This document contains three price schedule templates for federal construction contracts. The first template is for a seismic strengthening and kitchen renovation project at the Ahwahnee Hotel in Yosemite National Park. It includes 16 base line items and 4 option line items covering work such as structural bracing, fireproofing, and equipment anchoring. The second template is for a visitors center at Old Faithful in Yellowstone National Park, with 4 base line items and 2 option line items for items like a geothermal system. The third template is for a design-build project in Yosemite Valley, with 2 base line items to cover design and construction and 1 option line item for a photovoltaic system. All templates require offerors to provide lump sum pricing for base line items and unit prices as applicable, with instructions for calculating total proposed prices for base work and options.
View the file
Other files
Show 40 more
Latest 50 of 64 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| CONTRACT PRICE SCHEDULE |
| SOLICITATION NUMBER: |
| PARK - PMIS: YOSE 154910B |
| DEVELOPED AREA: Yosemite Valley |
| PROJECT TITLE: The Ahwahnee Seismic Strengthening and Kitchen Floor Replacement |
| 3/17/2022, revised 3/30/22 |
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. |
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. |
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Kitchen Renovation & Floor Replacement | 1 | Lump Sum | $ - 0 | $ - 0 |
| 2 | Shearwall & Truss for Dining Rm Bracing | 1 | Lump Sum | $ - 0 | $ - 0 |
| 3 | Insulate Kitchen Attic | 1 | Lump Sum | $ - 0 | $ - 0 |
| 4 | Kitchen Attic Fireproofing - Allowance | 2625 | Contact Sq Ft | $ - 0 | $ - 0 |
| 5 | Dining Room Seismic Bracing & Associated Work | 1 | Lump Sum | $ - 0 | $ - 0 |
| 6 | Dining Room AHU & Ducting | 1 | Lump Sum | $ - 0 | $ - 0 |
| 7 | South Wing Gypsum Block Bracing and Shearwalls | 1 | Lump Sum | $ - 0 | $ - 0 |
| 8 | Exterior Stone Anchoring | 1 | Lump Sum | $ - 0 | $ - 0 |
| 9 | Hotel Chimney Seismic Bracing & Waterproofing | 1 | Lump Sum | $ - 0 | $ - 0 |
| 10 | Anchoring of Mech Equipment in Basement | 1 | Lump Sum | $ - 0 | $ - 0 |
| 11 | Replace Glazing for Seismic - Dining & Solarium | 1 | Lump Sum | $ - 0 | $ - 0 |
| 12 | Brace Walkway and Pin Porte Cochere Column Stone | 1 | Lump Sum | $ - 0 | $ - 0 |
| 13 | Brace Cottage Chimneys | 1 | Lump Sum | $ - 0 | $ - 0 |
| 14 | Replace Terrace Concrete & Associated Work | 1 | Lump Sum | $ - 0 | $ - 0 |
| 15 | Replace Maintenance Shed | 1 | Lump Sum | $ - 0 | $ - 0 |
| 16 | Replace Waterproofing at Stone Piers | 1 | Lump Sum | $ - 0 | $ - 0 |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 16) ------------------------------------ | $0 | ||||
| 17 | OPTION A, Attic Fireproofing (NIC Kitchen) - Allowance | 7370 | Contact Sq Ft | $ - 0 | $ - 0 |
| 18 | OPTION B, Rehabilitate Windows at 1st Floor, Colonial, & Tressider | 1 | Lump Sum | $ - 0 | $ - 0 |
| 19 | OPTION C, Rehab Ext Wood Columns, Soffits, & Rafter Tails | 1 | Lump Sum | $ - 0 | $ - 0 |
| 20 | OPTION D, Add Epoxy Flooring - Dry Storage/Corridor | 1 | Lump Sum | $ - 0 | $ - 0 |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 17 through 20) ------------------------------------ | $0 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 20) ----------- | $0 | ||||
| All measurement and payment information is included in the project specifications, Section 01 27 00. |
PARK - PMIS
CPS - &P of &N
Design-Bid-Build Sample
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: N2011080811 | |||||
| PARK - PMIS: YELL 012345 | |||||
| DEVELOPED AREA: Old Faithful | |||||
| PROJECT TITLE: Johnstonian Visitors Center | |||||
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identify why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | L.F. | - 0 | |
| 3 | Sanitary Sewer line | 200 | L.F. | - 0 | |
| 4 | Rock Excavation | 150 | C.Y. | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) ------------------------------------ | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | $ - 0 | |
| 6 | OPTION B, Photovoltaic system | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 5 and 6) ------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) ------------- | $0.00 | ||||
| All measurement and payment information is included in the project specifications, Section 012700. |
YELL - 012345
CPS - &P
Design-Build Sample
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: N2011080811 | |||||
| PARK - PMIS: YOSE 012345 | |||||
| DEVELOPED AREA: Yosemite Valley | |||||
| PROJECT TITLE: Design and Build a New Structure | |||||
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | $0.00 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 2) --------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | $0.00 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3 ) ----------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 3) ------------ | $0.00 |
YOSE - 012345
CPS - &P