FINAL CD’s
Volume I
Mammoth Hotel Rehabilitation
Phase II
A&E Project # 15021.40
February 28, 2018
A DEEP UNDERSTANDING OF DETAIL
A&E 15021.40 MAMMOTH HOT SPRINGS HOTEL REHABILITATION - PHASE II
MAMMOTH HOT SPRINGS
YELLOWSTONE NATIONAL PARK, WYOMING
TABLE OF CONTENTS – VOLUME 1 TOC - 1
TABLE OF CONTENTS – VOLUME 1
The following listed documents comprise the Table of Contents for the MAMMOTH HOT SPRINGS
HOTEL REHABILITATION – PHASE II, MAMMOTH HOT SPRINGS, YELLOWSTONE NATIONAL
PARK, WYOMING. If the numerical sequence of Sections or Divisions is interrupted, such interruptions are intentional.
TABLE OF CONTENTS
SPECIAL NOTICES
WASTE REDUCTION NOTICE
UTILITY SHUTDOWN NOTICE
OVERSIZE TRAVEL RESTRICTIONS
FIRE WATCH NOTICE
HOT WORK PERMIT
TECHNICAL SPECIFICATIONS
DIVISION 01 – GENERAL REQUIREMENTS
010100 SUMMARY OF WORK
011216 WORK SEQUENCING
011700 ACCIDENT PREVENTION
012601 CONTRACT MODIFICATION PROCEDURES
012700 DEFINITION OF CONTRACT LINE ITEMS
013100 PROJECT MANAGEMENT AND COORDINATION
Request for Information (RFI Form)
013200 SCHEDULES
013216 CONSTRUCTION SCHEDULE
013233 PHOTOGRAPHIC DOCUMENTATION FOR HISTORIC PRESERVATION
PROJECTS
013323 SUBMITTAL PROCEDURES
013513.22 ARCHEOLOGICAL PROTECTION
013523 SAFETY REQUIREMENTS
013591 HISTORIC PRESERVATION TREATMENT PROCEDURES
014000 QUALITY REQUIREMENTS
Contractor’s Quality Control Daily Report Form (2 pgs.)
Daily Test Report Information Sheet
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
015213 FIELD OFFICES AND SHEDS
015300 BARRIERS
015700 TEMPORARY EROSION CONTROL
015719.11 INDOOR AIR QUALITY MANAGEMENT
015719.12 NOISE & ACOUSTICS MANAGEMENT
015723 TEMPORARY STORM WATER POLLUTION PREVENTION
015750 TRAFFIC CONTROL
016700 PRODUCT REQUIREMENTS
Substitution Request Form
017000 PROJECT CLOSEOUT
017200 FIELD ENGINEERING
017329 CUTTING AND PATCHING
TABLE OF CONTENTS – VOLUME 1 TOC - 2
017340 EXECUTION
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
Appendix A Appendix B
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
Equipment Data Sheet
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
018113 SUSTAINABLE DESIGN REQUIREMENTS
019113 GENERAL COMMISSIONING REQUIREMENTS
019114 TOTAL BUILDING COMMISSIONING
DIVISION 02 – EXISTING CONDITIONS
024119 SELECTIVE DEMOLITION
028200 ABATEMENT OF ASBESTOS-CONTAINING MATERIALS
028300 LEAD-BASED PAINT STABILIZATION AND COMPONENT REMOVAL
028400 REMOVAL OF POLYCHORINATED BIPHENYL (PCB) CONTAINING
MATERIALS
028700 REMOVAL OF MERCURY-CONTAINING MATERIALS
DIVISION 03 – CONCRETE
033000 CAST-IN-PLACE CONCRETE
033100 CONCRETE FOR SITE STRUCTURES
033500 CONCRETE CURBS, SIDEWALKS, AND ENTRY PADS
DIVISION 05 – METALS
050373.15 HISTORIC METAL BATHROOM FIXTURE REFINISHING
051200 STRUCTURAL STEEL FRAMING
055000 METAL FABRICATIONS
055100 METAL STAIRS
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY
061600 SHEATHING
061800 GLUED-LAMINATED CONSTRUCTION
062013 EXTERIOR FINISH CARPENTRY
064023 INTERIOR ARCHITECTURAL WOODWORK
064113 WOOD-VENEER-FACED ARCHITECTURAL CABINETS
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
070150.19 PREPARATION FOR REROOFING
071113 BITUMINOUS DAMPPROOFING
071326 SELF-ADHERING SHEET WATERPROOFING
072100 THERMAL INSULATION
072500 WEATHER BARRIERS
072600 VAPOR RETARDERS
072715 NON-BITUMINOUS SELF-ADHERING SHEET AIR BARRIERS
075323 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING
076200 SHEET METAL FLASHING AND TRIM
077200 ROOF ACCESSORIES
078413 PENETRATION FIRESTOPPING
079200 JOINT SEALANTS
TABLE OF CONTENTS – VOLUME 1 TOC - 3
DIVISION 08 – OPENINGS
080314 HISTORIC TREATMENT OF WOOD DOORS
080352 HISTORIC TREATMENT OF WOOD WINDOWS
081113 HOLLOW METAL DOORS AND FRAMES
081433 STILE AND RAIL WOOD DOORS
083113 ACCESS DOORS AND FRAMES
085200 WOOD WINDOWS
086101 WOOD WINDOW WALLS
087100 DOOR HARDWARE
088000 GLAZING
088813 FIRE-RESISTANT GLAZING
DIVISION 09 – FINISHES
092116.23 GYMPSUM BOARD SHAFT WALL ASSEMBLIES
092613 GYMSUM VENEER PLASTERING
092900 GYPSUM BOARD
093013 CERAMIC TILING
096400 WOOD FLOORING
096513 RESILIENT BASE AND ACCESSORIES
096516 RESILIENT SHEET FLOORING
096816 SHEET CARPETING
099113 EXTERIOR PAINTING
099123 INTERIOR PAINTING
099300 STAINING AND TRANSPARENT FINISHING
DIVISION 10 – SPECIALTIES
101419 DIMENSIONAL LETTER AND PANEL SIGNAGE
