This document is the Instructions to Bidders for a state construction contract issued by the State of Hawaii Department of Land and Natural Resources for repair and maintenance work on the Hapuna Beach State Recreation Area Pavilion located in Waimea, Hawaii (Project No. F75C646H, Solicitation H26002603). The project scope encompasses demolition and replacement of deteriorated exterior siding and screen wall assemblies, installation of concrete curbing, surface preparation, priming, painting, and related work to restore the pavilion's building envelope. A mandatory site visit and voluntary pre-bid conference will be held on May 5, 2026, at 10:00 a.m. at the parking lot closest to the pavilion. Sealed bids must be submitted through the State of Hawaii e-Procurement System (HIePRO) by May 14, 2026. The contract will be awarded to the lowest responsive and responsible bidder, with work completion required within 180 consecutive calendar days from written notice to proceed. Liquidated damages of $150 per calendar day will be assessed for failure to meet the completion deadline.
Bidders must hold a valid State of Hawaii Contractor's license (Classification A) and comply with all applicable Hawaii Revised Statutes and Administrative Rules requirements, including submission of tax clearance certificates, Department of Labor Certificate of Compliance, and Department of Commerce and Consumer Affairs Certificate of Good Standing, or alternatively utilize the Hawaii Compliance Express system. The estimated project budget is $245,000, with performance and payment bonds required equal to 100 percent of the total contract price. Prevailing wage requirements apply to all laborers and mechanics, and contractors must ensure that Hawaii residents compose at least 80 percent of the workforce. A 10 percent price preference for recycled products applies when proper certification is provided. Bidders are responsible for obtaining all required permits and licenses, providing a complete listing of joint contractors or subcontractors with appropriate specialty licenses, and verifying all field measurements and quantities before bid submission. No apprenticeship set-asides apply as the estimated construction cost falls below the $250,000 threshold triggering such requirements.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I-1
INFORMATION AND INSTRUCTIONS TO BIDDERS
CONTENTS
Page
A Project Location and Scope of Work ............................................................... I-2
B Proposals ........................................................................................................... I-2
C General Conditions ........................................................................................... I-2
D Proposal Form ................................................................................................... I-2
E Omissions or Erasures ....................................................................................... I-2
F Notice of Intent to Bid and Questionnaire .......................................................... I-2
G Bid Security ...................................................................................................... I-2
H Contractor’s License Required ........................................................................... I-2
I Irregular Bids .................................................................................................... I-3
J Withdrawal of Bids ........................................................................................... I-3
K Evaluation Criteria .............................................................................................. I-3
L Method of Award ................................................................................................ I-3
M Successful Bidder to File Performance and Payment Bonds ............................ I-3
N Number of Executed Original Counterparts of Contract Documents ............... I-3
O Change Orders .................................................................................................. I-4
P Wages and Hours .............................................................................................. I-4
Q Permits ................................................................................................................ I-4
R Property Damage ................................................................................................ I-4
S Time .................................................................................................................. I-4
T Bidder's Responsibility to Provide Proper Superintendence .............................. I-5
U Liquidated Damages ......................................................................................... I-5
V Hiring of Hawaii Residents ................................................................................ I-5
W Water and Electricity ........................................................................................ I-5
X Public Convenience and Safety ........................................................................ I-5
Y Work to be Done Without Direct Payment .......................................................... I-6
Z As-Built Drawings ............................................................................................ I-6
AA Asbestos Containing Materials ......................................................................... I-6
BB Worker Safety ..................................................................................................... I-6
CC Toilet Facilities ................................................................................................. I-6
DD Signs .................................................................................................................. I-6
EE Field Office for Department .............................................................................. I-7
FF Quantities .......................................................................................................... I-7
GG Other Health Measures ..................................................................................... I-7
HH Hawaii Business Requirement .......................................................................... I-7
II Compliance With §3-122-112 HAR ................................................................... I-7
I-2
INFORMATION AND INSTRUCTIONS TO BIDDERS
A. PROJECT LOCATION AND SCOPE OF WORK: The project location and scope of work shall be as generally described in the Notice to Bidders.
