This is an external memorandum from RESPEC to Bratslavsky Consulting Group, Inc. dated March 20, 2026, regarding Addendum No. 2 for the ANM-JRD Compound HVAC Modernization project. The memorandum provides revisions to electrical drawings and specifications for the compound's HVAC system upgrade.

The addendum specifies three drawing modifications: deletion of Sheet Keynote 6 from Sheet E1.1 (Office Building Floor 1), and replacement of Sheet Keynote 4 on both Sheet E1.4 (Dry Storage Building) and Sheet E1.5 (Warehouse) with detailed "Alternate 2" specifications. The Alternate 2 requirements include installation of a BTU meter with associated infrastructure in each building. For the Dry Storage Building, this involves providing a 1/2" conduit from the BTU meter to the data cabinet, a CAT6 cable connection to the existing DDC controller in the warehouse (routed through the same conduits as optic fiber and mechanical control cables), and branch circuiting from panel PP-2. For the Warehouse, the requirements include circuiting the BTU meter to the existing DDC controller via CAT6 cable in raceway and providing branch circuiting and conduit from panel PP-1A to the BTU meter.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

respec.com

9109 Mendenhall Mall Rd.

Suite 4

Juneau, AK 99801

907.780.6060

EXTERNAL MEMORANDUM

To: Felix Bratslavsky, MCA, CDP

Senior Vice President

Bratslavsky Consulting Group, Inc

500 W 27th Ave A

Anchorage, AK 99503 cc: Project Central File I1694.24002

From: Kyle Drapeaux, PE

Project Engineer

RESPEC

9109 Mendenhall Mall Rd., Suite 4

Juneau, AK 99801

Date: March 20, 2026

Subject: ANM-JRD Compound HVAC Modernization – Addendum No. 2 Electrical

Below are the addendum revisions to the electrical documents.

DRAWINGS:

/ Sheet E1.1 OFFICE BUILDING FLOOR 1: DELETE SHEET KEYNOTE 6.

/ Sheet E1.4 DRY STORAGE BUILDING: REPLACE SHEET KEYNOTE 4 with “ALTERNATE

2: PROVIDE A BTU METER. PROVIDE A 1/2” CONDUIT FROM THE BTU METER TO THE

DATA CABINET. PROVIDE A CAT6 CABLE FROM THE BTU METER TO THE EXISTING

DDC CONTROLLER IN THE WAREHOUSE IN THE SAME CONDUITS AS THE OPTIC

FIBER CABLE AND THE MECHANICAL CONTROL CABLE. PROVIDE BRANCH

CIRCUITING AND CONDUIT FROM PANEL PP-2 TO THE BTU METER.”

/ Sheet E1.5 WAREHOUSE: REPLACE SHEET KEYNOTE 4 with: “ALTERNATE 2: PROVIDE

A BTU METER. CIRCUIT THE BTU METER TO THE EXISTING DDC CONTROLLER WITH

A CAT6 CABLE IN RACEWAY. PROVIDE BRANCH CIRCUITING AND CONDUIT FROM

PANEL PP-1A TO THE BTU METER.”