102600 WALL AND DOOR PROTECTION
102800 TOILET, BATH, AND LAUNDRY ACCESSORIES
102819 TUB AND SHOWER ENCLOSURES
104413 FIRE PROTECTION CABINETS
104416 FIRE EXTINGUISHERS
DIVISION 11 – EQUIPMENT
111313 LOADING DOCK BUMPERS
111319 STATIONARY LOADING DOCK EQUIPMENT
DIVISION 12 – FURNISHINGS
123661 SIMULATED STONE COUNTERTOPS
DIVISION 14 – EQUIPMENT
14123.16 MACHINE ROOM-LESS ELECTRIC TRACTION PASSENGER ELEVATORS
END OF TABLE OF CONTENTS – VOLUME 1
A&E 15021.00 MAMMOTH HOT SPRINGS HOTEL REHABILITATION - PHASE 1
WASTE REDUCTION NOTICE - 1 -
WASTE REDUCTION NOTICE
Contractor shall identify all opportunities to reduce the volume of waste from construction operations at each site the contractor is operating in the Park. Contractor must divert, at minimum, at least 75% of resulting waste from landfill disposal through salvage/recycling. Contractor must complete a Waste Reduction Plan before Work commences, showing how Contractor will meet these requirements.
Contractor must also submit a monthly project report detailing all activities related to waste minimization and recycling, including costs, weight, and volume of materials, methods of disposal and diversion rates.
Contractor must maintain third-party receipts, for the duration of the Agreement, showing weights of materials disposed and tip fees. The Contacting Officer maintains the right to review all such documentation.
Refer to Section 017419 “Construction Waste Management and Disposal” for additional requirements.
UTILITY SHUTDOWN NOTICE - 1 -
UTILITY SHUTDOWN NOTICE
Contractor shall be responsible for providing a minimum 72-hour advanced written notice to the Contracting Officer for any interruption of utility service to the building during the entire construction period – without exception.
Coordinate with the Contracting Officer to establish necessary temporary utility service to occupied areas of the building during the temporary shutdown period(s).
Contractor shall pay all costs associated with setting and removing temporary utility service to occupied areas of the building.
Scheduled utility shutdowns shall be approved or disapproved, in writing, by the Contracting Officer.
SIZE AND WEIGHT LIMITATIONS OF TRAFFIC ON YELLOWSTONE NATIONAL PARK ROADS
AN OVERSIZE LOAD IS ONE THAT IS WIDER THAN 8’6” OR LONGER THAN 75’ LEGAL SIZE AND UNDER CAN TRAVEL PARK ROADS1
STATUTORY SIZE AND WEIGHT LIMITS ESCORT REQUIREMENTS SIGN REQUIREMENTS
Width:
8’7” to 10’ 1
10’1” to 11’ 1,2
11’1” to 18” 1, 2
None required.
Front required. Rear required also if load extends over center line, road closures may be required 1,2
Front and rear required, road closures may be required 1,2
All Oversize Loads
Front and rear signs which read “OVERSIZE
LOAD”; yellow, at least 60” wide by 10” high, with black lettering 8” high by 1” wide. Signs must be clean, fully visible, and shall not cover lights on vehicle.
Escort Vehicles
Signs that read “OVERSIZE LOAD” visible to approaching traffic; yellow, at least 60” wide by 10” high, with black lettering 8” high by 1” wide. Signs must be clean, fully visible, and shall not cover lights on vehicle.
Height: 13’6” and Over
(OF Overpass 16’ Northbound, 17’ Southbound)
It is the responsibility of permittee to ensure that load can safely traverse planned route. If it is necessary to lift overhead wires, cost will be borne by permittee.
Length: Total longitudinal dimension of any vehicle or combination of vehicles, including power unit or any load holding device.
75’- Combined length in a truck-tractor, semi-trailer, trailer combination: 48’ maximum for semi-trailer and 40’ maximum for trailer. The longest trailer, not including connecting mechanisms shall be the first unit behind the truck tractor.
75’ to 99’11” 1,2
100’ and over 1,2
No combination of vehicles shall consist of more than three single vehicles.
None required.
Front required, road closure/s may be required. 1,2
Front and rear required, road closure/s may be required. 1, 2
Weight:3 single axle 20,000lbs two-axle tandem 34,000lbs three-axle tandem 42,000lbs
No escorts are required based on vehicle weight 3
1. ALL OVERSIZE travel restricted to night travel- 9:00 p.m. to 9:00 a.m. between Friday of Memorial Day Weekend and Labor Day. See Reverse.