B. PROPOSALS: Bidders shall submit their bid, including the completed proposal form, bid bond, and any other documents required by the solicitation as part of their bid through the
State of Hawaii e-Procurement System (HIePRO). See Item D, PROPOSAL FORM.
C. GENERAL CONDITIONS: The Department of Land and Natural Resources Interim
General Conditions dated October 1994, as amended, shall be made a part of these contract specifications and are referred to hereafter as the General Conditions.
D. PROPOSAL FORM: The Bidders shall fill out and upload the electronic copy of the proposal form to the HIePRO website when submitting the bid. Bid Proposals shall not be mailed, faxed or delivered to the State, unless requested to do so after the designated closing date. The successful Bidder shall fill out and print a hard copy of the proposal form, sign and submit the form with the contract award package.
E. OMISSIONS OR ERASURES: Any proposal which contains any omission or erasure or alteration not properly initialed, or conditional bid, or other irregularity may be rejected by the Board of Land and Natural Resources (Board).
F. NOTICE OF INTENT TO BID AND QUESTIONNAIRE:
A Notice of Intent to Bid is not required for this project. In compliance with HRS Section
103D-310, the lowest responsive and responsible bidder may be required to complete a questionnaire. When requested by the State, the completed questionnaire shall be submitted to the Chief Engineer for evaluation. Failure to furnish the requested information within the time allowed may be grounds for a determination of non-responsibility, in accordance with
HRS Section 103D-310 and HAR Section 3-122-108.
G. BID SECURITY: A bid security will be furnished by each bidder as provided in sub-section
2.7 of the General Conditions. The successful bidder's bid security will be retained until
Contract execution and furnished a performance and payment bond in an amount equal to one hundred percent (100%) of the total Contract price, including an amount estimated to be required for extra work, is furnished.
The Board reserves the right to hold the bid securities of the four lowest bidders until the successful bidder has entered into a contract and has furnished the required performance bond. All bid securities will be returned in accordance with sub-section 3.5 of the General
Conditions.
Should the successful bidder fail to enter into a contract and furnish a satisfactory performance bond within the time stated in the proposal, the bid security shall be forfeited as required by law.
H. CONTRACTOR'S LICENSE REQUIRED: The Board will reject all bids received from contractors who have not been licensed by the State Contractors License Board in accordance
I-3 with Chapter 444, HRS; Title 16, Chapter 77, Hawaii Administrative Rules; and statutes amendatory thereto.
I. IRREGULAR BIDS: No irregular bids or propositions for doing the work will be considered by the Board.
J. WITHDRAWAL OF BIDS: No bidder may withdraw his bid between the time of the opening thereof and the award of contract.
K. EVALUATION CRITERIA:
1. The total lump sum base bid price and additives will be adjusted to reflect the applicable preferences.
2. Evaluating Bids with Additive Bid Items:
a. After the solicitation ends, the State will announce the project control budget.
All bids will be evaluated on the basis of the same additive item.
b. If the Base Bids of all the Bidders are within the project control budget (after application of the various preferences), Additive #4, then Additive #2, then
Additive #3, and then Additive #1 are added to the Base Bid amount. This
(these) sum(s) are compared to the project control budget and must be within the project control budget.
c. The Bidder with the lowest Base Bid or aggregate amount (Base Bid plus additives), within the project control budget, is the “Low Bidder” for that project and is designated for award.
L. METHOD OF AWARD:
1. The contract will be awarded to the lowest responsive and responsible Bidder whose bid (including any additive(s) which may be selected) meets the requirements and criteria set forth in the solicitation documents and as determined by the Board of Land and Natural Resources.
2. In the event the Lump Sum Base Bid of all bidders exceeds the project control budget, the Department reserves the right to make an award to the bidder with the lowest total lump sum base bid, after application of the preferences is designated, if additional funds are available or by reducing the scope of work through negotiation.
