WDS Bond Proposal Phase 1- Ealy, Middle School, Shoreline
Solicitation number
RFP WDS 270000000188 3
Issued by
Oakland County, Michigan

About this file

Summary

This document is a Pre-Bid Requests for Information (RFI) Addendum No. 2 for the Whitehall District Schools 2025 Bond project (25-2983) located at 541 E. Slocum Street, Whitehall, MI 49461. The addendum addresses eleven pre-bid RFIs submitted by Clark Construction Company between November 3-5, 2026, with responses provided by Pure Architects (Nate Gilman) between November 3-5, 2026. The RFIs address clarifications required for both Ealy Elementary and Whitehall Middle School renovation work, including demolition scope clarifications, drawing conflicts, missing alternates, material specifications, structural details, and mechanical/electrical coordination issues. Key issues resolved include removal of carpet tile salvage callouts in bathroom areas, coordination of ceiling removal work in Unit A, addition of Alternate A3 (manual roller shades) and Alternate A5 (Mosaic Tile) to the alternates legend, clarification that existing media center ceiling remains with only tile replacement required, resolution of conflicting slab thickness specifications (4" versus 5"), removal of a reference to non-existent drawing sheet A423, confirmation that no additional gym roof replacement details will be provided, and clarification on commissioning requirements for terminal equipment and lighting controls. All RFIs were resolved and assigned to Pure Architects team members (Gregory Richardson, Nate Gilman, Nick Wallis, and Quint Rauch) with completion status marked as of November 6, 2026.

The addendum also includes RFIs addressing floor sawcutting requirements in the cafeteria area for utility connections and clarification regarding prefinished aluminum sill flashing requirements at new window and cast stone sill locations at the middle school. No pricing information, payment terms, set-asides, incumbent contractor status, or funding sources are identified in this RFI addendum document, which serves solely as a pre-bid clarification mechanism to ensure consistent interpretation of contract documents by prospective bidders.

View the file

Other files

File Type Posted
01a - Pure Architects Bid Addendum 01.pdf PDF
01b - Millies Engineering Bid Addendum 01.pdf PDF
06 - Middle School Asbestos Survey 20260506.pdf PDF
01 - Pure Architects Addendum 02.pdf PDF
03 - Section 012300 - Alternates.pdf PDF
20261021 Phase 1 Project Schedule.pdf PDF
08 - Middle School OSHA Paint Sampling 20260914.pdf PDF
04 - Whitehall Middle School Interior Logistics Plan.pdf PDF
02 - Section 002416 Bid Category Specific Notes.pdf PDF
26 0930 WDS Ealy CD Drawings.pdf PDF
00 - Addendum 02 - Summary.pdf PDF
26 0930 WDS MS CD Drawings.pdf PDF
00 - Addendum 01 - Summary.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part1.pdf PDF
Ealy Site Logistics Plan.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part2.pdf PDF
02 - Section 002416 - Bid Categories.pdf PDF
07 - Ealy Asbestos Survey 20260501.pdf PDF
10 - 20261029 Pre-Bid Meeting.pdf PDF
05 - Middle School Existing Tunnel Location.pdf PDF
20261021 Clark Construction Project Manual.pdf PDF
09 - Ealy OSHA Paint Sampling 20260914.pdf PDF
Shoreline Logistics Plan.pdf PDF
11 - Pre-Bid RFIs Addendum 01.pdf PDF
03 - Section 012300 - ALTERNATES.pdf PDF
26 0930 WDS Shoreline CD Drawings.pdf PDF
WDS Middle School Logistics Plan.pdf PDF
26 0930 WDS Phase 1 - Project Manual_Part3.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information

Detailed with Comments and Links

Whitehall District Schools 2025 Bond (25-2983) 541 E. Slocum Street

Whitehall, MI 49461

0006 - Pre-Bid - Carpet Tile Salvage Callout in Bathrooms

Subject Pre-Bid - Carpet Tile Salvage Callout in Bathrooms

Status Closed by Architect n

Discipline

Demolition

Location

Ealy Elementary

Phase

Preconstruction

Created on

11/3/2026

Due date

11/10/2026

Date resolved

11/3/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/3/2026 10:48 AM

Please refer to attachment.

There is a callout in the gang bathrooms to salvage existing carpet tile around mechanical equipment for patch and repair. With the bathrooms not being carpeted, this callout would not apply. Please remove these callouts from the bathrooms.

File

RFI - Ealy - Bath...

