Amendment_0008_Q_and_A.pdf

PDF 51 KB Posted

Attached to
Seismic Stabilization and Rehabilitation of Mammoth Hotel Phase II
Solicitation number
140P2018R0039
Issued by

About this file

Amendment 0008_Q and A

View the file

Other files

File Type Posted
Amendment_0009_Q_and_A_05.04.2018.pdf PDF
Amendment_0009_SF30.pdf PDF
Amendment_0008_Addendum_4.pdf PDF
Amendment_0008_Attendance_List_Second_Site_Visit.pdf PDF
Amendment_0008_SF30.pdf PDF
Amendment_0007_Alternate_Contract_Price_Schedule_B.pdf PDF
Amendment_0007_SF30.pdf PDF
Amendment_0007_SF_1442.pdf PDF
Amendment_0007_Clause_Updates.pdf PDF
Amendment_0007_Alternate_Contract_Price_Schedule_C.pdf PDF
Amendment_0007_Alternate_Contract_Price_Schedule_A.pdf PDF
Amendment_0007_Section_L_&_M.pdf PDF
Amendment_0006_Addendum_3.pdf PDF
Amendment_0006_SF30.pdf PDF
Replacement_Q_and_A_from_Amendment_0004_04.26.2018.pdf PDF
Amendment_0006_-_Q&A_04.26.2018.pdf PDF
SF30_Amendment_0005.pdf PDF
Amendment_0004_SF30.pdf PDF
Amendment_0004_Q&A.pdf PDF
Amendment_0004_Attendance_List_Site_Visit_04.11.2018.pdf PDF
Amendment_0004_Addendum_2_YELL_205796.pdf PDF
B09_YELL_205796_Amend_0003__Addendum_1_Specs.pdf PDF
B09_YELL_205796_Amend_0003_Q&A.pdf PDF
B09__YELL_205796_Amend_0003_SF_30.pdf PDF
B09_YELL_205796_Amend_0002_Q&A.pdf PDF
B09_Amendment_0002_Attach_02_Geotechnical_Report.pdf PDF
B09_Amendment_0002_List_of_Changes.pdf PDF
B09_Amendment_0002_Attach_01_HSR_.pdf PDF
B08_YELL_205796_140P2018R0039_Amend_0002.pdf PDF
B09_Amendment_0002_Attach_03_Hazardous_Material_Survey.pdf PDF
B08_YELL_205796_140P2018R0039_Amend_0001.pdf PDF
B08_YELL_205796_Solit_Attach_02A_Drawings_Volume_1.pdf PDF
B08_YELL_205796_Solit_Attach_02B_Drawings_Volume_2.pdf PDF
B08_YELL_205796_Solit_Attach_01A_Specs_Volume_I.pdf PDF
B08_YELL_205796_Solit_Attach_07_Bid_Bond_Form.pdf PDF
B08_YELL_205796_140P2018R0039.pdf PDF
B08_YELL_205796_Solit_Attach_06_SubRefs.doc DOC document
B08_YELL_205796_Solit_Attach_01B_Specs_Volume_II.pdf PDF
B08_YELL_205796_Solit_Attach_05_KeyPers.docx DOCX document
B08_YELL_205796_Solit_Attach_03_WD.pdf PDF
B08_YELL_205796_Solit_Attach_11_SubCtrPlan.doc DOC document
B08_YELL_205796_Solit_Attach_12_PastPerf.doc DOC document
B08_YELL_205796_Solit_Attach_08_Equals.doc DOC document
B08_YELL_205796_Solit_Attach_10_GenRefs.doc DOC document
B08_YELL_205796_Solit_Attach_09_HazMat.doc DOC document
B08_YELL_205796_Solit_Attach_04_Experience.docx DOCX document
B01_YELL_205796_Synopsis_PreSolitNotice.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140P2018R0039 Mammoth Hotel Seismic Stabilization Phase 2

YELL 205796

Amendment 0008 Questions and Answers

Question 1: Each alternate schedule lists August 01, 2018 at the date for notice to proceed. Will the contractor have access to begin work in work area 2 (the entire guest wing) on August 01, 2018, or does the start of access to work area 2 remain at September 10, 2018?

Answer 1: Bidders should refer to sheet A0.02 for specific dates of work area availability.

Question 2: The way the specs are written and the response to the question about which lead paint guidelines to follow means the lead abatement subcontractor would need to do the plaster demo (not the Prime Contractor). So based on the information received, it seems like the Government intends for the contractor to encapsulate the paint, then have a containment with air monitoring and a full time IH present during demolition. Is this the Government’s intent?

Answer 2: The work related in section 028300 Lead-based Paint Stabilization and Component Renewal is NOT the abatement of lead based paint from the project nor to impose on the General Contract the requirement for demolition activities to items containing lead based paint is present to be completed by a specialty contractor. The work of this section is to provide requirements for training, containment and testing to facilitate the safe treatment and handling of materials containing lead based paint within the work including the following requirements that can all reasonably be undertaken by the General Contractor if they so choose.

1) Worker training in compliance with OSHA Lead in Construction Training as required by paragraph 1.8.

2) Provide for regulated areas to ensure capture and containment of lead dust to the work area as required by paragraph 1.5 and others.

3) Contractor required monitoring of Contractor’s personnel exposure per paragraph 2.3.

4) Contractor required testing of the waste stream for identification of legal disposal site per paragraph 2.3.

5) Contractor quality control testing per paragraph 2.3 as related to workers and area cleaning procedures.

The specification also outlines quality assurance testing practices that may be undertaken by the Government to ensure contractor has completed the work in accordance with the requirements.

Solicitation 140P2018R0039 Mammoth Hotel Seismic Stabilization Phase 2

YELL 205796

Again, it is not a requirement of the specification to require the General Contractor hire a specialty contractor to complete demolition work, to encapsulate lead based paint, or provide a FULLTIME onsite Industrial Hygienist, unless, at the General Contractor’s discretion, they so choose.

Question 3: Is the NPS open to competitive bids on the temperature control portion of this project or is it single source?

Answer 3: This project has been sole source justified for the existing building automation system extension into phase II by Johnson Controls Inc. Reference drawings and section 230993 for additional information.

Question 4: Will Phase II controls be tied into an existing building automation system?

If so, what is the existing system?

Answer 4: Yes, the current system is a Johnson Controls Metasys MSTP Network System. Reference 230993 for additional information.

Question 5: Is the existing system open protocol and accessible to allow competitive temperature control bidders?

Answer 5: The existing system is a Johnson Controls Metasys MSTP Network system.

The Government is requiring a single unified building automation system provided and serviced by a single vendor. Reference 230993 for additional information.

Question 6: The basis-of-design color for Bathrooms listed in section 123661 2.2-E-3-a “Nimbus” has been discontinued by the manufacturer. Is there an alternate basis-of-design color that is acceptable to the Government?

Answer 6: Please substitute color “Coral Clay” for the bathroom components indicated in section 123661 2.2-E-3-a. All other requirements remain unchanged.