02 - 630A4-22-700 Spec Section 01 31 00.01.pdf

PDF 121 KB Posted

Attached to
Y1BG--Brooklyn EHRM Infrastructure Upgrades Construction VA Medical Center Brooklyn, NY 630A4-22-700
Solicitation number
36C77626B0002
Issued by

About this file

This document is a Project Management and Coordination specification section for the EHRM Infrastructure Upgrades Project at the Brooklyn VA Medical Center. The specification requires a web-based project management software package (such as Procore or Oracle Primavera Submittal Exchange) to be used throughout the project for managing communications, documentation, and workflow processes. The software must include features like project data compilation, access control, document workflow planning, tracking of RFIs and submittals, real-time communication status tracking, PDF markup capabilities, payment application processing, meeting minute distribution, document management, and mobile device compatibility.

The contractor must provide user licenses for the Owner, Architect, and Architect's consultants, and provide eight hours of software training. At project completion, a digital archive must be delivered in a readable format acceptable to the Architect, with data locked to prevent further changes. The project number is 630A4-22-700, with a publication date of 2024-05, and is located at the Brooklyn VA Medical Center in Brooklyn, NY. The specification applies to coordinating construction operations and requires all contractors to participate in coordination requirements.

View the file

Other files

File Type Posted
36C77626B0002 0010.pdf PDF
0010 - 630A4-22-700 Responses to Tech Questions - 4-6-26.pdf PDF
0009 - 630A4-22-700 Brand Name Justification.pdf PDF
36C77626B0002 0009.pdf PDF
0009 - 630A4-22-700 Responses to Tech Questions - 4-2-26.pdf PDF
36C77626B0002 0008.pdf PDF
36C77626B0002 0007.pdf PDF
36C77626B0002 0006.pdf PDF
36C77626B0002 0005.pdf PDF
0005 - 630A4-22-700 Responses to Tech Questions - 3-3-26.pdf PDF
36C77626B0002 0004.pdf PDF
0003 - 630A4-22-700 Responses to Tech Questions - 2-24-26.pdf PDF
36C77626B0002 0003.pdf PDF
0003 - 630A4-22-700 Change Summary and Spec 01 32 16.15.pdf PDF
0002 - 630A4-22-700 Site Visit Sign-in Sheet - 2-3-26.pdf PDF
36C77626B0002 0002.pdf PDF
0002 - 630A4-22-700 DBA Wages - Kings County - 01-30-2026.pdf PDF
36C77626B0002 0001.pdf PDF
IFB 36C77626B0002 - 1-15-26.pdf PDF
07 - 630A4-22-700 Appx D-Asbestos Inspection Report.pdf PDF
08 - 630A4-22-700 Appx E-XRF Lead Report.pdf PDF
10 - 630A4-22-700 DWGS 1-CIVIL.pdf PDF
12 - 630A4-22-700 DWGS 3-ARCH.pdf PDF
15 - 630A4-22-700 DWGS 6-ELEC 1 of 2.pdf PDF
18 - 630A4-22-700 DWGS 7-TELECOM 2 of 2.pdf PDF
19 - 630A4-22-700 PCRA.pdf PDF
20 - 630A4-22-700 ICRA.pdf PDF
01 - 630A4-22-700 SPECS-R2-251030.pdf PDF
03 - 630A4-22-700 Appx A-CFD Analysis.pdf PDF
04 - 630A4-22-700 Appx B-Utilities Locate Survey.pdf PDF
05 - 630A4-22-700 Appx C-Topo Survey 1 of 2.pdf PDF
09 - 630A4-22-700 DWGS 0-GENERAL.pdf PDF
11 - 630A4-22-700 DWGS 2-STRUCT.pdf PDF
21 - 630A4-22-700 DBA Wages - Kings County - 01-02-2026.pdf PDF
22 - 630A4-22-700 VAAR 852.219-75 LOS - Construction.pdf PDF
13 - 630A4-22-700 DWGS 4-ENVIRO.pdf PDF
14 - 630A4-22-700 DWGS 5-MECH.pdf PDF
16 - 630A4-22-700 DWGS 6-ELEC 2 of 2.pdf PDF
06 - 630A4-22-700 Appx C-Topo Survey 2 of 2.pdf PDF
17 - 630A4-22-700 DWGS 7-TELECOM 1 of 2.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EHRM INFRASTRUCTURE UPGRADES PROJECT#: 630A4-22-700

BROOKLYN VA MEDICAL CENTER – BROOKLYN, NY PUB. DATE: 2024-05

PROJECT MANAGEMENT AND COORDINATION 01 31 00.01 – 1

SECTION 01 31 00.01

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provision for coordinating construction operations on

Project, including, but not limited to, the following:

1. Web-based Project management software package.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

1.3 DEFINITIONS

A. BIM: Building Information Modeling.

B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Web-Based Project Management Software Package: Provide, administer, and use web-based Project management software package for purposes of hosting and managing

Project communication and documentation until Final Completion.

1. Basis of Specification: Procore, Oracle Primavera Submittal Exchange, or other equivalent web-based project management software.

2. Web-based Project management software includes, at a minimum, the following features:

a. Compilation of Project data, including Contractor, subcontractors, Architect, Architect's consultants, Owner, and other entities involved in

Project. Include names of individuals and contact information.

b. Access control for each entity for each workflow process, to determine

EHRM INFRASTRUCTURE UPGRADES PROJECT#: 630A4-22-700

BROOKLYN VA MEDICAL CENTER – BROOKLYN, NY PUB. DATE: 2024-05

PROJECT MANAGEMENT AND COORDINATION 01 31 00.01 – 2

entity's digital rights to create, modify, view, and print documents.

c. Document workflow planning, allowing customization of workflow between project entities.

d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor Changes in the Work, Construction Change Directives, and Change

Orders.

e. Track status of each Project communication in real time, and log time and date when responses are provided.

f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.

g. Processing and tracking of payment applications.

h. Processing and tracking of contract modifications.

i. Creating and distributing meeting minutes.

j. Document management for Drawings, Specifications, and coordination drawings, including revision control.

k. Management of construction progress photographs.

l. Mobile device compatibility, including smartphones and tablets.

3. Provide Project management software user licenses for use of Owner, Architect, and Architect's consultants. Provide eight hours of software training for web-based Project software users.

4. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Architect. Provide data in locked format to prevent further changes.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

- - - END - - -