This document is an Environmental Permits/Authority to Proceed Guidance for the 99th Civil Engineer Squadron (99 CES/CEIE) at Nellis Air Force Base, dated 10 April 2023. The comprehensive guidance outlines required environmental permits and responsibilities for contractors working on base, covering multiple environmental program areas including Air Quality, Drinking Water, Storm Water, Asbestos/Lead/Toxics, Solid Waste, Cultural Resources, Natural Resources, and Petroleum, Oil, and Lubricants (POL).

Key requirements include obtaining Clark County Dust Permits for trenches over 100 linear feet or land disturbances over 1/4 acre, securing Authority to Construct (ATC) permits for various equipment types, submitting Storm Water Pollution Prevention Plans (SWPPP) for projects disturbing one acre or more, conducting asbestos and lead-based paint surveys/abatements, managing hazardous materials and waste, performing cultural and natural resource consultations, and completing Work Clearance Requests (AF Form 103). Contractors are responsible for initiating permits with specific coordinating agencies, including Clark County Department of Environment and Sustainability, Nevada Division of Environmental Protection, Southern Nevada Health District, and various Nellis AFB program managers.

View the file

Other files

File Type Posted
Atch 80_ RFI Response Log_General Solicitation 9 March 2026.xlsx XLSX spreadsheet
Solicitation Amendment FA486125R00030013 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030011.pdf PDF
Solicitation Amendment FA486125R00030010 SF 30.pdf PDF
Attach 74 SABER Seed Attachment 18 - Knox Box Location.pdf PDF
Attach 75 SABER Seed Attachment 19 - B10250 comm room.pdf PDF
76 - RFI Response Log General Solicitation 13_Jan 26.xlsx XLSX spreadsheet
(Attachment 63) SABER Seed SOO Honor Guard Building 10250 Attachment 10 - Asbestos and Lead testing dated 24 February 2014.pdf PDF
Attachment 71 SABER IDIQ Preproposal Conference Slides 29 October 2025 FA486125R0003.pptx PPTX presentation
Solicitation Amendment FA486125R00030006 SF 30.pdf PDF
Solicitation Amendment FA486125R00030005 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030005.pdf PDF
Solicitation Amendment FA486125R00030004 SF 30.pdf PDF
Solicitation Amendment - FA486125R00030002.pdf PDF
Attachment 54 Gordian SABER CTC.pdf PDF
Attachment 52 Nellis AFB Base Pass Request.xlsx XLSX spreadsheet
Atch 41 NV20250038 19Sep25 Bldg Clark.pdf PDF
Atch 43 NV20250001 1Aug25 NTTR.pdf PDF
1 - SABER SOW 25 Sep 25.pdf PDF
4 - PPQ _PAST_PERFORMANCE_QUESTIONNAIRE FA486125R0003.pdf PDF
7 - Nellis-Creech Electrical Req 2023-10-17.pdf PDF
10_Nellis-Creech Utility Meter Req 2019-09-13.pdf PDF
11_Nellis-Creech Plant List.pdf PDF
13 - Work Clearance Triggers.pdf PDF
16_USAF Integrated Cultural Resources Mgmt Plan 32-7065 ICRMP - 06 Nov 2019.pdf PDF
19_UF3.PC Concrete Pad for Three Phase Requirement - Aug 2016.pdf PDF
20_UT1-UT5 Modified Trenching Drawing - Aug 2016.pdf PDF
24_UG3.3 Three Phase Six Bushing Pad-mounted Transformer - Aug 2016.pdf PDF
31 - AF Form 3052 Cost Estimate Template.xlsx XLSX spreadsheet
35 - AF 66 Schedule of Material Submittals.xlsx XLSX spreadsheet
36 - AF 3000 Material Approval Submittal - 01 Sep 2003.pdf PDF
38_NTTR Automated Information System _AIS_ Equipment Form.pdf PDF
41 - General Decision Number_NV20240038 Building Clark County.pdf PDF
44- SABER SOO RKMF240010 Renovate Honor Guard 99 FSS B10250_14Feb2025.pdf PDF
45 - Attachment Contract Information Sheet.pdf PDF
46 - Example SABER Design Intent Drawing Set Level 1_20 Nov.pdf PDF
49 - As-Builts.pdf PDF
Solicitation - FA486125R0003.pdf PDF
8_Nellis-Creech Lighting Req 2019-01-22.pdf PDF
15 - Hazardous Material Management Guidance Document 2023-06-03.pdf PDF
18 - Nellis Supplement to DAFI 31-218 Motor Vehicle Traffic Supervision - 23 Mar 2023.pdf PDF
23_Power Trench Sand and Backfill Requirements - Apr 2013.pdf PDF
27 - NTTR Visit Request - 27 Jan 2023.pdf PDF
28 - Nuclear Gauge Form 1.xlsx XLSX spreadsheet
29 - Nuclear Gauge Form 2.docx DOCX document
30 - AF Form 103 Base Civil Engineering Work Clearance Request - 01 Aug 1994.pdf PDF
39 - Form SS-PER-007-003 Internal Combustion Engine Worksheet.pdf PDF
42 - General Decision Number NV20240001 Bldg NTTR.pdf PDF
47 - Example SABER Design Intent Drawing Set Level 2_20 Nov.pdf PDF
52 - 99 SFS - Mass Pass Request Template.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