Wyatt Foerch

ANSWER Nate Gilman on 11/3/2026 01:17 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)

Noted - removed per Addendum #2

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 1 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750852

Whitehall District Schools 2025 Bond (25-2983) 541 E. Slocum Street

Whitehall, MI 49461

0007 - Pre-Bid - Unit A Ceiling Removal Drawing Conflict

Subject Pre-Bid - Unit A Ceiling Removal Drawing Conflict

Status Closed by Architect n

Discipline

Architectural

Location

Ealy Elementary

Phase

Preconstruction

Created on

11/3/2026

Due date

11/10/2026

Date resolved

11/3/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/3/2026 10:52 AM

Please refer to attachment.

In unit A, most of the area is hatched and called out as "not in scope". The hatching overlaps a section of ceiling called out to be removed and replaced. Please remove the "not in scope" hatching from the ceiling area being worked on to avoid confusion.

File

RFI - Ealy - Unit...

Wyatt Foerch

ANSWER Nate Gilman on 11/3/2026 01:28 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)

Noted, ceiling work hatch will be coordinated with MEP - within Addendum #2

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 2 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750859

0008 - Pre-Bid - Ealy Missing Alternates List

Subject Pre-Bid - Ealy Missing Alternates List

Status Closed by Architect n

Discipline

Architectural

Location

Ealy Elementary

Phase

Preconstruction

Created on

11/3/2026

Due date

11/10/2026

Date resolved

11/3/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/3/2026 11:00 AM

Please refer to attachment.

On sheet G002, there do not appear to be any alternates listed. On sheet I101, there is an alternate listed for manual roller shades. Please add this alternate and any other missing alternates to G002.

File

RFI - Ealy - Wind...

Wyatt Foerch

ANSWER Nate Gilman on 11/3/2026 01:32 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)

Noted Alternate A3 shall be added to G002 on Ealy per Addendum 02

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 3 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750873

0009 - Pre-Bid - Material Selection Schedule Tile Alternate

Subject Pre-Bid - Material Selection Schedule Tile Alternate

Status Closed by Architect n

Discipline

Architectural

Location

Middle School

Phase

Preconstruction

Created on

11/3/2026

Due date

11/10/2026

Date resolved

11/3/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/3/2026 11:02 AM

Please refer to attachment.

On sheet I001, there is an alternate listed for Mosaic Tile. This alternate is not listed in the alternates on G002. Please add this alternate to that list on G002.

File

RFI - MS - Tile A...

Wyatt Foerch

ANSWER Nate Gilman on 11/3/2026 01:46 PM (Promoted by Wyatt Foerch on 11/6/2026 11:15 AM)

This will be changed to A5 and added to the alternates legend on G002

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 4 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750874

0010 - Pre-Bid - Media Center Ceiling Demo

Subject Pre-Bid - Media Center Ceiling Demo

Status Closed by Architect n

Discipline

Demolition

Location

Middle School

Phase

Preconstruction

Created on

11/3/2026

Due date

11/10/2026

Date resolved

11/3/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/3/2026 11:04 AM

Please refer to attachment.

The mechanical and electrical drawings show demo of ceiling fixtures in the media center. D201 does not show demo of the ceiling itself at all; is the intention for the ceiling to be removed as well or no? If it is, please adjust drawings accordingly.

File

RFI - MS - Media ...

Wyatt Foerch

ANSWER Nate Gilman on 11/3/2026 01:52 PM (Promoted by Wyatt Foerch on 11/6/2026 11:16 AM)

Drawings are correct, existing ceiling remains. Only replace ceiling tiles as required for new MEP work.

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 5 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=750875

0011 - Pre-Bid - Unit B Slab Thickness

Subject Pre-Bid - Unit B Slab Thickness

Status Closed by Architect n

Discipline

Structural

Location

Middle School

Phase

Preconstruction

Created on

11/4/2026

Due date

11/11/2026

Date resolved

11/6/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/4/2026 11:28 AM

On sheet S101B, the plans call for a 4" slab on grade, however the notes below call for a 5" slab on grade with 2.9w.

Please advise what is to be quoted.

File

RFI - MS - Unit B...

Wyatt Foerch

ANSWER Nate Gilman on 11/6/2026 07:29 AM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM)

See the attached drawing -

File

WDS - MS RFI 0011...

Nate Gilman

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 6 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=752415 https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=753886

0012 - Pre-Bid - Reference to Non-Existent Drawing

Subject Pre-Bid - Reference to Non-Existent Drawing

Status Closed by Architect n

Discipline

All Disciplines

Location

Middle School

Phase

Preconstruction

Created on

11/4/2026

Due date

11/11/2026

Date resolved

11/4/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/4/2026 11:55 AM

Please refer to attachment.

On sheet A120, detail 3/A423 is referenced. There does not appear to be a sheet A423. Please adjust the detail/drawings accordingly.