M. SUCCESSFUL BIDDER TO FILE PERFORMANCE AND PAYMENT BONDS: The successful bidder will be required to file performance and payment bonds each; in the amount equal to the total contract price, including amounts estimated to be required for extra work, as provided in sub-section 3.6 of the General Conditions.
N. NUMBER OF EXECUTED ORIGINAL COUNTERPARTS OF CONTRACT
DOCUMENTS: If requested by the Board, six copies of the Contract, performance and payment bonds shall be executed.
I-4
O. CHANGE ORDERS: No work of any kind in connection with the work covered by the plans and specifications shall be considered as change order work, or entitle the Contractor to extra compensation, except when the work has been ordered in writing by the Chief Engineer
(Engineer) and in accordance with sub-section 4.2 of the General Conditions.
The Contractor shall clearly identify and inform the Engineer in writing of any deviations from the contract documents at the time of submission and shall obtain the Engineer's written approval to the specified deviation prior to proceeding with any work.
P. WAGES AND HOURS: In accordance with sub-sections 7.3 to 7.9 of the General
Conditions relative to hours of labor, minimum wages and overtime pay, the current minimum wage rates promulgated by the Department of Labor and Industrial Relations
(DLIR) shall be paid to the various classes of laborers and mechanics engaged in the performance of this contract on the job site. The minimum wages shall be increased during the performance of the contract in an amount equal to the increase in the prevailing wages for those kinds of work as periodically determined by the DLIR.
The Department of Land and Natural Resources will not recognize any claim for additional compensation because of the payment by the Contractor of any wage rate in excess of the said minimum wage rates. The possibility of wage increase is one of the elements to be considered by the Contractor in determining his bid, and will not, under any circumstances, be considered as the basis of a claim against the Department under this Contract.
No work shall be done on Saturdays, Sundays, legal State holidays, and/or in excess of eight
(8) hours each day without the written consent of the Engineer. Should permission be granted to work at such times, the Contractor shall pay for all inspection administrative costs thereof. No work shall be done at night unless authorized by the Engineer.
Q. PERMITS: The State will process permit applications whenever possible, and the Contractor shall procure the pre-processed permits and pay the required fees. If permit applications are not processed by the State, the Contractor shall process the permit applications, permits and licenses, and pay all charges and fees. In all cases, the Contractor shall give all notices necessary and incident to the due and lawful prosecution of the work.
R. PROPERTY DAMAGE: It shall be the responsibility of the contractor to respect State property and to prevent damage to existing improvements. The Contractor will be responsible for damages resulting from construction operations. Immediately upon discovery, the Contractor shall repair such damage to the satisfaction of the Engineer.
All trees and shrubbery outside the excavation, embankment or construction limits shall be fully protected from injury.
S. TIME: The time of completion is specified in the Proposal. It is the Board's intention to insist the Contractor diligently prosecute the work to completion within the specified time.
Prospective bidders are reminded that the State has the option to proceed with or abandon a project depending on whether the project can be completed for occupancy in the specified time.
I-5
It is the bidder's responsibility to check the availability of all materials before bidding. The bidder shall select sub-contractors and suppliers who can warrant availability and delivery of all specified or qualified materials to assure project completion within the specified time.
The successful bidder must assume all risks for completing the project by the specified date.
There shall be no extension of time for any reason except for delays caused by acts of God, labor disputes involving unions, or actions of the State. If for any reason the project falls behind schedule, the Contractor shall at its own cost, take necessary remedial measures to get the project back on schedule, i.e., working overtime, air freighting all materials, etc. In addition, if the Contractor fails to fully complete the project by the completion date, Contractor will be required to make the facility usable at its own cost.
T. BIDDER'S RESPONSIBILITY TO PROVIDE PROPER SUPERINTENDENCE: The successful low bidder shall designate in writing to the Engineer the name of its authorized superintendent (Superintendent), who will be present at the job site whenever any work is in progress. The Superintendent shall be responsible for all work, receiving and implementing instructions from the Engineer in a timely manner. The cost for superintendence shall be considered incidental to the project.
If the Superintendent is not present at the site of work, the Engineer shall have the right to suspend the work as described under sub-section 5.5 c. and 7.20 - Suspension of Work of the
General Conditions.
