SECTION F – DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
ALTERNATE 1 (APR 1984)
The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work relating to the interior guest wing ready for overnight guest occupancy use not later than the beneficial occupancy date identified in awarded Alternate Schedule, and all remaining work under the contract in its entirety by September 02, 2019. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by August 01, 2018. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of Clause)
52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,338.00 for each calendar day of delay until the work is completed or accepted, the amount of $1,338.00 applies to both period of performance end dates of the beneficial occupancy date identified in awarded Alternate Schedule and September 02, 2019.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
| SECTION F – Deliveries or Performance |
| 52.211-10 Commencement, Prosecution, and Completion of Work Alternate 1 (APR 1984) |
| 52.211-12 Liquidated Damages—Construction (SEPT 2000) |