote 11 calls for the collector to be installed at lines W1 and W2. Please confirm this is erroneous and that the limits of the collector per 1/S1.5 are along line WA from W2 to W8 per keynote 4/A6.2.
ARG: Refer to sheet S1.5 DEG: Collector is on WA from W2 to W8
95 Please provide detailing for the vertical epoxy dowels at the existing footings at the ground floor. DEG: Bar sizes are called out. Embedment length per epoxy manufacturers printed instructions.
Follow details of those instructions.
96 This calls for epoxy anchors below the roof framing and refers to the structural drawings. This is not shown on sheet S2.2, nor is the cricket. Please clarify.
ARG: Refer to Detail 11/A8.3 and 8/S2.2. Supplemental structural detail to be provided.
DEG: See new detail 9/S2.2 in Addendum 3.
6 Revised drawing S2.2
97 Finish Schedule Kitchen, room 006 Chef’s Table calls for new GWB Ceiling. This room is not shown on the RCP or Floor Plan per A2.2. Please clarify.
ARG: Sheet A7.2 updated to remove Chef's Table room in Addendum 3. 6 Revised drawing A7.2
98 What are the limits of application of the Silane / Siloxane water repellent? ARG: The silane/siloxane water repellent is limited to the stone piers and chimneys. Refer to details 3 & 6/A8.3 and 3 & 6/A8.4.
6 Revised drawings A8.3 and A8.4
99 Please confirm details 3&6/A8.4 are applicable to Balcony Stone Piers per 9/S6.5. ARG: Yes these architectural details provide waterproofing requirements for the balcony stone piers also shown in detail 9/S6.5.
100 General Notes, section III: Shotcrete; note 1 limits shotcrete placement to where shown on plans only. Sheet S1.5: Notes for structural work at west end of dining room; note 6 specifies the new beams to be shotcrete. Detail 4/S6.5 shows removal of the column stone at the top 1/3 of the shotcrete beams such that the beams can be poured monolithically with the column core. Should the column cores be shotcreted, or is a cold joint at the intersection between the column and the beam acceptable?
DEG: Filling the void in the stone columns should be poured with an appropriate construction joint to the shotcreted beams. Propose details for review.
101 General Notes, section III: Shotcrete; note 3 delineates strength requirements for shotcrete at beams and walls. Are there any walls where shotcrete would be acceptable? The south wing shear walls where the existing gyp block is to remain on one side might be a logical choice.
DEG: The south wing shear walls can certainly be shotcrete. The new wall in the Kitchen can be shotcrete at Contractor’s option.
102 The rat slab only requires 2500 psi concrete per the structural notes, but spec 2.08.F.4 calls for a maximum w/cm ratio of
0.45. For an economical mix, that will drive the cementitious content to at least 6.5 sacks/cy (611 pcy) which is normally a 4,000 psi mix. Can the rat slab have a maximum w/cm of 0.60 maximum?
DEG: Yes, the rat slab is non‐structural and can have a higher w/cm ratio. 6
103 Spec 2.08.F.6 calls for a total air content of 6% maximum. Does this mean all interior concrete which is not exposed to freeze/thaw cycles can be non‐air entrained (so 1.5% trapped air for 1” gravel mixes)? Our supplier would recommend this since there’s no need to entrain air for interior concrete.
DEG: No need for air content on interior concrete. Mix designs by Contractor as a required submittal. 6
104 Per ACI reference standards in paragraphs 1.3 C & H ‐ All exterior flatwork is Exposure Category F2 and, per the referenced ACI 318 should require an air content of 6% with a placement tolerance of 1.5% (which could violate the 6% maximum spec referenced in section 03 30 00 – 2.8.F.6).
DEG: Exterior concrete is F2 and follows ACI’s air content recommendations 6
105 Sheet S0.0, part V.5 specifies all concrete other than rat slab and slab on grade as 4,000psi. Rat slab and slab on grade as specified as 2,500psi. Presumably, the terrace concrete is slab on grade, and should be specified as 4,500psi per the referenced ACI standard. Please confirm PSI rating required for terrace concrete.
DEG: Terrace concrete may be exposed to deiceing chemicals and should be 5000 psi concrete. 6 Revised drawing S0.0
106 Spec 3.06.E calls for steel trowel finish for both slab cases. ACI specifically prohibits the use of air entraining admixtures for steel troweled slabs which must have a total air content less than 3% to ensure no delamination of the surface. Please clarify.