2. Contact the Visitor Services Office for approval (307) 344-2115 or 344-2106. If transport of oversize loads necessitates a road closure, the cost will be borne by the permittee.
3. Weight limit restrictions apply to some park bridges, check with the Visitor Services Office at (307) 344-2115.
Until late in June, a weight limit of 350 lb./inch width of tire is in effect. After road conditions improve (which is determined by the Chief of Maintenance), the limitations are raised to 450 lb./inch. Gross vehicle weight may exceed 80,000 lbs. only if it is in accordance with Montana and Wyoming State requirements pertain to number of axles and bridge length
(distance between the extremes of any group of two or more consecutive axles) and weight does not exceed Federal Highway Load Factor Limits for specific park bridges.
Gross weight is defined as the total weight of a vehicle and vehicle combinations including the weight of any load carried in or on a vehicle or vehicle combination.
OVERSIZE RESTRICTIONS
1. Permits are required for vehicles and loads that exceed the above statutory limits.
2. Due to peak visitation from Friday before Memorial Day through Labor Day, travel for any vehicles exceeding the statutory limits is restricted to night- 9:00 p.m. to 9:00 a.m. If an oversize loaf requires temporary road closures, the National Park Service will determine the time that travel is permitted.
3. Vehicles transporting petroleum products within the park shall be prohibited during peak visitation times and dates and must meet requirements in Yell-307.
4. All oversize loads or cargoes or portions thereof will be adequately lashed or secured to the bed of the vehicle.
5. Oversize movements must display yellow warning signs that read “OVERSIZE LOAD” visible from the front and rear. The signs must be at least 60 inches wide by 10 inches high, and the lettering must be black, 8 inches high, with 1-inch lettering. The signs shall be kept in a clean condition, fully visible, and shall not cover lights on the vehicle.
6. Escort vehicles must display yellow warning signs, visible to approaching traffic that reads “OVERSIZE LOAD”. The signs must be at least 60 inches wide by 10 inches high, and the lettering must be black, 8 inches high, with 1-inch lettering. The signs shall be kept in a clean condition, fully visible, and shall not cover lights on the vehicle.
7. All headlights, tail lights, and running lights of all escort and oversize movements will be on at all times while vehicle is on roadway.
8. Projections extending more than 12 inches beyond the body of the vehicle or load must be marked with a clean, bright red flag at least 12 inches square.
9. Maximum speed of any oversize vehicle or vehicles shall be 35 mph.
10. Oversize and escort vehicles will use roadside turnouts and parking areas whenever possible to permit passage of vehicles and to maintain a free flow of traffic.
12. Any equipment breakdowns or stoppages involving partial or complete blocking of roadway will necessitate flagmen and adequate markers on each side of the convoy unit to allow safe passage of other traffic.
The above special requirements shall not apply to snow removal equipment or to the transportation of petroleum or asphalt products required to repair or maintain roads within
Yellowstone National Park. These vehicles will adhere to traffic control regulations specified in NPS-50.
FIRE WATCH NOTICE - 1 -
FIRE WATCH NOTICE
Contractor shall be responsible for providing a qualified “Fire Watcher,” an individual responsible for 24-hour, 7-days per week fire-watch when the existing automatic fire sprinkler protection is disabled or not operable at anytime during the construction period – without exception.
Per NFPA 1 a “Fire Watcher” is:
“A person assigned to be in an area for the express purpose of notifying the fire department of an emergency, preventing a fire from occurring, extinguishing small fires, or protecting the public from fire or life safety dangers addressed in this Code. Specific requirements for personnel, their training, and any equipment are found in the appropriate sections of this Code.”
Contractor shall provide written 72-hours advanced notice to the Contracting Officer prior to enacting a fire-watch period. Contractor shall submit to the Contracting Officer all requirements and applicable training certificates for “Fire Watcher” personnel.
Contractor shall insure no “hot work” is performed in any area where the existing automatic fire sprinkler system is disabled or not operational. Contractor to reference mandatory NFPA 1, Chapter 41.2.3 “Fire Safety During Construction” and at a minimum, comply with the following: Fire Watch is required in any area exceeding 400 square feet of floor area (including, but not limited to, crawlspaces, attics, and concealed combustible areas) not protected by the existing enabled automatic fire sprinkler system or new operable automatic fire sprinkler system.
At all times during a period of fire watch, the contractor shall provide adequate fire extinguisher quantities and locations, as required by Specification Section 024119 “Selective Demolition” and Section 015000 “Temporary Facilities and Controls.” Coordinate with the Contracting Officer to identify a designated prior-approved authority who shall be in immediate radio contact with Fire Watch personnel at all times during a period of fire watch. Fire Watch personnel shall be provided with adequate 2-way radios to provide immediate notification to a prior-approved authority
INSTRUCTIONS
BEFORE INITIATING HOT WORK, ENSURE PRECAUTIONS ARE IN PLACE!
MAKE SURE AN APPROPRIATE FIRE EXTINGUISHER IS READILY AVAILABLE.
Required Precautions Checklist
SIGNED:
Hot Work Permit
This Hot Work Permit is required for any operation involving open flames or producing heat and/or sparks. This includes, but is not limited to: Brazing, Cutting, Grinding, Soldering, Thawing Pipe, Torch Applied Roofing, and Cadwelding.
□ Available sprinklers, hose streams and extinguishers are in service and operable.
□ Hot Work equipment in good repair.
