About this file

This is a Questions and Answers document (Volume 3) issued by the Oregon Department of Transportation (ODOT) Procurement Office regarding RFP #730-73000-0001954 for ITSM Replacement Software, dated February 5, 2025. The document addresses two questions from interested parties, with questions being accepted until two business days prior to the bid opening date of March 7, 2025.

The Q&A document clarifies that ODOT does not have a preferred implementation partner for the ITSM replacement project. The document maintains that no modifications to the original RFI documents are made through these responses, and any changes would require a formal Addendum issued through ORBUYS.

View the file

Other files

File Type Posted
11954_Questions and Answers_Vol.4 POSTED.docx DOCX document
11954_Questions and Answers_Vol.5_POSTED.docx DOCX document
11954_Questions and Answers_Vo1.docx DOCX document
11954_Questions and Answers_Vol.2~1.docx DOCX document
11954_RFI_Addendum 2_Final.docx DOCX document
11954_Vol.8. Questions and Answers__Final Posted.docx DOCX document
Bid Cancellation Notice - 24-175-S.pdf PDF
11954_Final RFI_Posted.docx DOCX document
11954_RFI_Addendum1_Bid Open Date Changed.docx DOCX document
11954_Vol.9_Questions and Answers__Final Posted.docx DOCX document
11954_Questions and Answers_Vol.6_Final.docx DOCX document
11954_Questions and Answers_Vol.7_Final.docx DOCX document
11954_RFI_Addendum 3_Final.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ODOT Procurement Office

ODOT Procurement Office 355 Capitol St. NE Salem, OR 97301 Telephone: 503-986-2710 Email: katie.bighill@odot.oregon.gov

Date:February 5, 2025
RE:RFP #730-73000-0001954 / ITSM Replacement Software

This Questions and Answers document is ODOT’s response to questions asked by parties interested in this Request for Information (RFI). The responses are being made available to all parties interested in this RFI. This Questions and Answers document does not change or otherwise modify the RFI documents; the RFI documents can only be changed by Addendum issued on ORBUYS.

Questions and Answers, Vol #3

QUESTION:

1. Can you confirm if you have a partner of choice for the implementation of this new possible ITSM replacement?

RESPONSE:

1. We do not have an implementation partner of choice.

QUESTION:

2. Also, is the Q & A open until the RFI is closed or is there a window to submit questions?

RESPONSE:

Page 12 #8, calls for all questions to be received 2 business days prior to the BID Opening date specified in OregonBuys which is 03/07/2025

***End of Document*** Page 2 of 3 Q & A #3 RFI S-73000-0001954 image1.wmf