04 - Pre-bid RFIs Addendum 2.pdf
PDF 275 KB Posted
- Solicitation number
- RFP WDS 270000000188 3
- Issued by
- Oakland County, Michigan
About this file
Summary
This document is a Pre-Bid Requests for Information (RFI) Addendum No. 2 for the Whitehall District Schools 2025 Bond project (25-2983) located at 541 E. Slocum Street, Whitehall, MI 49461. The addendum addresses eleven pre-bid RFIs submitted by Clark Construction Company between November 3-5, 2026, with responses provided by Pure Architects (Nate Gilman) between November 3-5, 2026. The RFIs address clarifications required for both Ealy Elementary and Whitehall Middle School renovation work, including demolition scope clarifications, drawing conflicts, missing alternates, material specifications, structural details, and mechanical/electrical coordination issues. Key issues resolved include removal of carpet tile salvage callouts in bathroom areas, coordination of ceiling removal work in Unit A, addition of Alternate A3 (manual roller shades) and Alternate A5 (Mosaic Tile) to the alternates legend, clarification that existing media center ceiling remains with only tile replacement required, resolution of conflicting slab thickness specifications (4" versus 5"), removal of a reference to non-existent drawing sheet A423, confirmation that no additional gym roof replacement details will be provided, and clarification on commissioning requirements for terminal equipment and lighting controls. All RFIs were resolved and assigned to Pure Architects team members (Gregory Richardson, Nate Gilman, Nick Wallis, and Quint Rauch) with completion status marked as of November 6, 2026.
The addendum also includes RFIs addressing floor sawcutting requirements in the cafeteria area for utility connections and clarification regarding prefinished aluminum sill flashing requirements at new window and cast stone sill locations at the middle school. No pricing information, payment terms, set-asides, incumbent contractor status, or funding sources are identified in this RFI addendum document, which serves solely as a pre-bid clarification mechanism to ensure consistent interpretation of contract documents by prospective bidders.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information
Detailed with Comments and Links
Whitehall District Schools 2025 Bond (25-2983) 541 E. Slocum Street
Whitehall, MI 49461
0006 - Pre-Bid - Carpet Tile Salvage Callout in Bathrooms
Subject Pre-Bid - Carpet Tile Salvage Callout in Bathrooms
Status Closed by Architect n
Discipline
Demolition
Location
Ealy Elementary
Phase
Preconstruction
Created on
11/3/2026
Due date
11/10/2026
Date resolved
11/3/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/3/2026 10:48 AM
Please refer to attachment.
There is a callout in the gang bathrooms to salvage existing carpet tile around mechanical equipment for patch and repair. With the bathrooms not being carpeted, this callout would not apply. Please remove these callouts from the bathrooms.
File
RFI - Ealy - Bath...
Wyatt Foerch
ANSWER Nate Gilman on 11/3/2026 01:17 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)
Noted - removed per Addendum #2
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 1 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750852
Whitehall District Schools 2025 Bond (25-2983) 541 E. Slocum Street
Whitehall, MI 49461
0007 - Pre-Bid - Unit A Ceiling Removal Drawing Conflict
Subject Pre-Bid - Unit A Ceiling Removal Drawing Conflict
Status Closed by Architect n
Discipline
Architectural
Location
Ealy Elementary
Phase
Preconstruction
Created on
11/3/2026
Due date
11/10/2026
Date resolved
11/3/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/3/2026 10:52 AM
Please refer to attachment.
In unit A, most of the area is hatched and called out as "not in scope". The hatching overlaps a section of ceiling called out to be removed and replaced. Please remove the "not in scope" hatching from the ceiling area being worked on to avoid confusion.
File
RFI - Ealy - Unit...
Wyatt Foerch
ANSWER Nate Gilman on 11/3/2026 01:28 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)
Noted, ceiling work hatch will be coordinated with MEP - within Addendum #2
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 2 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750859
0008 - Pre-Bid - Ealy Missing Alternates List
Subject Pre-Bid - Ealy Missing Alternates List
Status Closed by Architect n
Discipline
Architectural
Location
Ealy Elementary
Phase
Preconstruction
Created on
11/3/2026
Due date
11/10/2026
Date resolved
11/3/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/3/2026 11:00 AM
Please refer to attachment.