DEG: We will work with concrete subcontractor to agree on a proper solution. 6
107 Could exposure classes per the referenced ACI specifications be identified for each concrete use? DEG: Exterior concrete F3 and C2. Kitchen floor concrete F0 and C1. Other interior concrete F0 and C0.
108 The shotcrete spec calls for ASTM C‐150, Type I cement which isn’t available… California producers make a Type II/V due to sulfates in the soil. Will Type II/V cement will be allowed?
DEG: Type II/V will be allowed. 6
109 The sloped topping slab over existing slab shown on sheet A2.1 cannot be achieved using the specified concrete mix due to aggregate size. Please specify a material for this application. We have used SikaQuick and SikaTop products for similar applications. These products can be feathered down to 1/4".
ARG: SikaQuick / SikaTop or equal is acceptable where specified topping slab concrete mix aggregate exceeds the slab thickness.
110 Slab Plan note 1 specifies the top of the new structural slab to be 4" below the elevation of the existing slab, and the plan specifies elevations relative to the top of the existing slab (datum 0.0), all of which are higher than the ‐4" per the note. Is this indicating that the structural slab should be poured level at ‐4" relative to the existing slab, and then a topping slab installed over it to achieve the desired elevations and slopes?
ARG: Confirmed structural slab is to be flat ‐4" below existing slab and a sloped topping slab is to be installed over the structural slab.
111 Please confirm the kitchen equipment curbs are NIC and by others. Because the Resinous Flooring cove base is applied to the face of the curbs, they will need to be installed prior to flooring application. Please confirm this will be completed by the FS contractor during Kitchen construction.
ARG: The kitchen equipment curb installation and coordination with FS contractor / vendor are part of this contract.
112 The referenced details call for a fluid‐applied waterproof membrane to be installed under the new Kitchen topping slab at existing slab locations and over the new concrete and under the resinous flooring at the new slab locations. Typically, all areas over existing slab and new slab will be shotblasted as a preparatory measure for either sloping compound or resinous flooring (this is a requirement of section 09 67 23 for Resinous Flooring). It appears the fluid applied membrane is incompatible with this process. Please confirm the fluid‐applied membrane is necessary, and if so, confirm that it is compatible as a substrate over shotblasted concrete for the sloping compound and resinous flooring. Please also confirm that this is the fluid‐applied waterproofing product per section 07 14 00.
ARG: Referring to drawing sheet A8.1 and A9.3 details, fluid‐applied membrane is a redundancy and omitted in Detail 6, 7, 10/A8.1 and 6, 7, 8, 9/A9.3 in Addendum 3.
6 Revised drawings A8.1 and A9.3
113 S0.3 references (5) chimney locations associated with seismic repair detail on S1.11, please confirm seismic coring of chimeneys is at these 5 locations on the hotel only. In addition, please provide dimensioned elevations of each chimney or an assumed vertical foot quantity of core drilling required for each chimney.
ARG: Refer to Item 52 response above. A total of 5 chimneys at the hotel and 2 chimneys at the cottages require seismic anchorage.
DEG: Contractor to estimate length of cores, make an estimate plus price per foot for +/‐.
114 Schedule outline indicates that the work associated with CLIN 17 must be performed during the 8‐week Hotel Closure, which will take place starting January 2 2023. Solicitation Section H Special Requirement 1 allows the Contracting Officer to award bid options (including CLIN 17) within 180 days after contract award. CLIN 17 will need to be awarded well in advance of 180 days after contract award, as the contractor will need sufficient time to select and contract with a vendor to perform the work, obtain and submit all product data, procure material, and perform the work within a short window. Please confirm that CLIN 17 will be awarded no later than 90 days prior to the start of the Hotel Closure.
The time constraints outlined in the comment are understood. If awarded, CLIN 17 will be awarded a minimum of 90 days prior to the start of the Hotel closure.
115 Section 01 11 00 paragraph 1.6.A indicates regular work hours are 8:30 to 5:30 Monday through Friday except during the hotel closure period and when otherwise indicated. Please confirm that during the 8 week hotel closure period, the contractor will be allowed to work extended hours (early start, late finish) and weekends to ensure the critical work schedule is accomplished, without restriction.
During the closure period the contractor will be allowed to work extended hours and weekends, without limitations.