Requirements within 35 ft. (10 m) of work
□ Flammable liquids, dust, lint and oil deposits removed.
□ Explosive atmosphere in area eliminated.
□ Floors swept clean.
□ Combustible floors wet down, covered with damp sand or fire-resistant sheets.
□ Remove all combustibles where possible.
Otherwise, protect with fire-resistant tarpaulins or metal shields.
□ All wall and floor openings covered.
□ Fire-resistant tarpaulins suspended beneath work.
Work on walls or ceilings/enclosed equipment
□ Construction is noncombustible and without combustible covering or insulation.
□ Combustibles on other side of walls moved away.
□ Danger exists by conduction of heat into another area.
□ Enclosed equipment cleaned of all combustibles.
□ Containers purged of flammable liquids/vapors.
Fire watch/Hot Work area monitoring
□ Firewatch will be provided during and for
(30 minutes) after work, including any coffee or lunch breaks.
□ Firewatch is supplied with suitable extinguishers.
□ Firewatch is trained to use equipment and in sounding alarm.
□ Firewatch may be required for adjoining areas, above, and below.
□ Monitor Hot Work area for 30 minutes after job is completed.
Other Precautions Taken
□ Confined space entry permit required.
□ Is area protected with smoke and heat detection.
□ Ample ventilation to remove smoke/vapor from work area.
□ Lockout/tagout required.
THIS PERMIT IS GOOD FOR ONE
DAY ONLY!
PERMIT
EXPIRES
IN THE EVENT OF AN EMERGENCY DIAL 911 AND USE
YOUR FACILITIES EMERGENCY PROCEDURES.
A. Verify precautions listed at right (or do not proceed with the work).
B. Complete and retain.
C. Issue COPY to person doing job.
DATE: LOCATION:
HOT WORK BEING DONE BY
□ EMPLOYEE
□ CONTRACTOR _____________________
I verify the above location has been examined, the precautions checked on the required precautions checklist have been taken to prevent fire, and permission is authorized for work.
NAME OF PERSON DOING WORK:
NAME OF FIREWATCHER:
DATE: TIME:
NATURE OF PROJECT:
051517 010100 - 1
SUMMARY OF WORK
SECTION 010100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. The Work of this Contract includes, but is not limited to, structural renovation and rehabilitation of the National Register Listed Mammoth Hot Springs Hotel and adjacent grounds. Mammoth Hot Springs Hotel is located in the Mammoth Historic District, Mammoth Hot Springs in Yellowstone National Park. The project consists of approximately 56,000 square feet of gross construction area over four floors and one basement/crawlspace. The Work generally consists of demolition of existing finishes and constructions, interior and exterior reconfigurations, new structural upgrades and assemblies, new mechanical systems, new electrical and communication systems, new life safety systems, new and restored architectural finishes and components, new exterior windows, roofing upgrades, minor additions, new passenger elevator, site utilities, paving, loading dock and equipment, site furnishing and appetences, and other miscellaneous work indicated.
B. The entire Project consists of multiple phases of Work. Phase II Work shall be conducted in one
(1) phase under one (1) Prime Contract.
C. The Work generally consists of demolition of existing finishes and constructions, interior and exterior reconfigurations, new structural upgrades and assemblies, new mechanical systems, new electrical and communication systems, new life safety systems, new and restored architectural finishes and components, new exterior windows, roofing upgrades, minor additions, new passenger elevator, site utilities, paving, loading dock and equipment, site furnishing and appetences, and other miscellaneous work indicated.
D. Reference Complete Construction Documents including the Contract for Construction, Construction Drawings, Project Manuals, and Addenda issued during the bidding process for additional requirements of the Work.
1.2 LOCATION & ACCESS
A. The Work to be completed is at a location inside Yellowstone National Park, Wyoming. The National Register Listed Mammoth Hot Springs Hotel is located on Grand Loop Road also known as US Highway 89 in the Mammoth Hot Springs area approximately 6 miles inside of the North Entrance to Yellowstone National Park.
B. Grand Loop Road and the North Entrance to Yellowstone National Park is open all year to vehicle travel. Roads from other entrances of the Park are open seasonally to wheeled vehicles.
For safety considerations, temporary road closures due to weather over high mountain passes and road snow removal scheduling are at the discretion of the Government. As a result, delays due to visitor traffic and road construction may occur, contact the Park’s Visitor’s Service Office at 307-344-2107 for general road construction and maintenance schedules and Park road opening and closing schedule dates. Road information during off-hours may be obtained from the Park’s Communication Center at 307-344-7381. Since most of the construction work will be completed during the winter season there are additional requirements.
051517 010100 - 2
C. Contractor shall have full use of Project site for construction operations during the construction period. Contractor's use of Project site is limited only by Contracting Officer’s right to perform work or to retain other contractors on portions of the Project and the Contact Officer’s right to access to the Project site for maintenance, observation, and emergency response. Reference the Construction Drawings for definition of site boundaries specific to the Project.
D. Maintain access and emergency systems in safe and operable conditions as required by Authorities Having Jurisdiction at all times. Keep driveways, roadways, and entrances serving the premises and adjacent locations clear and available to Government, Government’s Employees, Concessionaire, Concessionaire’s Employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.3 USE OF THE PREMISES
A. Contractor shall coordinate Work of this Contract with the Contracting Officer.
1. Additional entities requiring coordination through the Contracting Officer include, but are not limited to the National Park Service (NPS), Xanterra Parks & Resorts, and other Authorities Having Jurisdiction (AHJ).
B. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during various times during the construction period, with the exception of areas under construction.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
b. Maintain largest number of parking spaces possible adjacent to the Mammoth Hot Springs Hotel during operational periods until closure for public and government access. Coordinate work and parking space provisions with requirements of sequencing drawings for road relocation. Provide plan for review and approval prior to closure of existing parking spaces. Following closure of the existing Mammoth Hot Springs Hotel all parking spaces shall be free for the Contractor’s exclusive use within the project site.
D. During the Work the Contractor shall:
1. Cooperate with all entities listed above or engaged by the Contracting Officer to minimize conflicts and access, security, controls and protection in addition to guest services and ongoing building operations.
2. Reach Substantial Completion and remediate any and all non-conforming or incomplete Work and perform all prerequisites to the issuance of a Certification of Substantial Completion on or before the dates indicated.
3. Meter and pay utilities required during the Contractor’s Work for the Project.
4. Coordinate all construction activities, deliveries and the like with the operation of adjacent facilities and area guest services.
051517 010100 - 3
5. Keep driveways, fire lanes, and entrances serving the premises and adjacent areas clear at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
E. Maintain entire building in a weathertight condition throughout construction period. Repair damage caused by construction operations to the satisfaction of the Contracting Officer at no additional cost.
F. Contractor shall be responsible for all snow removal from adjacent maintained roadways to the project site and within the project site for the duration of the Work.
G. Construction Camp: Establishment of a camp within the park will not be permitted.
1.4 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts.
Coordinate the Work of this Contract with work performed under separate contracts.
1.5 CONSTRUCTION RELATED DAMAGE
A. Construction Related Damage: Contractor agrees to pay the Contracting Officer all damages and costs incurred by the Contracting Officer or caused by the Contracting Officer by reason of the Contractor’s construction activity related damage.
1.6 WORK RESTRICTIONS
A. Cleaning General: Contractor shall clean the Project site daily and/or multiple times daily due to construction operations, dust generated, and/or debris generated to prevent tracking dirt and debris to areas outside of the Project site. Provide additional walk-off mats at entrances, containment curtains, protective enclosures, and any other Contracting Officer approved dust, dirt, and debris containment operations necessary to maintain a clean, neat, orderly, and safe Project site.
B. Work Restrictions General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of Authorities Having Jurisdiction.
C. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 7:00 p.m., Monday through Friday, unless otherwise indicated.
D. Existing Utility Interruptions: Do not interrupt utilities serving adjacent facilities occupied by Contracting Officer or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Obtain written permission from the Contracting Officer before proceeding with utility interruptions.
051517 010100 - 4
E. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
1. Smoking is not allowed in this Project site.
2. Prohibit on-property smoking within 25 feet of any entry, any existing or new outdoor air intake, any operable windows.
F. Contractor, Contractor’s personnel, and Subcontractors shall comply with all applicable federal, state and local environmental laws and regulations, including but not limited to those involving hazardous waste. The Contractor, Contractor’s personnel, and Subcontractors shall participate in all meetings necessary or requested with Contracting Officer and any federal, state, or local government official responsible for environmental enforcement or inspection to discuss compliance with the obligation set forth in this paragraph. Contractor shall make all reports and require subcontractors to make all reports requested by the Contracting Officer or required by law concerning the obligations set forth in this paragraph.
1. Pollution of natural resources of air, land, and water by operations under this Contract shall be prevented, controlled, and abated in accordance with the rules, regulations, and standards adopted and established by the U.S. Government. Contractor shall provide such air, land and water pollution control measures required to comply with the minimum standards established by such agencies.
2. Contractor shall schedule and conduct operations so as to minimize erosion of soils and prevent sediment from entering the storm drainage system or washing to other low areas. Contractor shall incorporate all permanent erosion control features into the Work at the earliest practicable time, and provide such temporary control measures as may be needed during construction to serve until the permanent features are completed.
G. Contractor shall ensure proper continuous oversight of the execution of the Work as necessary to coordinate all construction activities of the Contractor’s personal, Subcontractor(s) engaged in the Work, and provide for necessary management activities and communications with Contracting Officer and Contracting Officer’s designees. Contractor shall provide for full project duration (Final Completion) a minimum of the following:
1. ONE (1) FULL-TIME CONTINUOUS ON-SITE PROJECT SUPERINTENDENT for Pro-ject construction oversight for the entire duration of Work including remediation work re-quired to meet the requirements for Final Completion.
2. ONE (1) PART-TIME CONTINUOUS PROJECT ENGINEER for Project management oversight including but not limited to shop drawings, quality control, schedules, RFIs/RFPs, change orders, pay requests, and other administrative work functions.
3. Personnel shall be properly trained and experienced in the position held. While sched-uled work operations are being conducted by the Contractor or prime-subcontractors, regardless of day or work hour, oversight by the Project Superintendent is required.
4. Management personal shall remain designated and actively involved with the daily opera-tions of the project from execution through Final Completion without change unless agreed to in writing by the Contracting Officer.
H. Contractor shall be responsible for the safety of all workers and the quality of all Work.
Contractor’s designated on-site Project Superintendent shall not be simultaneously employed as a laborer or subcontractor, and shall have not have the added responsibility of physically doing labor or craft skills that would deter from assigned management duties.
