Solicitation
Document No.
140P1422R0002
Document Title Northern Rockies MABO Construction MATOC
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF-1442) - pages 1- 2 of this package
As requirements develop, task orders will be competed among the MATOC awardees. This is not a Requirements contract per FAR 16.503; the Government reserves the right to issue additional solicitations and award additional contracts within the locations covered by this solicitation outside of this MATOC. In accordance with the Federal Acquisition Streamlining Act and FAR 16.505(b), the Contracting Officer will provide each awardee a “fair opportunity” to be considered for each order in excess of $2,000, unless one of the conditions outlined MULTIPLE AWARDEES, FAIR OPPORTUNITIES CLAUSE (SPECIAL PROVISION) at FAR 16.505(b) applies.
SECTION B – BID SCHEDULE
MATOC BINDING RATES
DIRECT LABOR RATES-MAXIMUM CEILING RATES PRICED PER YEAR
Burdened: Rates shall be burdened with taxes, insurance, and home office overhead; but shall not include job site overhead or profit.
LABOR
DISCIPLINES
UNIT YEAR 1
RATES
YEAR 2
RATES
YEAR 3
RATES
YEAR 4
RATES
YEAR 5
RATES
Construction Superintendent / Foreman
HR
Construction Project Manager HR
MATOC - INDIRECT COSTS
Overhead, General and Administrative (G&A)
PROFIT TABLE
ROM up to - $150k %
ROM $150k - $250k %
ROM $250k - $500k %
ROM $500k - $1.0M %
ROM >$1.0M %
Yearly Rate 1 will go into effect upon contract award date. The subsequent Yearly Rates 2-5 will go into effect each year on anniversary of contract award for the life of the contract. The contractor shall be responsible to ensure correct pricing is being utilized each year.
Document Title
The following contract line items for the seed task order shall be incorporated as binding rates for identical future work that meets the description for each line below. Reference the Seed Task Order Statement of Work, Attachment J6, Section 10, for a definition of each Contract Line-Item Number (CLIN) below SEED Task Order CLIN 1: The base line funding shall be all work related to the installation of the fire suppression system including the repairs to return to as condition of the ceilings all areas (ceiling area repairs only not the removal / demolition of all ceiling types)
1a: Demo all points of entry within the ceiling to provide access to the current fire suppression system.
This line item consists of all the labor, equipment, and materials necessary to:
Remove and dispose of the required ceiling sections to provide access for the removal of the current fire suppression system components.
Total $ ________________ 1b: Demo current fire suppression system and prepare area for the new suppression system upgrade.
This line item consists of all the labor, equipment, and materials necessary to disconnect, remove and dispose of the current fire suppression system components including the riser.
Total $ ________________
1c: Installation of the new fire suppression system.
This line item consists of all the labor, equipment, and materials necessary to install the new fire suppression as per the attached drawing / design requirements.
Total $ ________________
1d: Suppression System testing.
This line item consists of all the labor, equipment, and materials necessary to soft start and test the new fire suppression system as per the attached drawing/ design requirements.
The testing shall include Yellowstone National Park technical experts and the Park Fire Chief.
Total $ ________________ 1e: Replace/repair all points of entry in the ceiling.
This line item consists of all the labor, equipment, and materials necessary to repair all points of entry in the ceiling.
The cost shall include the replacement of all ceiling tiles updated to a 2’x2’ drop ceiling. The cost shall include updating/replacing all lighting fixtures to LED.
Total $ ________________ 1f: Clean and decontaminate all surfaces.
This line item consists of all the labor, equipment, and materials necessary to clean and decontaminate all surfaces. This shall include a final wipe test to determine cleanliness.
The tests shall be used to monitor the cleanliness of the working surfaces in the area where asbestos was present. The samples shall be collected using micro-vacuuming on PCM cassettes or as wipe samples on all work areas. Independent test results shall be provided to the Government with the final approvals punch list.
Total $ ________________ Seed Task Order CLIN 2: Option line shall be work related to the removal of all Asbestos material within the building this line option is dependent on the availability of funds and will be awarded or declined not to exceed 30 days after
NTP.
Document Title
Test, demo, remove and the dispose of all hazardous materials.
• Test for hazardous materials (all locations of work)
• This line item consists of all the labor, equipment, and supplies necessary to test for all hazardous materials and for the removal and disposal of the above hazardous materials as per State and Federal requirements.
Total $ ________________
Seed Task Order CLIN 2: Option line two shall be related to the removal/demolition of all ceiling components including: ceiling tiles/ grid system, gypsum board and glue down ceiling tiles on gypsum board.
• To access all the required demolition of the fire suppression system the awarded contractor shall remove all the ceiling types where required and replace in kind.
• The determination for award of this option line item shall be determined at the time of award.
Total $ ________________
| SECTION A – SOLICITATION / CONTRACT FORM |
| SECTION B – BID SCHEDULE |
| SECTION C – SPECIFICATIONS / DRAWINGS |
| SECTION D – PACKAGING AND MARKING |
| SECTION E – INSPECTION AND ACCEPTANCE |
| SECTION F – DELIVERIES OR PERFORMANCE |
| SECTION G – CONTRACT ADMINISTRATION DATA |
| SECTION H – SPECIAL CONTRACT REQUIREMENTS |
| H.1 PROHIBITION OF ALL TERRAIN VEHICLES (ATV)S – OFFICE SUPPORTING REGIONS 6, 7, & 8 |
| H.2 FIRE DANGER SEASON |
| H.3 EXTENT OF OBLIGATION |
| H.4 WORK BY THE GOVERNMENT |
| H.5 COMPLIANCE WITH STATE AND FEDERAL LAWS AND REQUIREMENTS |
| H.6 KEY PERSONNEL (WILL BE COMPLETED WITH AWARD) |
| H.7 UTILITY SERVICES |
| H.8 GENERIC GENDER TERMINOLOGY |
| H.9 NON-DISCRIMINATION NOTICE |
| H.10 EXPENSES RELATED TO OFFERS |
| H.11 SPECIAL MATOC CONTRACT REQUIREMENTS |
| PART II – CONTRACT CLAUSES |
| SECTION I – Contract Clauses |
| CLAUSES INCORPORATED BY REFERENCE (CLAUSES CONTAING FILL-INS OR BLANK SPACES WILL BE COMPLETED IN THE TASK oRDER SOLICITATION AND INCORPORATED BY FULL TEXT): |
| CLAUSES INCORPORATED BY FULL TEXT: |
| PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS |
| SECTION J – List of Attachments |
| PART IV – REPRESENTATIONS AND INSTRUCTIONS |
| SECTION K – Representations, Certifications and Other Statements of Offerors |
| 52.204-8 Annual Representations and Certifications (MAR 2023) |
| SECTION L – Instructions, Conditions and Notices to OFFERORS |
| 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions. |
SECTION M – EVALUATION FACTORS FOR AWARD
File details come from the government source that posted it. Updated .