WDS Bond Proposal Phase 1- Ealy, Middle School, Shoreline
Solicitation number
RFP WDS 270000000188 3
Issued by
Oakland County, Michigan

About this file

This document is a Pre-Bid Meeting summary for the Whitehall District Schools Phase 1 Projects in Michigan, managed by Clark Construction Company. The project encompasses three school facilities—Whitehall Middle School, Ealy Elementary, and Shoreline Elementary—with 32 bid categories including final cleaning, commissioning, selective demolition, concrete, masonry, structural steel, carpentry, roofing, windows and glazing, drywall, flooring, painting, food service equipment, HVAC, plumbing, electrical, low voltage, fire alarm, site work, utilities, and landscaping. The pre-bid meeting was held on October 29, 2026, at 1:00 PM (ET) in Whitehall, Michigan, with site walkthroughs immediately following at Whitehall Middle School and Ealy Elementary. Bid submissions were due by November 11, 2026, at 1:00 PM (ET) through BuildingConnected, with bid opening on the same date and time. Post-bid interviews for apparent lowest responsible bidders were scheduled between November 13-20, 2026, at Clark Construction's West Michigan office in Grand Rapids. Construction phases begin April 2, 2027, for Whitehall Middle School and Ealy Elementary, concluding August 11, 2027, with Shoreline Elementary running June 7, 2027, through August 5, 2027.

Bid security of 5 percent is required, with performance and payment bonds and all associated costs included in base bids. State sales tax is required and must be incorporated into bid pricing. Prevailing wages and certified payroll are not required for this project. Trade contractors must complete Clark Construction's pre-qualification process to be eligible for Construction Manager recommendation. Mandatory bid forms include Familial Disclosure Affidavit, Affidavit of Compliance—Iran Sanctions Act, and Affidavit of Compliance—Criminal Backgrounds Check. Pre-bid requests for information were due November 3, 2026, submitted to the Project Manager via email. Bid documents, including the Clark Project Manual, Pure Architects Project Manual, and project drawings, were available through BuildingConnected. Site access requirements include mandatory personal protective equipment (hard hats, safety glasses, high-visibility shirts/vests, and gloves), daily Stretch and Flex sessions, Job Safety Analysis (JSA) submissions, and daily cleanup. Seventeen contractors and representatives attended the pre-bid meeting, representing various trade disciplines.

View the file

Other files

File Type Posted
01a - Pure Architects Bid Addendum 01.pdf PDF
01b - Millies Engineering Bid Addendum 01.pdf PDF
06 - Middle School Asbestos Survey 20260506.pdf PDF
01 - Pure Architects Addendum 02.pdf PDF
03 - Section 012300 - Alternates.pdf PDF
20261021 Phase 1 Project Schedule.pdf PDF
08 - Middle School OSHA Paint Sampling 20260914.pdf PDF
04 - Whitehall Middle School Interior Logistics Plan.pdf PDF
02 - Section 002416 Bid Category Specific Notes.pdf PDF
26 0930 WDS Ealy CD Drawings.pdf PDF
00 - Addendum 02 - Summary.pdf PDF
26 0930 WDS MS CD Drawings.pdf PDF
00 - Addendum 01 - Summary.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part1.pdf PDF
Ealy Site Logistics Plan.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part2.pdf PDF
02 - Section 002416 - Bid Categories.pdf PDF
04 - Pre-bid RFIs Addendum 2.pdf PDF
07 - Ealy Asbestos Survey 20260501.pdf PDF
05 - Middle School Existing Tunnel Location.pdf PDF
20261021 Clark Construction Project Manual.pdf PDF
09 - Ealy OSHA Paint Sampling 20260914.pdf PDF
Shoreline Logistics Plan.pdf PDF
11 - Pre-Bid RFIs Addendum 01.pdf PDF
03 - Section 012300 - ALTERNATES.pdf PDF
26 0930 WDS Shoreline CD Drawings.pdf PDF
WDS Middle School Logistics Plan.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part3.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Whitehall District Schools – Phase 1 Projects

Bid Release 01

Trade Contractor Pre -Bid Meeting (Non-Mandatory)