I. Work on Saturdays, Sundays, Recognized Federal Holidays, or at night may be performed only with prior consent of the Contracting Officer. The Contractor shall provide written notice 72 hours prior to work during these periods to the Contracting Officer. No Work will be approved during these time frames unless the Work is directly supervised by the Contractor’s Project
051517 010100 - 5
Superintendent and the crews that plan to work have recorded 40 regular hours over the previous five days OR the weather has precluded working those days. In case of legitimate emergencies, sound judgment shall be exercised.
J. Contractor shall be responsible for proper storage of materials within the construction limits indicated in the Drawings.
K. Unless otherwise noted, open flame or burning are NOT permitted in the building or on the Project site.
L. No signs or advertisements (except those specified herein) shall be displayed on the construction site, Contractor’s jobsite equipment, Contractor’s storage units or within the park unless approved by the Contracting Officer.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Construction access, timing, and completion of the Work shall be the responsibility of the Contractor within the following requirements and limits.
1. Work of this Contract is required to reach substantial completion by the dates established within the Contract. These dates are critical as Contracting Officer’s obligations for occupancy of the building in coordination with these dates cannot be changed.
2. Coordinate Work with the Contracting Officer by developing a “Work Plan.” The Work Plan shall document the scheduled, timely, diligent, and safe completion of the Project by the Date of Substantial Completion. The Work Plan shall contain, at a minimum, the following:
a. Coordinated construction schedule with sufficient detail to track major work activities of the Contractor and Subcontractor(s).
b. Plan for transportation and storage of materials and debris.
c. Plan for housing and/or transportation of assigned personal.
d. Plan for protection procedures.
e. Plan for Work sequencing and staging.
B. Contractor shall be required to assist the Contracting Officer’s asset decommissioning and tracking with regard to National Park Service owned and tracked property within the scope of this Project. A completed list of existing Assets will be provided by the Contracting Officer for purposes of tracking decommissioning and disposal. Contractor shall provide required information through the submittal process for all new assets required by the Contracting Officer to be added to Asset lists. Any item within the Work bearing a National Park Service Asset Property Number shall be maintained and disposed of in compliance with NPS requirements.
C. Project Superintendent shall be responsible for securing the Project site and staging areas at the end of each workday and shall coordinate with other Contractors on site and Contracting Officer to maintain security. All doors, windows, etc. shall be closed and locked. Power equipment used for construction activities shall be unplugged, flammable materials properly stored, equipment properly secured and locked, and ladders taken down and stored.
1.8 SPECIAL PARK REQUIREMENTS
A. Contractor shall make themselves aware of all special conditions and requirements for Working and staying within Yellowstone National Park. Contractor shall abide by all National Park Service requirements as applicable to the Work of this Project.
051517 010100 - 6
B. Contractor shall abide by the following during the operations within the Park:
1. Contractor shall supply a list of all Contractor and Subcontractor(s) employees and personnel to the District Ranger.
2. To prevent unnatural attractants to bears, no food, garbage, drinks, trash, or food or drink containers shall be placed outside trailers or buildings, except during actual use. Store lunch pails, food containers, and coolers inside vehicles or hard sided job trailers.
3. Bear-proof trash cans shall be provided by the Contractor for disposal of all food wastes.
All waste containers for food wastes not of bear-proof construction shall be located inside trailers or buildings.
4. All office trash and food wastes shall be placed in plastic bags before being dispensed of offsite.
5. Contractor shall ensure segregation of construction debris, recycling, and food wastes at all times.
6. All barbecue units or other food preparation devices shall be appropriately stored when not actively being used inside trailers and buildings.
7. Bird feeders are prohibited.
8. Pets are prohibited
9. Feeding of any wildlife is prohibited.
10. Any mishandling of garbage, trash, foods, and other potential animal attractants may result in Contractor or responsible personal receiving citation, fine, and or require appearance before the U.S. Magistrate.
11. All costs associated with bear and wildlife management actions resulting from mishandling of garbage, trash, food or other potential animal attractants shall be paid by the Contractor and/or Contractor’s or Subcontractor’s responsible personal.
12. Contractor shall require of all employees, Subcontractor’s personal, and other associated individuals living or working within the Park to attend a bear and wildlife orientation session presented by the National Park Service, and shall facilitate presentation of orientations by appropriate NPS personal.
C. Hauling Restrictions: Comply with all load restrictions in the hauling of materials. Load restrictions on Park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on Park roads is included in the front section of this Specification and/or may be obtained from the Park’s Visitor Service Office. A special permit will not relieve Contractor of liability for damage, which may result from moving of equipment or materials.
1. Contractor shall be responsible for direct coordination with the Park Visitor Services Office at least one (1) week prior to transporting of trailers, large cranes, or other oversize loads and equipment through the Park. This coordination is critical for smooth travel of the Contractor’s Vehicles. Immediate notification of any unforeseen delays is required. During high Park visitation periods, travel for any contractor vehicles exceeding the park limits shall be restricted to night travel. For oversize loads requiring temporary road closures, the park will determine the time that travel is permitted. Existing traffic and road construction schedules will influence the entrance gate and travel route to be used.
2. Park’s Visitor Service Office (VSO) at Mammoth Hot Springs can be reached at (307-344- 2107).
D. Winter Operations: Grand Loop Road from Gardiner Montana to the Northeast Entrance of Yellowstone National Park at Cook City, Montana is maintained by the government, subject to closures from time to time.