116 Section 01 11 00 paragraph 1.6.A indicates regular work hours are 8:30 to 5:30 Monday through Friday except during the hotel closure period and when otherwise indicated. During normal work while the hotel is open will the NPS consider allowing 4‐10 hour work days, Mon‐Thurs, either 7:30am to 6pm or 8am to 6:30pm?
During the closure, yes a 4/10 schedule is acceptable. A 4/10 schedule will not be allowed while the hotel is in operation outside of the closure period.
117 Section 01 11 00 paragraph 1.6.A.2 indicates that drilling or other noisy activities are allowed only from 9 am to 5:30 pm Monday thru Friday, except during the hotel closure period. During normal work while the hotel is open will the NPS consider extending the allowable hours to coincide with 4‐10 hour work shifts, Monday thru Thursday?
During the closure, yes a 4/10 schedule is acceptable. A 4/10 schedule will not be allowed while the hotel is in operation outside of the closure period. Drilling or other noisy activities are allowed only from 9 am to 5:30
118 Please confirm that elevator/s can be used for construction access for attic fireproofing & chimney work performed during the hotel closure.
Yes, the freight elevator can be used. 6
119 Please confirm that elevator/s can be used for construction access for attic fireproofing & chimney work performed outside of the hotel closure.
CLIN 17 attic fireproofing to be completed during the closure. Yes, it is acceptable to use the freight elevator to access the chimney work outside the hotel closure.
120 Amendment 5 Solicitation Section L, Instruction for the Submission of Offers and Other Information ‐ Competitive Source Selection, Paragraph C.1 (Page 45 of 53) indicates that proposals are due at "1500 PD." Please confirm "PD" is referring to Pacific Daylight Time
Yes, it is confirmed, PD is referring to Pacific Daylight Time 6
121 Referenced note requires repair of cracks wider than 2mm in size and spalls larger than dime‐size. Determining an accurate quantity of repair is not possible without a detailed inspection of the existing terrace. In order to reduce the likelihood of quantity dispute during project execution, please consider providing an allowance for this scope of work for the bidders to include with proposals.
ARG: see response to Item 47 above. 6
122 East Loggia includes Demolition Callout "PC" for Protect Existing Concrete Improvements to Remain. Please clarify whether the East Loggia should be removed
ARG: The East Loggia concrete floor is to be demolished and reconstructed to match original concrete in design and color per keynote 14 on sheet A2.7. The West Loggia is original to the hotel construction and is to remain.
123 Work associated with existing chimneys poses an inherent safety risk to areas within the zone of influence below the work.
Please confirm that those areas can be vacated and safed off during the construction above.
The NPS and concessionaire will collaborate with the construction contractor to ensure safe work zones are established for the chimney work.
124 Regarding access to high chimney work associated with Bid Option C, will access to the existing interior service elevator and access to existing patios be made available, or will all access to such areas be required to be made from the exterior of the building? Yes, however access will need to be coordinated with the NPS and concessionaire.
125 Due to the significant amount of additional cost associated with providing exterior access, please confirm that openings can be made in the roof to allow access to/from the attic for the chimney repair scope of work, if required
Yes. Please provide a description of your proposed attic access in your technical approach narrative.
126 Section 08 01 52 Repair and Restoration of Wood Windows
2.3 Glazing Materials – B Replacement Glass
Specifications call out for replacement of glass over 16 SQFT in area. To provide clear tempered glass to match existing in size, thickness, color, and texture.
Does the current glass have a wavy distorted look to it?
The manufacturing of glass in the “olden days” had a wavy look to the glass with a semi distortion look. Present day glass manufacturing is non‐wavy, clear and non‐distorted.
Please advise it is critical to match existing due to limited glass companies that
ARG: Existing large panes of glass do not have a wavy or distorted appearance. The glass for window #10 in the Dining Room was relatively recently replaced with clear tempered glass and its appearance is indistinguishable from the historic glass.
127 Specifications states an asbestos report survey dated October 22, 1990 has been prepared by Management services, Inc.
Please provide a copy of the report.
Report provided in Amendment No. 1 6
128 Will there be a background check for construction workers onsite? No. 6 129 There is a range of temperature the contractor needs to follow for certain work scope specifications. Please provide a degree day chart for the year in Yosemite as it might interfere with the construction schedule.
Consult national weather service data. 6
130 Please provide an award date as the contractor needs to plan accordingly for lodging/booking. Yosemite could get busy certain times of the year. If awarded late, will the contractor be compensated a change order for lodging?