Clark Construction Project #25 -2983

Thursday, October 29, 2026, at 1:00 PM (ET)

Viking Athletic Center, 541 E Slocum Street , Whitehall, MI 49461

1. Introduction and Roles

Owner: Whitehall District Schools

Construction Manager: Clark Construction Company

Senior PM/Market Leader: Jamie Cardinal

Superintendent: Joe Barker

Project Manager: Tom Brennan

Project Engineer: Wyatt Foerch

Architect: Pure Architects

MEP Engineer: Millies Engineering Group

Structural Engineer: JDH Structural Engineering

Civil Engineer: Troyer Group

Technology Engineer: Communications By Design

Food Services Consultant: JRA Food Services Consultants

2. Project Background and General Scope

a. Bid Categories :

01A Final Cleaning

01B Commissioning

02A Selective Demolition

03A Concrete

04A Masonry

05A Structural & Miscellaneous Steel

06A Rough and Finish Carpentry & General Trades

07A Roofing

08A Entrances and Storefronts, Windows, Glass and Glazing

09A Metal Studs, Gypboard, Acoustical Ceilings & EIFS

09B Carpet, Resilient Flooring & Hard Tile

09C Painting and Wall Covering

11A Food Service Equipment

23A HVAC & Plumbing (Whitehall Middle School)

23B HVAC & Plumbing (Ealy Elementary)

26A Electrical, Low Voltage & Fire Alarm

31A Site Work & Site Utilities

32A Landscaping

3. Bid Documents (BuildingConnected – most reliable source)

a. Clark Project Manual

b. Pure Architects Project Manual

c. Drawings by Pure Architects

i. Whitehall Middle School

ii. Ealy Elementary

iii. Shoreline Elementary

d. Project Schedule (reference only)

4. Bidding Requirements

a. Pre-Bid Meeting / Site Visits

i. Site Walkthrough

1. Immediately following this meeting at Whitehall Middle School and

Ealy Elementary

b. Pre-Bid RFI’s

i. Submit in writing via email to Tom Brennan at tbrennan@clarkcc.com

1. Do not submit RFI’s directly to Owner or A/E

ii. Deadline for questions is 1:00 PM on Tuesday, November 3, 2026

c. Pre-Qualification

i. Trade contractors will need to be pre -qualified by Clark Construction at the time of their post-bid interview to be eligible for CM recommendation to the school district.

ii. Visit www.clarkcc.com and click on “Trade Partner Pre -Qualification” under the “Bids” menu at the top right -hand corner of the homepage.

d. Prevailing Wages

i. Prevailing wages/certified payroll are NOT required for this project.

e. Bid Submissions

i. Bids are due no later than WEDNESDAY , NOVEMBER 1 1, 2026 BY 1:00 PM

(ET) .

1. Bids are to be submitted electronically through BuildingConnected.

2. Emailed or hard copy bids will not be accepted.

ii. Bid security of 5% is required. Attach copies of bonds to electronic bid submissions.

iii. Review bid form prior to submission and familiarize yourself with certifications, questions, etc. that are required.

iv. The following forms are to be completed and attached to the electronic bid submission:

1. Familial Disclosure Affidavit

2. Affidavit of Compliance – Iran Sanctions Act

3. Affidavit of Compliance – Criminal Backgrounds Check

v. Bid opening will be on Wednesday, November 11, at 1:00 PM (ET) . Bids will be opened and read publicly in -person and via MS Teams via the link provided in the “Invitation For Bids ” document included in the project manual.

f. Post-Bid

i. Bid tabulation will be posted on Building Connected following the bid opening.

ii. Post-bid interviews will be conducted in -person between November 13-20 at

Clark Construction Company’s West Michigan office, located at 146 Monroe Center St. NW, Suite 610, Grand Rapids, MI 49503. Meeting invitations will be emailed to the apparent lowest, responsible bidders from each Bid Category on Thursday, November 12, 2026.

iii. Contractor’s proposed Project Manager and Superintendent/Foreman are expected to attend the post-bid meeting.

iv. The following will be required to be submitted at the post -bid interview:

1. Lead times for submittals

2. Lead times for materials/equipment

3. Number of working days to perform each task

4. Labor rates

5. Preliminary SOV

6. Name and contact information for proposed project manager, superintendent/foreman, safety officer, and accounting staff

7. All Clark pre -qualification documents (complete electronically)

g. Other Requirements

i. Performance and payment bonds will be required. Include cost of these in your base bid.

ii. State sales tax IS required. Include in the cost of your base bid.

iii. Mandatory Bid Alternatives:

1. Refer to Section 012300 and individual Bid Categories

iv. Specific bid categories include allowance(s) in the scope description. Include the cost of allowances in your base bid. Base bid is to include mark -up/GC’s related to the allowances.

5. Project Schedule & Phasing

a. Pull planning meeting will be held with the project team after award of bids at a date/time to be determined.

b. Site investigation walk -through will be held with the project team after award of bids at a date/time to be determined.

c. Whitehall Middle School

i. Start Date: 4/2/2027

ii. End Date: 8/11/2027

d. Ealy Elementary

i. Start Date: 4/2/2027

ii. End Date: 8/11/2027

e. Shoreline Elementary

i. Start Date: 6/7/2027

ii. End Date: 8/5/2027

6. Site Logistics/Access/Other

a. All personnel working on site will be required to wear hard hats, safety glasses, high vis shirts or vests.

b. Gloves are required to be worn at all times.

c. Strech and Flex will be done on the project everyday.

d. Work, materials, and deliveries will need to be coordinated with Clark Construction, and deliveries made per logistics plans.

e. JSA’s will be utilized and required to be submitted daily.

f. Daily cleanup will be required.

g. Onsite storage will be limited.

7. Questions

8. Site Walk -throughs

Whitehall District Schools – Phase 1 Projects

Bid Release 01

Clark Construction Project #25 -2983

Thursday, October 29, 2026, at 1:00 PM (ET)

Viking Athletic Center, 541 E Slocum Street , Whitehall, MI 49461

No. Name Organization Office Phone Cell Phone Email

1 Joe Vandenberg VanDyken Mechanical 616-224-7030 616-292-5501 jvandenberg@vdminc.com

2 Chad Vantuinen CSI 616-210-5671 chadvan@lgsti.com

3 Brandon Hills G&D Electric 616-754-9132 616-902-1048 brandonh@ganddelectric.com

4 Brad Douglass C&I Building Maintenance 616-262-1955 bradd@cibminc.com

5 Gregory Richardson Pure Architects 616-551-7684 gregory@purearchitects.com

6 Nick Wallis Pure Architects 616-485-8992 nick@purearchitects.com

7 Kyle Paquette J Stevens Construction jason@jstevensconstruction.com

8 Julie Fancher CBS 231-744-2461 231-578-3254 jfaucher@cbs -mi.com

9 Gene Magoon Pleune Service Co. 616-260-9489 gmagoon@pleuneservice.com

10 Juan Munoz Excel Roofing 616-446-5430 juan@excelroofs.com

Whitehall District Schools – Phase 1 Projects | Bid Release 01

No. Name Organization Office Phone Cell Phone Email

11 Steve Null Tridonn 231-638-8796 snull@tridonn.com

12 Alan Nicholson E3M 517-214-9050 anicholson@e3msolutions.com

13 Justin Visconti White Lake Glass 231-578-7541 justin@whitelakeglass.com

14 Doug Boardwell Hurst Mechanical 616-784-4040 dboardwell@hurstind.com

15 Calvin Cusack Cusacks Masonry 989-981-6625 mail@cusacksmasonry.com

16 Nate Armstrong Skyproof 906-203-2702 nate@skyproof.com

17 Erik Allore Clifford Buck Construction 231-286-8043 erik@cliffordbuck.com

20261029 WDS Prebid Meeting
1. Introduction and Roles
2. Project Background and General Scope
3. Bid Documents (BuildingConnected – most reliable source)
4. Bidding Requirements
5. Project Schedule & Phasing
6. Site Logistics/Access/Other
7. Questions
8. Site Walk-throughs

20261029 WDS Prebid Meeting - Sign-in