On sheet G002, there do not appear to be any alternates listed. On sheet I101, there is an alternate listed for manual roller shades. Please add this alternate and any other missing alternates to G002.
File
RFI - Ealy - Wind...
Wyatt Foerch
ANSWER Nate Gilman on 11/3/2026 01:32 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)
Noted Alternate A3 shall be added to G002 on Ealy per Addendum 02
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 3 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750873
0009 - Pre-Bid - Material Selection Schedule Tile Alternate
Subject Pre-Bid - Material Selection Schedule Tile Alternate
Status Closed by Architect n
Discipline
Architectural
Location
Middle School
Phase
Preconstruction
Created on
11/3/2026
Due date
11/10/2026
Date resolved
11/3/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/3/2026 11:02 AM
Please refer to attachment.
On sheet I001, there is an alternate listed for Mosaic Tile. This alternate is not listed in the alternates on G002. Please add this alternate to that list on G002.
File
RFI - MS - Tile A...
Wyatt Foerch
ANSWER Nate Gilman on 11/3/2026 01:46 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)
This will be changed to A5 and added to the alternates legend on G002
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 4 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750874
0010 - Pre-Bid - Media Center Ceiling Demo
Subject Pre-Bid - Media Center Ceiling Demo
Status Closed by Architect n
Discipline
Demolition
Location
Middle School
Phase
Preconstruction
Created on
11/3/2026
Due date
11/10/2026
Date resolved
11/3/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/3/2026 11:04 AM
Please refer to attachment.
The mechanical and electrical drawings show demo of ceiling fixtures in the media center. D201 does not show demo of the ceiling itself at all; is the intention for the ceiling to be removed as well or no? If it is, please adjust drawings accordingly.
File
RFI - MS - Media ...
Wyatt Foerch
ANSWER Nate Gilman on 11/3/2026 01:52 PM (Promoted by Wyatt Foerch on 11/6/2026 11:16 AM)
Drawings are correct, existing ceiling remains. Only replace ceiling tiles as required for new MEP work.
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 5 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750875
0011 - Pre-Bid - Unit B Slab Thickness
Subject Pre-Bid - Unit B Slab Thickness
Status Closed by Architect n
Discipline
Structural
Location
Middle School
Phase
Preconstruction
Created on
11/4/2026
Due date
11/11/2026
Date resolved
11/6/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/4/2026 11:28 AM
On sheet S101B, the plans call for a 4" slab on grade, however the notes below call for a 5" slab on grade with 2.9w.
Please advise what is to be quoted.
File
RFI - MS - Unit B...
Wyatt Foerch
ANSWER Nate Gilman on 11/6/2026 07:29 AM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM)
See the attached drawing -
File
WDS - MS RFI 0011...
Nate Gilman
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 6 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=752415 https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=753886
0012 - Pre-Bid - Reference to Non-Existent Drawing
Subject Pre-Bid - Reference to Non-Existent Drawing
Status Closed by Architect n
Discipline
All Disciplines
Location
Middle School
Phase
Preconstruction
Created on
11/4/2026
Due date
11/11/2026
Date resolved
11/4/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/4/2026 11:55 AM
Please refer to attachment.
On sheet A120, detail 3/A423 is referenced. There does not appear to be a sheet A423. Please adjust the detail/drawings accordingly.
File
RFI - MS - Refere...
Wyatt Foerch
ANSWER Nate Gilman on 11/4/2026 12:51 PM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM) that reference shall be removed in Add 02. There is no sheet A423.