U. LIQUIDATED DAMAGES: Liquidated damages in the amount specified in the Proposal will be assessed for each and every calendar day from and after the expiration of the time period stated in the Contract for the completion of the project.
V. HIRING OF HAWAII RESIDENTS: The Contractor shall comply with Act 68, SLH 2010, in the performance and for the duration of this contract. The Contractor shall ensure that
Hawaii residents compose not less than eighty percent of the workforce employed to perform the contract work on the project. The eighty percent requirement shall be determined by dividing the total number of hours worked on the contract by Hawaii residents, by the total number of hours worked on the contract by all employees of the Contractor in the performance of the contract. The hours worked by any Subcontractor of the Contractor shall count towards the calculation for this section. The hours worked by employees with shortage trades, as determined by the Department of Labor and Industrial Relations (DLIR), shall not be included in the calculation for this section.
The requirements shall apply to any subcontract of $50,000 or more in connection with the
Contractor, that is, such Subcontractors must also ensure that Hawaii residents compose not less than eighty percent of the Subcontractor’s workforce used to perform the subcontract.
W. WATER AND ELECTRICITY: The Contractor shall make all necessary arrangements and pay all expenses for water and electricity used in the construction of this project.
X. PUBLIC CONVENIENCE AND SAFETY: The Contractor shall conduct construction operations with due regard to the convenience and safety of the public at all times. No materials or equipment shall be stored where it will interfere with the safe passage of public
I-6 traffic. The Contractor shall provide, install, and maintain in satisfactory condition, all necessary signs, flares and other protective facilities and shall take all necessary precautions for the protection of the work and the convenience and safety of the public. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section
7.20 - Suspension of Work of the General Conditions.
Y. WORK TO BE DONE WITHOUT DIRECT PAYMENT: Whenever the contract that the
Contractor is to perform work or furnish materials of any kind for which no price is fixed in the contract, it shall be understood that the Contractor shall perform such work or furnish said materials without extra charge or allowance or direct payment of any sort. The cost of performing such work or furnishing said material is to be included by the Contractor in a unit price for the appropriate item unless it is expressly specified that such work or material is to be paid for as extra work.
Z. AS-BUILT DRAWINGS: As-built drawings, the intent of which is to record the actual in-place construction so that any future renovations or tie-ins can be anticipated accurately, shall be required. All authorizations given by the Engineer to deviate from the plans shall be drawn on the job site plans. All deviations from alignments, elevations and dimensions which are stipulated on the plans shall be recorded on the as-built drawings. Final as-built drawings shall be submitted to the Engineer for review and approval. After the Engineer approves the as-built drawings, the contractor shall submit an electronic copy in Adobe PDF format on CD ROM.
AA. ASBESTOS CONTAINING MATERIALS: The use of asbestos containing materials or equipment is prohibited. The Contractor shall insure that all materials and equipment incorporated in the project are asbestos-free
BB. WORKER SAFETY: The Contractor shall provide, install and maintain in satisfactory condition all necessary protective facilities and shall take all necessary precautions for the protection and safety of its workers in accordance with the Occupational Safety and Health
Standards for the State of Hawaii. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section 7.20 - Suspension of Work of the
General Conditions.
CC. TOILET FACILITIES: All toilet facilities constructed at the project site shall be in accordance with the Public Health Regulations of the State Department of Health (DOH).
All necessary precautions shall be observed at the project site. The use of sanitary facilities shall be strictly enforced and workers violating these provisions shall be promptly discharged.
DD. SIGNS: Whenever the project involves closing or obstructing any public thoroughfare, the
Contractor shall provide traffic signs conforming to the applicable provisions of the current edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", published by the Federal Highway Administration as directed by the Engineer for the purpose of diverting or warning traffic prior to the construction area. All traffic signs shall bear proper wording stating thereon the necessary information as to diverting or warning traffic.