1. Access to the Project Site during plowing operation periods shall be coordinated with the Contracting Officer. Access may be restricted to occur prior to or after snow plowing operations for the day.
051517 010100 - 7
2. Park regulations including hours of travel, speed, hauling/load limits, and safety regulations shall be followed at all times.
3. Contractor is responsible for any required snow removal from the Project site to an approved area.
E. Contractor shall be responsible for obtaining Yellowstone National Park entrance permits for all employees, including subcontractors and other project personal. Passes may be obtained through the Contracting Officer from the Visitor Services Office at no charge.
F. Importation of non-native species and materials:
1. All vehicles and equipment shall be inspected prior to entry into the Park for mud, weeds, and other substances. Prior to arrival at a park entrance, Contractor shall steam clean all earth-moving equipment (excluding hauling vehicles), clean hauling vehicles before their initial entrance into the Park. Subsequent returns will not require cleaning unless requested by the Contracting Officer. Notify the Contracting Officer and VSO a minimum of 48-hours prior to entry of vehicles to the Park.
2. Borrow and fill materials, fiber mulch, and other site materials must be certified weed-free and be acquired from sources approved by the Contracting Officer and NPS.
G. Contractor shall take every precaution and make every effort to protect the delicate environment of Yellowstone National Park. Store all fuel tanks and fuel trucks at staging areas. Use fuel absorbent mats when refueling equipment. Refuel equipment at locations to restrict spills from entering the environment. Dispose of all contaminated soils according to NPS, Federal, State, and Local regulations.
1.9 PRESERVATION OF NATURAL FEATURES
A. Confine all operations to work limits indicated. Prevent damage to natural surroundings, plants, and other vegetation. No activity, including vehicle or materials use or storage, will be allowed outside the work limits. Restore any damaged areas or features to the satisfaction of the Contracting Officer at no additional cost. The following steps, at a minimum, shall be taken by the Contractor to minimize environmental impacts:
1. Parking shall only be allowed within the limits indicated in the Drawings or on approved hard surfaces.
2. Provide temporary barriers to protect existing trees and plants especially root zones.
3. Do not remove, drive over with vehicles or equipment, injure, damage, or otherwise destroy trees or other plants without written approval from Contracting Officer.
4. Trenching routes and disturbance zones shall be flagged by the Contractor and approved in writing by the Contracting Officer prior to any trenching activities. All flagging and debris shall be removed from the area after the Work is complete and area shall be prepared for revegetation.
5. All access points to the project site and construction limits indicated in the documents shall be strictly adhered to. Contractor shall restore all disturbed site and construction areas upon completion of the Project to the satisfaction of the Contracting Officer at no additional cost to the Contract.
6. Do not fasten ropes, cables, or guys to existing trees.
7. Carefully supervise excavating, grading, filling, and other construction operations near trees, wetlands, and sensitive geological areas to prevent damage.
B. Maintain Project Fencing throughout construction activities. Install and maintain secure fencing for both security of the site, building and staging areas.
051517 010100 - 8
1.10 PUBLIC AND ADMINISTRATIVE ACCESS
A. Maintain safe access to all areas of the project site for administrative and other official business throughout duration of the Project.
B. Vehicular access to the Project site will be allowed for Contracting Officer’s Project personal and Project Design Team.
C. Contractor shall be responsible for maintaining the site and clearing snow from the Project site to an approved offsite area. Contractor shall not conduct snow removal activities on the Park roadways.
1.11 EXISTING UTILITIES
A. Notify Contracting Officer and utility companies of proposed locations and times of excavation activities.
1. Contractor shall be responsible for location and preventing damage to known utilities. If damage occurs, repair utility at no additional cost to the project.
2. Do not interrupt existing utility services to adjacent or occupied buildings without written approval from the Contracting Officer. Provide minimum 72-hour notice of any utility interruptions. Back-up or alternate utility services shall be provided by the Contractor for service interruptions lasting more than 4 hours. To the greatest extent possible, schedule utility shutdowns for off-season periods and times were weather conditions will not present a safety risk to buildings or persons.
B. All existing utility locations indicated within the documents are approximate. All existing utilities may not be shown.
C. Contractor shall contact Contracting Officer, utility company(ies), and Owners of other utilities for location information before conducting any excavation activities.
D. Contractor shall record meter readings prior to the start of work and pay for all utilities associated with the Work of this Project until the point of substantial completion.
E. Utility Contact List:
1. Primary Power: Wyoming one-call is 800-348-1030 for locates from North Western Energy.
2. Telephone: Branch of Information Systems Management, Mammoth at 307-344-2071 for locates from Century Link.
3. Water & Sewer: NPS Mammoth Area Maintenance Shop at 307-344-2430.
1.12 HISTORIC SITE
A. The Mammoth Hot Springs Hotel is recognized as a contributing resource to the Mammoth Historic District and is listed on the National Register of Historic Places. The building elements, not specifically called out for Work shall be protected from damage. Contractor shall be responsible for any damage and repair necessary due to execution of the Work as applicable to the historic building components to remain. All repairs shall be conducted in a manner complaint with the Secretary of the Interior’s Standards for Historic Preservation and acceptable to the Contracting Officer at no additional cost.