99 CES/CEIE

ENVIRONMENTAL PERMITS/AUTHORITY TO PROCEED GUIDANCE

For General Information, call (702) 679-0131 10 April 2023

PERMIT/AUTHORITY TO CONSTRUCT

RESPONSIBLE PARTY TO

OBTAIN PERMIT

PERMITTING/COORDINATING AGENCY

Air Quality Program

Clark County Dust Permit:

- Trench >/= 100 LF

- Disturbance >/= ¼ Acre (10,890 SF)

- Structural demo >/= 1000 SF

Party Executing the Work

Clark County Department of Environment and Sustainability

(DES)

(https://www.clarkcountynv.gov/government/departments/e nvironment_and_sustainability/division_of_air_quality/permitt ing/applications_forms/dust_permitting_forms.php) (702) 455-1524

Authority to Construct (ATC) required prior to commencing construction:

- Boilers

- Cooling Towers

- Baghouse/Cyclones

- Fuel Dispensing Equipment

- Fuel Storage Tanks

- Asphalt Batch Plant

- Concrete Batch Plant

- Rock Crusher/Mineral Processing

- Paint Booths

- Media Blasters

- Water Heaters

- HVAC Heaters

- Generators

- Hush House

- Degreasers

- Fuel Cell Maintenance

- Woodworking Equipment

Nellis AQ PM is responsible for the permitting process

(nellis.air.quality@us.af.

mil (702) 652-8897/2882)

The party adding the equipment/operation is responsible for ensuring the permitting process has been initiated. If the

AQ PM has not been contacted concerning the equipment/operation and been provided all requested information then the permitting process has not been initiated.

Clark County DES

- Refrigerants and other Ozone Depleting Chemicals Contractor

Party Executing the Work Contact AQ PM (702) 652-8897/2882

Drinking Water - Water Program

Projects impacting drinking water must be submitted to the BSDW for review prior to commencing the water project. Contractor

Party Executing the Work

Nevada Division of Environmental Protection (NDEP) Bureau of Safe Drinking Water View requirements here: https://ndep.nv.gov/water/drinking-water/engineering-reviews/when-to-submit-plans

Water Program Manager (702) 652-8897

Storm Water - Water Program

Temporary Discharge to Waters Discharges from remediation and disinfection activities, well pump testing, aquifer drawdown testing, dewatering, underground injection of fluids, and other discharges of a temporary nature.

Contractor Party Executing the Work

Nevada Division of Environmental Protection (NDEP)

Construction Storm Water Discharge Permit Requires SWPPP– If an acre or more of land is disturbed.

SWPPP Format: https://ndep.nv.gov/water/water-pollution-control/permitting/stormwater-discharge-permits/construction-sites-greater-than-1-acre

Contractor Party Executing the Work

Submit a copy of SWPPP to base Water Program Manager for approval and provide a copy of NoI. Submit NoT at completion of the project. Provide to base contracting for Civil Engineering to incorporate in project folder. SWPPP is approved by WQ PM. NOI with CSW is issued by NDEP after paying the fee. Both NOI and SWPPP will need approval from WQ PM. NDEP SWPPP form link:

https://ndep.nv.gov/uploads/water-wpc-permitting-stormwater-construction-docs/nvr100000-const-swppp-template-2017.pdf (please fill out with as much details as possible) and store the plan with the map at jobsite.

https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/dust_permitting_forms.php https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/dust_permitting_forms.php https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/dust_permitting_forms.php mailto:nellis.air.quality@us.af.mil mailto:nellis.air.quality@us.af.mil http://www.leg.state.nv.us/nac/NAC-445A.html#NAC445ASec66585 https://ndep.nv.gov/water/drinking-water/engineering-reviews/when-to-submit-plans https://ndep.nv.gov/water/drinking-water/engineering-reviews/when-to-submit-plans https://ndep.nv.gov/water/water-pollution-control/permitting/stormwater-discharge-permits/construction-sites-greater-than-1-acre https://ndep.nv.gov/water/water-pollution-control/permitting/stormwater-discharge-permits/construction-sites-greater-than-1-acre https://ndep.nv.gov/water/water-pollution-control/permitting/stormwater-discharge-permits/construction-sites-greater-than-1-acre https://ndep.nv.gov/uploads/water-wpc-permitting-stormwater-construction-docs/nvr100000-const-swppp-template-2017.pdf https://ndep.nv.gov/uploads/water-wpc-permitting-stormwater-construction-docs/nvr100000-const-swppp-template-2017.pdf https://ndep.nv.gov/uploads/water-wpc-permitting-stormwater-construction-docs/nvr100000-const-swppp-template-2017.pdf