File

RFI - MS - Refere...

Wyatt Foerch

ANSWER Nate Gilman on 11/4/2026 12:51 PM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM) that reference shall be removed in Add 02. There is no sheet A423.

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 7 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=752434

0013 - Pre-Bid - Gym Roof Replacement Details

Subject Pre-Bid - Gym Roof Replacement Details

Status Closed by Architect n

Discipline

Architectural

Location

Middle School

Phase

Preconstruction

Created on

11/4/2026

Due date

11/11/2026

Date resolved

11/4/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/4/2026 11:58 AM

Are there any further details forthcoming for the middle school gym roof replacement shown on detail 1/A120?

ANSWER Nate Gilman on 11/4/2026 12:53 PM (Promoted by Wyatt Foerch on 11/6/2026 11:18 AM)

No additional details will be provided. The note for roof 17 state the expectations.

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 8 of 11Printed on: 11/6/2026ProjectSight

0014 - Pre-Bid - Commissioning Clarification Questions

Subject Pre-Bid - Commissioning Clarification Questions

Status Closed by Architect n

Discipline

Mechanical

Location

Multiple

Phase

Preconstruction

Created on

11/4/2026

Due date

11/11/2026

Date resolved

11/4/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/4/2026 12:05 PM

Will terminal heating and cooling equipment need to be commissioned?

Will the project testing requirements involve 100% verification of in-scope equipment?

According to the Michigan Energy Code, lighting controls that are automatic receptacle control are required to be commissioned. Will this be required as part of the commissioning scope of work?

ANSWER Nate Gilman on 11/4/2026 01:50 PM (Promoted by Wyatt Foerch on 11/6/2026 11:19 AM)

Yes, project commissioning and testing shall include 100% of the new systems and equipment. Yes commissioning for new lighting and receptacle control systems shall be included.

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 9 of 11Printed on: 11/6/2026ProjectSight

0015 - Pre-Bid - Cafeteria Sawcutting for Utilities

Subject Pre-Bid - Cafeteria Sawcutting for Utilities

Status Closed by Architect n

Discipline

Demolition

Location

Middle School

Phase

Preconstruction

Created on

11/5/2026

Due date

11/12/2026

Date resolved

11/5/2026

Author

Wyatt Foerch

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Wyatt Foerch on 11/5/2026 08:12 AM

Please refer to attachment.

In the area highlighted in yellow, the floor is called out to be removed for new utility connections (note 15). There is no underslab MEP work indicated in this area; should it be removed for note 15?

Please advise.

File

D101B Sawcutting ...

Wyatt Foerch

ANSWER Nate Gilman on 11/5/2026 09:33 AM (Promoted by Wyatt Foerch on 11/6/2026 11:20 AM)

Yes, it can be removed. Even with these demo plans, there still needs to be coordination between all trades for exact locations of demo.

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Page 10 of 11Printed on: 11/6/2026ProjectSight https://prod.projectsightapp.trimble.com/web/app/Project?orgid=b3aa1dd5-8e59-4df0-a565-5749fd1ed64f&projid=182&Key=753083

0016 - Pre-Bid - Prefinished aluminum sill flashing at new windows

Subject Pre-Bid - Prefinished aluminum sill flashing at new windows

Status Closed by Architect n

Discipline

Architectural

Location

Middle School

Phase

Preconstruction

Created on

11/5/2026

Due date

11/12/2026

Date resolved

11/5/2026

Author

Tom Brennan

Clark Construction Company

Resolved by

Nate Gilman

Pure Architects

QUESTION Tom Brennan on 11/5/2026 03:34 PM

At Whitehall Middle School, detail 2/A421 indicates prefinished aluminum sill flashing over the existing cast stone sill as part of the new window assembly. Details 4/A421 and 6/A421 appear to depict similar prefinished aluminum sill flashing over the new cast stone; however, the flashing is not identified or called out in these details. Please clarify whether prefinished aluminum sill flashing is required at the new cast stone sills shown in Details 4/A421 and 6/A421.

ANSWER Nate Gilman on 11/5/2026 04:27 PM (Promoted by Wyatt Foerch on 11/6/2026 11:21 AM)

Please provide prefinished aluminum sill flashing at all new sills

ASSIGNMENTS

Gregory Richardson (Pure Architects) Done on 11/6/2026

Nate Gilman (Pure Architects) Done on 11/6/2026

Nick Wallis (Pure Architects) Done on 11/6/2026

Quint Rauch (Pure Architects) Done on 11/6/2026

Tom Brennan (Clark Construction Company) Done on 11/6/2026

Page 11 of 11Printed on: 11/6/2026ProjectSight