When indicated in the Proposal, the Contractor shall provide a project sign, size 4'-0" x 7'-0" to be placed as directed by the Engineer. The sign shall be constructed in accordance with
I-7
Section 01581 - Project Sign of these specifications and approved by the Engineer. All wording, type and size of lettering and color selection shall be as specified in these specifications or as approved by the Engineer.
All signs shall be kept neat and clean, and properly erected at all times.
EE. FIELD OFFICE AREA FOR DEPARTMENT: When indicated in the Proposal, the
Contractor shall provide a housed working area of at least 100 square feet adjacent to the
Contractor's office for the Department's use. This area will be used by the Engineer to perform tests and to store equipment. As a minimum, the field office shall include the following: standard sized office desk and chair, lighting, ventilation, window-type air conditioning rated at 5,000 BTU, door and window with locking hardware, electrical outlets, and working communications facilities (a cellular telephone is acceptable). The Department will pay for all long distance toll charges made by the Engineer.
FF. QUANTITIES: All bids will be compared on the basis of quantities of work to be done as shown in the Proposal; the quantities shown in the Unit Price items are estimated, being given as a basis for comparison of bids. The Board reserves the right to increase or decrease the quantities given under the items or delete items entirely as may be required during the progress of the work.
GG. OTHER HEALTH MEASURES: Forms of work site exposure or conditions which may be detrimental to the health or welfare of workers or of the general public shall be eliminated or reduced to safe levels as required by the DOH codes, standards, and regulations. Suitable first aid kits and a person qualified to render first aid, as specified in the DOH regulations, shall be provided at all times when work is scheduled.
HH. HAWAII BUSINESS OR COMPLIANT NON-HAWAII BUSINESS REQUIREMENT:
Bidders (Contractors) shall be incorporated or organized under the laws of the State or be registered to do business in the State as a separate branch or division that is capable of fully performing under the contract, as stipulated in §3-122-112 HAR.
II. COMPLIANCE WITH §3-122-112 HAR:
As a condition for award of the contract and as proof of compliance with the requirements of
103D-310(c) HRS, the apparent low bidder shall furnish the required documents to the
Department. If the valid required certificates are not submitted on a timely basis for award of a contract, a bidder otherwise responsive and responsible may not receive the award. Bidder is responsible to apply for and submit the following documents to the Department.
A. TAX CLEARANCE REQUIREMENTS (HRS Chapter 237): Bidder shall obtain a tax clearance certificate from the Hawaii State Department of Taxation (DOTAX) and the Internal Revenue Service (IRS). The certificate is valid for six months from the most recently approved stamp date on the certificate; the certificate must be valid on the date received by the Department.
B. Department of Labor (DLIR) “Certificate of Compliance”. (HRS Chapter 383 -
Unemployment Insurance, Chapter 386 - Workers’ Compensation, Chapter 392 -
Temporary Disability Insurance, and 393 – Prepaid Health Care): Bidder shall obtain
I-8 a certificate of compliance from the Hawaii State Department of Labor and Industrial relations (DLIR). The certificate is valid for six months from the date of issue;
certificates must be valid on the date received by the Department.
C. Department of Commerce and Consumer Affairs (DCCA), Business Registration
Division (BREG) “Certificate of Good Standing”. Bidder shall obtain a certificate of good standing issued by the Department of Commerce and Consumer Affairs
(DCCA), Business Registration Division (BREG). The certificate of good standing is valid for six months from the date of issue; certificates must be valid on the date received by the Department.
Alternately, instead of separately applying for these certificates at the various state agencies, bidder may choose to use the Hawaii Compliance Express (HCE), which allows businesses to register online through a simple wizard interface at http://vendors.ehawaii.gov to acquire a
“Certificate of Vendor Compliance” indicating the bidder’s status is compliant with the requirements of §103D-310(c), HRS, and shall be accepted for contracting and final payment purposes. Bidders that elect to use the new HCE services will be required to pay an annual fee of $12.00 to the Hawaii Information Consortium, LLC (HIC). Bidders choosing not to participate in the HCE program will be required to provide the paper certificates as instructed in the previous paragraphs.
http://vendors.ehawaii.gov/