We anticipate an award date in late July. 6
131 Will fire suppressions need to be set up for the onsite work. The existing building has a supression system. Temporary standpipes and hoses to be provided in locations where the existing supression system is deactivated to implement the project improvements. Temporary fire protection will be required. Refer to specification section 01 35 23, Part 3.2; 01 35 50, Part 3.4E; 01 35 91, Parts 3.6 & 3.7; 01 50 00 Part 3.4J
132 Will the 8‐week closure be recurring? No. 6 133 Is there a report on lead paint for the exterior/interior of the building? There is not a lead paint survey report available. The contractor shall assume that lead paint is present. Sanding or other activities that generate dust from confirmed or assumed LCP‐coated building components must be conducted per the requirements of the Occupational Safety and Health Administration (OSHA) Lead‐in Construction standards in Title 29 Code of Federal Regulations (CFR) Part 1926.62.
134 Is the current roof tile over the dining room still available? Has the hotel had to repair that roof in the past? Does the hotel have any of the current tile left over or stock piled?
The most recent re‐roof of the hotel was completed in 2010 by Martech Associates, Millheim, PA, under contract to the previous concessioner. There is no left‐over slate available. The slate was sourced from New England Slate, the same source of the hotel's original slate, and consists of four colors 1. Semi‐Weathering Grey/Green 2. Royal Purple 3. Semi‐Weathering Grey/Black 4. Unfading Mottled Green and Purple.
135 Stone Cottage Chimney S2.2. what is the substructure of the chimney made of and how thick is it? DEG: The original construction drawings show a one foot concrete slab foundation. 6 136 Detail 5 A93 Weep hole detail. The mentioned detail shows the weep hole weeping onto the pan deck on foam insulation and can get between the pan and the insulation and eventually rot the metal decking. Is this correct?
ARG: Weep hole note omitted in 5/A9.3 in Addendum 3. 6 Revised drawing A9.3
137 Missing detail on sheet A1.6 note # 9. The note calls out “NOT USED” However the sheet shows arrow indicators pointing out items that need to be identified under note # 9. Please advise
ARG: Use of keynote 9 on A1.6 has been deleted in Addendum 3. 6 Revised drawing A1.6
138 Sheet A1.7 note 12. Says to “remove wood shed completely” including SOG. However, the legend shows selected demo only?
If I am leaving selected wall framing, what is the limit of the concrete removal limit from the wall to the saw cut line?
ARG: Note 12 revised to “remove wood shed as indicated” in Addendum 3. 6 Revised drawing A1.7
139 Owners’ construction schedule outline. This schedule outline does not mention the civil or utility improvements. What is the civil work time line? There is 5 months’ time between the hotel closure and June 28th the 10th day after the NTP is granted is the mobilization. Can we start on the civil, concrete walk demo and grading before the shut down?
Yes, civil utility work can begin prior to the shut down. Some of the concrete terrace replacement work may be accomplished prior to the shutdown, however the timing of that work would need to be coordinated with the concessionaire and sequenced to minimize visitor impacts. Because the work will impact public access to the outside, the extent and sequence to execute the terrace replacement scope needs to be closely coordinated with the concessionaire. While the temporary kitchen is in operation (west side) the concessionaire desires to provide public access to the east terraces.
Because these terraces are the primary outdoor access from the hotel’s interior public spaces, the schedule for this work must be coordinated with hotel operations. It is anticipated that this work will be phased (east, south, west sections) to allow partial guest access during the work.
140 Form 1442 funding verbiage clarification. According to the verbiage, the funding may or may not be available. Do we have an update on this issue? When should we know if this will be funded?
The NPS has a high level of confidence that the project will be fully funded. 6
141 Is there micropiles required? If so is there a foundation plan showing pile locations and loads? Micropiles are not required. 6 142 Is the fire alarm system a Notifier or Siemens? Notifier 6 143 Amendment 6 revision to sheet A7.2 Kitchen Finish Schedule removed two notes (General Finish Note #3 and note below
Finish Schedules) which had indicated that the insulated panels associated with several rooms in the kitchen area shall be provided by others. This deletion conflicts with the remainder of the drawing package (various elevations, sections, key notes, etc.) which still indicate that the insulated panels/ cooler units are NIC. Please confirm that all cooler units and associated refrigeration equipment are NIC. If the NPS requires the cooler units to be part of this project, please allow the contractors to provide an allowance for this added scope of work due to the timing of the release of Amendment 6 relative to the bid due date.
The insulated panels/cooler units are part…