Water Program Manager (702) 652-7639

Asbestos/Lead/Toxics Program

Asbestos:

- ACM Survey/Abatement

- Notification/Demolition Permit

- ACM Waste Manifest

- Abatement Plans approval

Lead Based Paint:

- LBP Survey/Abatement

Contractor

(Bill of Lading signed by Authorized Pgm Mgr, notify at least 2 days before shipment (702) 679-0131)

Provide to base contracting for Civil Engineering to incorporate in project folder.

Water connections tapping into ACM distro lines will require asbestos abatement plans approved before disturbing (cutting, drilling) the line.

Asbestos Demo Notification (10 days Prior to demo) https://www.clarkcountynv.gov/government/departments/en vironment_and_sustainability/division_of_air_quality/permitti ng/applications_forms/asbestos_forms.php

Lead Based Paint:

- LBP Waste Manifest

Contractor Party Executing the Work

Provide to base contracting for Civil Engineering to incorporate in project folder.

Manifest signed by Authorized Pgm Mgr (HAZWASTE PM,

(702) 652-3159)

- PCB disposal

- Hazardous Materials

- Hazardous Waste

Nellis Hazardous Waste Pgm Mgr: (702) 652-3159 Obtain HAZMART ((702) 652-9856) approval.

Nellis Hazardous Material Pgm Mgr: (702) 652-3159 Nellis Bioenvironmental Engr: (702) 652-3316 Nellis Haz Waste Pgm Mg: (702) 652-3159/679-0476

Solid Waste Program

- Landfills (None on Nellis)

- Recycled Materials

Contractor Party Executing the Work

Nellis Solid Waste Program Manager: (702) 652-4123 Qualified Recycling Program Technician: (702) 652-5270

Cultural Resources

Cultural Resources:

- Historical Sites/Facilities

- Archaeological Sites

- Tribal Consultation

Nellis AFB CRM

Nellis Archaeologists: (702) 652-6097

(702) 652-5813

Natural Resources Program

Natural Resources:

- Presence of Desert Tortoise Nellis AFB-Area I, Area II, and NTTR: Sec 7 consultation with USFWS

- Presence or Creation of a Wetland-USACE Permit

- Plants and Landscaping-tree removals-bldg demos:

Migratory Bird Treaty Act nesting surveys from Mar 1 thru Sep 1.

Proponent/ Contractor Party Executing the Work

Nellis Natural Resource Program Managers:

(702) 652-4354/7606

Petroleum, Oil, and Lubricants Program (POL)

Above-Ground Storage Tank (AST), Underground Storage Tank (UST) and Generator

- UST Installation/Upgrade/Repair Permit Application

- AST installation, upgrade, or repair

- Generator installation, upgrade, or repair

Contractor Party Executing the Work

USTs— Southern Nevada Health District: (702) 759-0603

ASTs—Storage tanks AST/UST/POL Program Manager (702)652-6121/4123

Fire Dept.—Nellis: (702) 652-9626

FUEL SPILL

Party Executing the Work

Immediately call this number anytime of the day.

Recommend posting at the job site.

702-277-1977

Work Clearance Requests (AF Form 103)

Work Clearance Requests (AF Form 103)

Contractor Party Executing the Work

Nellis CE Customer Service: (702) 652-2301 NOTE: if dust permit, ATC/OP, SWPPP, or NPDES permit required based on the guidance provided in this document, must provide them with AF Form 103 submittal!

If dust permit, ATC/OP, SWPPP, or NPDES permit required based on the guidance provided in this document, must provide them with AF Form 103 (dig permit) submittal!

If driving or storing equipment on unpaved ground, Dust permit and SWPPP Map must include those areas.

Nellis AFB unpaved areas may also be protected desert tortoise areas, therefore it is important to include the equipment driving route in the project map submittal.

https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/asbestos_forms.php https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/asbestos_forms.php https://www.clarkcountynv.gov/government/departments/environment_and_sustainability/division_of_air_quality/permitting/applications_forms/asbestos_forms.php

File details come from the government source that posted it. Updated .