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 7 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=752434
0013 - Pre-Bid - Gym Roof Replacement Details
Subject Pre-Bid - Gym Roof Replacement Details
Status Closed by Architect n
Discipline
Architectural
Location
Middle School
Phase
Preconstruction
Created on
11/4/2026
Due date
11/11/2026
Date resolved
11/4/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/4/2026 11:58 AM
Are there any further details forthcoming for the middle school gym roof replacement shown on detail 1/A120?
ANSWER Nate Gilman on 11/4/2026 12:53 PM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM)
No additional details will be provided. The note for roof 17 state the expectations.
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 8 of 11Printed on: 11/6/2026ProjectSight
0014 - Pre-Bid - Commissioning Clarification Questions
Subject Pre-Bid - Commissioning Clarification Questions
Status Closed by Architect n
Discipline
Mechanical
Location
Multiple
Phase
Preconstruction
Created on
11/4/2026
Due date
11/11/2026
Date resolved
11/4/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/4/2026 12:05 PM
Will terminal heating and cooling equipment need to be commissioned?
Will the project testing requirements involve 100% verification of in-scope equipment?
According to the Michigan Energy Code, lighting controls that are automatic receptacle control are required to be commissioned. Will this be required as part of the commissioning scope of work?
ANSWER Nate Gilman on 11/4/2026 01:50 PM (Promoted by Wyatt Foerch on 11/6/2026 11:19 AM)
Yes, project commissioning and testing shall include 100% of the new systems and equipment. Yes commissioning for new lighting and receptacle control systems shall be included.
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 9 of 11Printed on: 11/6/2026ProjectSight
0015 - Pre-Bid - Cafeteria Sawcutting for Utilities
Subject Pre-Bid - Cafeteria Sawcutting for Utilities
Status Closed by Architect n
Discipline
Demolition
Location
Middle School
Phase
Preconstruction
Created on
11/5/2026
Due date
11/12/2026
Date resolved
11/5/2026
Author
Wyatt Foerch
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Wyatt Foerch on 11/5/2026 08:12 AM
Please refer to attachment.
In the area highlighted in yellow, the floor is called out to be removed for new utility connections (note 15). There is no underslab MEP work indicated in this area; should it be removed for note 15?
Please advise.
File
D101B Sawcutting ...
Wyatt Foerch
ANSWER Nate Gilman on 11/5/2026 09:33 AM (Promoted by Wyatt Foerch on 11/6/2026 11:20 AM)
Yes, it can be removed. Even with these demo plans, there still needs to be coordination between all trades for exact locations of demo.
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Page 10 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=753083
0016 - Pre-Bid - Prefinished aluminum sill flashing at new windows
Subject Pre-Bid - Prefinished aluminum sill flashing at new windows
Status Closed by Architect n
Discipline
Architectural
Location
Middle School
Phase
Preconstruction
Created on
11/5/2026
Due date
11/12/2026
Date resolved
11/5/2026
Author
Tom Brennan
Clark Construction Company
Resolved by
Nate Gilman
Pure Architects
QUESTION Tom Brennan on 11/5/2026 03:34 PM
At Whitehall Middle School, detail 2/A421 indicates prefinished aluminum sill flashing over the existing cast stone sill as part of the new window assembly. Details 4/A421 and 6/A421 appear to depict similar prefinished aluminum sill flashing over the new cast stone; however, the flashing is not identified or called out in these details. Please clarify whether prefinished aluminum sill flashing is required at the new cast stone sills shown in Details 4/A421 and 6/A421.
ANSWER Nate Gilman on 11/5/2026 04:27 PM (Promoted by Wyatt Foerch on 11/6/2026 11:21 AM)
Please provide prefinished aluminum sill flashing at all new sills
ASSIGNMENTS
Gregory Richardson (Pure Architects) Done on 11/6/2026
Nate Gilman (Pure Architects) Done on 11/6/2026
Nick Wallis (Pure Architects) Done on 11/6/2026
Quint Rauch (Pure Architects) Done on 11/6/2026
Tom Brennan (Clark Construction Company) Done on 11/6/2026
Page 11 of 11Printed on: 11/6/2026ProjectSight
File details come from the government source that posted it. Updated .