140L6221R0001 AMD 0007 Questions and Answers_0007.docx

DOCX document 16 KB Posted

Attached to
SPLIT ROCK REC SITE PARKING LOT REBUILD
Solicitation number
140L6221R0001
Issued by

About this file

This document contains questions and answers related to a federal solicitation for rebuilding the parking lot at the Split Rock Rec Site. The solicitation is being conducted by the Department of the Interior Bureau of Land Management Wyoming Region to solicit bids for removing the existing asphalt and road base at the parking lot, grinding both together using a reclaimer to create a recycled base material, recompacting the base to meet specifications, tying new concrete into the existing restroom concrete pad, draining the new concrete correctly, and replacing any bear proof trash cans that need to be removed during construction. Bids are due by mid-August 2021, and work must be completed between mid-August and September 2021. Potential water sources near the site include Lander and Rawlins. Additives to new concrete may be proposed for review.

View the file

Other files

File Type Posted
140L6221R0001 AMD 00008 QUESTION AND ANSWERS.docx DOCX document
Sol_140L6221R0001_Amd_0008.pdf PDF
Pre-Bid Split Rock Parking Lot_0007.pdf PDF
Sol_140L6221R0001_Amd_0007.pdf PDF
140L6221R0001 AMD 0006 QUESTIONS AND ANSWERS_0006.docx DOCX document
Sol_140L6221R0001_Amd_0006.pdf PDF
Sol_140L6221R0001_Amd_0005.pdf PDF
140L6221R0001 AMD 0005 QUESTION AND ANSWER_0005.docx DOCX document
Typ Pavement Cross Section Concrete Cross Section 1_0004.pdf PDF
Sol_140L6221R0001_Amd_0004.pdf PDF
140L6221R0001 AMD 0004 QUESTIONS AND ANSWERS_0004.docx DOCX document
Sol_140L6221R0001_Amd_0003.pdf PDF
140L6221R0001 AMD 0003 QUESTIONS AND ANSWERS_0003.docx DOCX document
UPDATED 01 21 2021 01009 General Information and Requirements_0002.docx DOCX document
Split Rock Ruler_0002.pdf PDF
Sol_140L6221R0001_Amd_0002.pdf PDF
Split Rock_0002.jpg JPG image
140L6221R0001 AMD 0002 QUESTION AND ANSWER_0002.docx DOCX document
140L6221R0001 AMD 0001 QUESTIONS AND ANSWERS_0001.docx DOCX document
Sol_140L6221R0001_Amd_0001.pdf PDF
REVISED 01 19 2021 Bid Schedule Split Rock Parking Lot Rebuild_0001.xlsx XLSX spreadsheet
01009 General Information and Requirements.docx DOCX document
03310 Structural Concrete.docx DOCX document
02722 Aggregate Base Course.docx DOCX document
01458 Testing Laboratory Services.docx DOCX document
02223 Selective Site Demolition.docx DOCX document
Location Map.docx DOCX document
02339 Watering.docx DOCX document
Bid Schedule Split Rock Parking Lot Rebuild.xlsx XLSX spreadsheet
01505 Mobilization.docx DOCX document
Typ Pavement Cross Section.pdf PDF
Typ Pavement Cross Section Existing Asphalt.pdf PDF
Typ Pavement Cross Section Concrete Cross Section.pdf PDF
Sol_140L6221R0001.pdf PDF
01500 Temporary Facilities and Controls.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L6221R0001 Amendment: 00007

Q1. Would we be able to use a reclaimer to grind up the asphalt and road base at the same time creating a recycle base to be recompacted?

A1. Yes. A reclaimer can be used to grind up the asphalt and the road base at the same time can be used as a recycle base to be recompacted. The base will need to meet the compaction specifications.

February 11, 2021 Site Visit Questions/Answers:

1. Edge will be the bollard.

2. Bear proof trash cans may have to removed but will be replaced upon completion (not a requirement, but if moved need to put them back in place).

3. Drain the concrete correctly, not towards the restroom.

4. Tie into the existing concrete of the restroom

5. Closure of the Rec Site? Whomever receives the award will need to ask, not sure the Field Office will allow full closure.

6. Timeframe for actual work is mid-August to September (approximately two weeks) per Section 01009 General Information and Requirements.

7. Water source – Lander Rawlins would be the closest water sources.

8. Additives to the concrete? Additives to the concrete are not currently in the specifications. If awarded can submit a submittal form for review and will evaluate.

File details come from the government source that posted it. Updated .