About this file
This is an external memorandum from RESPEC to Bratslavsky Consulting Group, Inc. dated March 20, 2026, regarding Addendum No. 2 for the ANM-JRD Compound HVAC Modernization project. The memorandum provides revisions to electrical drawings and specifications for the compound's HVAC system upgrade.
The addendum specifies three drawing modifications: deletion of Sheet Keynote 6 from Sheet E1.1 (Office Building Floor 1), and replacement of Sheet Keynote 4 on both Sheet E1.4 (Dry Storage Building) and Sheet E1.5 (Warehouse) with detailed "Alternate 2" specifications. The Alternate 2 requirements include installation of a BTU meter with associated infrastructure in each building. For the Dry Storage Building, this involves providing a 1/2" conduit from the BTU meter to the data cabinet, a CAT6 cable connection to the existing DDC controller in the warehouse (routed through the same conduits as optic fiber and mechanical control cables), and branch circuiting from panel PP-2. For the Warehouse, the requirements include circuiting the BTU meter to the existing DDC controller via CAT6 cable in raceway and providing branch circuiting and conduit from panel PP-1A to the BTU meter.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
respec.com
9109 Mendenhall Mall Rd.
Suite 4
Juneau, AK 99801
907.780.6060
EXTERNAL MEMORANDUM
To: Felix Bratslavsky, MCA, CDP
Senior Vice President
Bratslavsky Consulting Group, Inc
500 W 27th Ave A
Anchorage, AK 99503 cc: Project Central File I1694.24002
From: Kyle Drapeaux, PE
Project Engineer
RESPEC
9109 Mendenhall Mall Rd., Suite 4
Juneau, AK 99801
Date: March 20, 2026
Subject: ANM-JRD Compound HVAC Modernization – Addendum No. 2 Electrical
Below are the addendum revisions to the electrical documents.
DRAWINGS:
/ Sheet E1.1 OFFICE BUILDING FLOOR 1: DELETE SHEET KEYNOTE 6.
/ Sheet E1.4 DRY STORAGE BUILDING: REPLACE SHEET KEYNOTE 4 with “ALTERNATE
2: PROVIDE A BTU METER. PROVIDE A 1/2” CONDUIT FROM THE BTU METER TO THE
DATA CABINET. PROVIDE A CAT6 CABLE FROM THE BTU METER TO THE EXISTING
DDC CONTROLLER IN THE WAREHOUSE IN THE SAME CONDUITS AS THE OPTIC
FIBER CABLE AND THE MECHANICAL CONTROL CABLE. PROVIDE BRANCH
CIRCUITING AND CONDUIT FROM PANEL PP-2 TO THE BTU METER.”
/ Sheet E1.5 WAREHOUSE: REPLACE SHEET KEYNOTE 4 with: “ALTERNATE 2: PROVIDE
A BTU METER. CIRCUIT THE BTU METER TO THE EXISTING DDC CONTROLLER WITH
A CAT6 CABLE IN RACEWAY. PROVIDE BRANCH CIRCUITING AND CONDUIT FROM
PANEL PP-1A TO THE BTU METER.”