051517 010100 - 9
B. Each employee of the Contractor and their Subcontractors shall be informed of the historic significance of the Mammoth Hot Springs Hotel, site, grounds, and adjacent buildings and shall be made responsible for the protection of building fabric, natural resources, and artifacts. Found objects and other “collectible items” uncovered during the Work are the property of the National Park Service and as such are considered valuable. No such property shall be removed from the Project site by the Contractor, Contractor’s employees, or Subcontractors. If artifacts are discovered, stop work in the area and contact the National Park Service and Contracting Officer immediately.
C. Contractor shall protect adjacent historic fabric during demolition and construction, typical of this historic building, site, and staging area.
D. Contractor shall take every precaution to prevent damage to the existing historic building, furnishings, and interior and exterior finishes scheduled to remain in place including, but not limited to landscaping, parking areas, driveways and sidewalks, interior and exterior floor, wall and ceiling finishes, hardware, fixtures, furnishings, windows, doors and other miscellaneous construction. Provide adequate temporary protection to prevent damage during historic finishes, fixtures, accessories, materials and hardware, fixtures, and furnishings. Provide adequate temporary protection to prevent damage during selective demolition work and installation of temporary protection. Should accidental damage occur, coordinate repair procedures with the Contracting Officer. All repair work shall be conducted to the satisfaction of the Contracting Officer at no additional cost.
E. Contractor shall use extreme caution to insure protection of adjacent structures, structural components, landscape features, roads, sidewalks and adjacent buildings.
1.13 FIELD VERIFICATION
A. Contractor shall be responsible for field verification of existing conditions affecting the execution of the Work. Notify the Contracting Officer in writing of any conditions that may adversely affect the outcome of the Work.
B. Contractor shall document field conditions that vary from those indicated and provide written request for clarification to the Contracting Officer for conditions that may adversely affect the intended outcome of the Work.
1.14 CONFLICTS WITHIN THE CONTRACT DOCUMENTS
A. Where conflicts arise between the quantities, qualities, or requirements of Work within the contract documents, Contractor shall provide products and labor necessary to complete the greater quantity, higher quality, or more restrictive requirement of Work
B. Where conflicts arise between time requirements for execution of the Work or requirements thereof, the more beneficial time requirement to the Project and/or Contracting Officer shall prevail.
1.15 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
051517 010100 - 10
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings and/or commonly utilized in the construction industry.
1.16 SOILS INVESTIGATION REPORT
A. A geotechnical design report entitled Geotechnical Report for: Mammoth Hotel Mammoth Hot Springs, Wyoming dated June 2015 was prepared for this project by Craig R. Madson, P.E., Principal Geotechnical Engineer.
B. Electronic copies of report is available to plan holders from the Contracting Officer.
C. If conflicts occur between the reports and the drawings or specifications, the drawings and specifications govern.
1.17 HISTORIC STRUCTURES REPORT
A. A Historic Structures Report entitled Mammoth Hot Springs Hotel Historic Structures Report dated March 2015 was prepared for the building by A&E Architects, P.C. Missoula, Montana.
B. Electronic copies of report is available to plan holders from the Contracting Officer.
C. If conflicts occur between the reports and the drawings or specifications, the drawings and specifications govern.
1.18 LIMITED HAZARDOUS MATERIALS REPORT
A. A Limited Hazardous Materials Inspection Report entitled Limited Hazardous Materials Inspection Rehabilitation Phase II Mammoth Hotel report dated January 9, 2017 was prepared for for Xanterra Parks & Resorts by Tetra Tech Inc. Billings, Montana.
B. Electronic copies of report is available to plan holders from the Contracting Officer.
C. Information is provided solely for informational purposes. Contractor shall make themselves aware of all potential hazardous materials within the area of work and take steps to provide for the safe execution of thereof.
051517 010100 - 11
1.19 WARRANTY
A. Warranty & Service: Contractor shall warranty all materials, equipment, and labor for one (1) year following the date of Substantial Completion.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END SECTION 010100
102717 011216 - 1
WORK SEQUENCING
SECTION 011216 – WORK SEQUENCING
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes the general requirements and restrictions for work sequencing & phasing operations on the project site.
B. The project phasing information presented within the Contract Documents provide the Contracting Officer’s anticipated phasing utilized for planning the construction project and the National Park Service’s operational needs. This information is provided for the Contractor’s convenience and is intended to supplement rather than serve in lieu of Contractor’s own investigation and planning. The final phasing plan shall be produced by the Contractor for review and approval by the Contracting Officer based on the indicated access and operations dates and phasing milestone dates established within the documents.
C. Related Requirements:
1. Section 011100 Summary of Work
2. Section 012700 Definition of Contract Line Items
3. Section 013216 Construction Schedule
1.2 ACTION SUBMITTALS
A. Phasing Plan: Contractor shall provide a detailed phasing plan incorporating the availability of the work areas, staging areas, and operating dates of the facility indicated at the time of project solicitation with Construction Baseline Schedule in section 013216. Plan shall include, but is not limited to the following minimum requirements:
1. Shop Drawings and details showing locations of work for phasing periods indicated within the documents including the anticipated start and end dates for specific phasing activities.
2. Detailed schedule and description of each phase & sub-phase of the work including the intended process for timely completion of the work taking into account site, building, and trail closure dates, vacations of existing structures, and work processes that may affect the work progress.
3. Plan shall incorporate maps and other details outlining the sequential progress of the work
1.3 PRELIMINARY PHASING
A. General: Given the constraints of…