B08_140P1422R0002_RFP_Amendment_Letter_5_Q_A_0005.pdf

PDF 77 KB Posted

Attached to
National Park Service, Northern Rockies MABO, Mult
Solicitation number
140P1422R0002
Issued by

View the file

Other files

File Type Posted
B08_140P1422R0002_RFP_Amendment_Letter_6_Q_A_0006.pdf PDF
Sol_140P1422R0002_Amd_0006.pdf PDF
Sol_140P1422R0002_Amd_0005.pdf PDF
B08_140P1422R0002_RFP_Amendment_Letter_4_Site_Visit_Sign_In_Form_0004.pdf PDF
Sol_140P1422R0002_Amd_0004.pdf PDF
B08_140P1422R0002_RFP_Amendment_Letter_4_Q_A_0004.pdf PDF
RFP_Amendment_Letter_3_Q_A_0003.pdf PDF
Sol_140P1422R0002_Amd_0003.pdf PDF
B08_140P1422R0002_MATOC_RFP_Revised_4May2023_0003.pdf PDF
RFP_Amendment_Letter_3_Asbestos_Sampling_Report2May2023_0003.pdf PDF
B08_140P1422R0002_Attachment_J10_Seed_TO_RFP_Form_Revised_4May2023_0003.pdf PDF
RFP_Amendment_Letter_3_Attachment_J6_SEED_TO_SOW_Revised_2May2023_0003.pdf PDF
B08_140P1422R0002_Attachment_J10_Seed_TO_RFP_Form_Revised_27Apr2023_0002.pdf PDF
RFP_Amendment_Letter_2_Drawing_YCC_MESS_HALL_0002.pdf PDF
Amendment_Questions_0002.pdf PDF
RFP_Amendment_Letter_2_Attachment_J6_SEED_TO_SOW_Revised_25Apr2023_0002.pdf PDF
B08_140P1422R0002_MATOC_RFP_Section_B_Revised_27Apr2023_0002.pdf PDF
Sol_140P1422R0002_Amd_0002.pdf PDF
RFP_Amendment_Letter_2_Site_visit_Sign_In_Log_0002.pdf PDF
Sol_140P1422R0002_Amd_0001.pdf PDF
B08_140P1422R0002_Attachment__J2_TO_RFP_Form_Sample.docx DOCX document
B08_140P1422R0002_Attachment_J9__SEED_TO_Proposed_Equals_Request.docx DOCX document
Sol_140P1422R0002.pdf PDF
B08_140P1422R0002_Attachment__J1_NPS_Safety_and_Checklist.pdf PDF
B08_140P1422R0002_Attachment__J4_Past_Performance_Questionnaire.docx DOCX document
B08_140P1422R0002_Attachment_J8_Wage_Determination_Park_Co_Bldg_WY20230013_Dated_27Jan2023.pdf PDF
B08_140P1422R0002_Attachment_J7_SEED_TO_Drawings_2021-11-24.pdf PDF
B08_140P1422R0002_Attachment__J3_Will_Not_Compete.docx DOCX document
B08_140P1422R0002_Attachment_J6_SEED_TO_SOW_Revised_30Mar2023.pdf PDF
B08_140P1422R0002_Attachment_J10_Seed_TO_RFP_Form.docx DOCX document
B08_140P1422R0002_Attachment_J11_Dry_Sprinkler_System_Design_Calculations_2021-11-24.pdf PDF
B08_140P1422R0002_Attachment__J5_LmtOnSubconRpt.xlsx XLSX spreadsheet
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. In Section L, Technical Factor 4 – Relevant Experience, it states “Offerors shall identify the following in list form: All Federal, State or Local Government agencies and commercial businesses for whom the offeror has been awarded a contract during the past three (3) years.”

“…..identify no more than 10 contracts applicable to the work of this MATOC.” If we have 10 projects that were awarded in the past 3 years, are we required to provide 10 projects for Factor 4 Experience, which will then also require 10 CPARS/PPQs for Factor 5?

• Yes, Submit Past Performance information for the same projects submitted under Relevant Similar Experience (Technical Factor 4)

2. In Section L, Technical Factor 4 – Relevant Experience, it states “Recent experience is defined as currently on-going, or completed within the past five years of the solicitation close date” and then in the next paragraph it states: “Offerors shall identify the following in list form: All Federal, State or Local Government agencies and commercial businesses for whom the offeror has been awarded a contract during the past three (3) years.” Please clarify if project experience is to be within 5 years or 3 years.

• 3 years

3. Per page 67 of the solicitation, “For each project submitted as past experience/past performance, the offeror shall provide a copy of this questionnaire (standardized past performance questionnaire provided).”

Per page 68 of solicitation “the offeror shall address each of the following aspects of past performance: quality of product/service, documentation quality, work site safety, cost control, management responsiveness, contract management

Does NPS require references and/or reference projects and/or additional narratives of the reference projects in addition to the past performance questionnaires? I believe there is a maximum of 10 reference projects and past performance questionnaires per page 67 of solicitation.

• Submit Past Performance information for the same projects submitted under Relevant Similar Experience (Technical Factor 4)

4. If bid per Amendment CLIN 1, it appears to call for, "ceiling area repairs only not the the removal / demolition of all ceiling types"

• Clin 1 is to remove only the required access points in the ceiling to remove the fire suppression system and repair those access points.

• 2. Clin 2 is an option line item for contractors to provide pricing on the price is to remove all the ceiling all locations and install new ceilings in kind.

5. Per SOW, page 3 of 8, it appears that all gypsum ceilings that require repair (including exposed/painted gypsum, and gypsum with glued acoustic ceiling tiles) are to receive a 1/2" drywall overlay. Is the intent to receive 1/2" new drywall over the majority of drywall ceilings?

• The statement is there to reduce labor hours of repair, If a contractor determined that the 5/8 gypsum board access holes would be easier to repair by cover all ceiling areas with an additional ½ gypsum board to achieve the level 4 finish. that is acceptable.

• The 5/8 fire board shall be replaced before covering with the ½ inch

File details come from the government source that posted it. Updated .