01500 Temporary Facilities and Controls.docx
DOCX document 27 KB Posted
- Attached to
- SPLIT ROCK REC SITE PARKING LOT REBUILD
- Solicitation number
- 140L6221R0001
About this file
This document provides specifications for temporary facilities and controls for the Split Rock Recreation Site Parking Lot Rebuild project solicited by the Bureau of Land Management Wyoming Region. The specifications require the contractor to submit a traffic control plan detailing signs, signals, barricades and flaggers to ensure safety during construction on Highway 287. The contractor must also install a project identification sign at the main construction entrance and provide temporary utilities, haul routes, and maintain and remove temporary facilities once construction is complete. No direct payment will be made for temporary facilities and controls, as consideration is included in other contract line items.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| DIVISION 1 | SECTION 01500 |
| GENERAL REQUIREMENTS | TEMPORARY FACILITIES AND CONTROLS |
| DIVISION 1 | SECTION 01500 |
| GENERAL REQUIREMENTS | TEMPORARY FACILITIES AND CONTROLS |
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
PART 1: GENERAL
1.1 SUMMARY
A. Section Includes: Requirements for temporary construction signs, vehicular access, temporary barriers and controls, and project identification.
1.2 SUBMITTALS
| A. | Traffic Control Plan: Submit three (3) copies. Include the following topics: |
| 1. | The requirements for specific signs, signals, channelizing and lighting devices, barricades, and flagpersons that are detailed in the current ANSI D6.1. |
| 2. | Provide construction and rest area closed signs on Highway 287 following Wyoming Department of Transportation and the MUTCD signing manual. |
| 3. | Provide for temporary connections of sufficient width for one line of traffic between the existing entrance and new temporary construction, where necessary. |
| 4. | Provide for such guards as may be necessary to ensure against accidents and avoid damage or injury to passing traffic in areas where the nature of construction operations in progress and equipment and machinery in use pose a hazard. |
1.3 QUALITY ASSURANCE
| A. | Regulations: Comply with applicable local regulations for haul routes over public highways, roads, or bridges. Comply with industry standards and applicable laws and regulations of authorities having jurisdiction including, but not limited to the following: |
| 1. | Wyoming Department of Transportation |
| 2. | Health and safety regulations. |
B. Manuals: Comply with latest Manual on Uniform Traffic Control Devices (MUTCD).
C. Contractor shall coordinate with Wyoming Department of Transportation.
D. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits.
1.4 EXPLOSIVES
A. Explosives: Shall not be permitted.
1.6 PROJECT CONDITIONS
A. Access Routes: Use only established roadways, areas, and haul routes, or temporary roadways, areas, or haul routes.
B. Traffic Control Plan: Provide for approval by the Contracting Officer a plan to control and protect public traffic adjacent to and within the project according to the MUTCD.
PART 2: PRODUCTS
2.1 UTILITIES
A. General: Electrical power, telephone, heat, and water are not available on the site and shall not be provided by the Government.
2.2 PROJECT IDENTIFICATION
A. Project Site Sign: Within 30 days after Notice to Proceed and before construction, furnish and install a project sign which shall be located at the main construction entrance to the site and on Highway 287. The size, mounting, construction, paint colors and lettering shall be per the Wyoming Department of Transportation and MUTCD specifications.
B. Construction Signs: All signs shall be approved by the Contracting Officer before erecting. Only signs to expedite deliveries, maintain traffic flow, promote safety, and caution against danger shall be erected, as necessary. No advertising of their company.
PART 3: EXECUTION
3.1 VEHICLE TRAFFIC CONTROL
| A. | Preparation: Provide, erect, and maintain all necessary traffic control devices, including traffic cones, delineators, concrete safety barriers, barricades, suitable and sufficient flasher lights, flagpersons, danger signals, and signs, as specified on approved Traffic Control Plan and as required by the State and local authorities having jurisdiction. Take all necessary precautions for protection of the work and safety of the public on roads affected by the work during the contract period as construction work proceeds. |
| 1. | Do not start any construction work along public or private roads until the proper traffic control devices for warning, channeling, and providing safety for the motorists as specified on the approved traffic control plan are in place at the construction site. |
| B. | Application: Maintain flow of public traffic and conduct operations for construction of roadways so as to offer the least possible obstruction and inconvenience to public traffic. |
| 1. | Protect all roads closed to traffic with effective barricades having acceptable warning and detour signs. Conduct operation in a manner that will not close any thoroughfare or interfere with traffic except with written permission of the Contracting Officer. Illuminate all barricades and obstructions at night, and keep all lights burning from sunset until sunrise. |
| 2. | Maintain the condition, operation, and effectiveness of all traffic control devices throughout their period of use. Remove all temporary traffic control devices when no longer needed. |
3.2 HAUL ROUTES, ROADWAYS, PARKING AREAS, AND STORAGE/STAGING AREAS
A. Examination: Investigate the condition of available public or private roads for clearances, restrictions, bridgeload limits, bond requirements, and other limitations that affect or may affect access and transportation operations to and from the jobsite.
B. Established Roadways As Haul Routes: Use existing available Public highways, roads, or bridges as haul routes subject to the applicable local regulations.
3.3 MAINTENANCE AND REMOVAL
A. Maintenance: Maintain temporary structures, facilities, and controls as long as needed for safe and proper completion of the work and as directed by the Contracting Officer.
B. Removal: Remove temporary structures, facilities, and controls as rapidly as progress of the work will permit and as approved by the Contracting Officer.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT
A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.
END OF SECTION