VTANG Replace B-120 Chiller

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W50S9C-22-B-0004
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
South Burlington, Vermont 05403, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks a construction contractor to replace an existing 81-ton roof-mounted chiller on Building 120 at the Vermont Army National Guard facility in South Burlington, Vermont. The selected contractor will remove the existing chiller and install a new ground-mounted chiller system, along with all associated electrical, mechanical, and plumbing work. The contractor must provide a sequenced work plan with new chiller installation, a maximum two-week transfer period to the new system, and demolition of the existing chiller. The solicitation was issued by the Department of the Army with responses due by August 11, 2022.

The opportunity is set aside for total small businesses. The NAICS code is 238210 and PSC code R499 covers the replacement of the chiller. The possible award value ranges from $500,000 to $1 million for a one-year period of performance to complete the project. Two bids were received in response to the solicitation. The selected contractor will perform all work at the Vermont Army National Guard facility located at South Burlington, Vermont 05403.

Notice text

5 versions

Update #5 · Latest ·

This project includes replacement of the existing 81-ton, roof-mounted Chiller on Building 120 with a ground-mounted Chiller, including all electrical/mechanical/plumbing piping, controls and wiring required for a complete system as indicated in project drawings and specifications.

This project will include sitework to modify the flightline fence to maintain security between construction area and the flightline. The proposed work will require a sequenced work flow with new chiller construction first, a maximum of 2 week transfer of existing to new, and finally demolition/removal of the existing chiller afterwards.

Included in this work, as detailed in the specifications and drawings, is the preparation and delivery of any redline/ markup drawings by the construction contractor to be submitted to the government. Operation and Maintenance manuals will also be provided to the government by the construction contractor.

****

27 Jul 22 - Following Documents Added

Pre-Bid and Site Visit Attendance - Replace B-120 Chiller

W50S9C-22-B-0004 Replace B-120 Chiller Pre-Bid Slides

****

2 Aug 22 - Following Documents Added

Q and A as of 2Aug22 W50S9C22B0004

WALL TYPES-BI ADD_072922

****

3 Aug 22 - Following Document Added

Q and A as of 3Aug22 W50S9C22B0004

****

9 Aug 22 - Following Document Added

Amendment 0001 Incorporating Question & Answers into Solicitation

****

11 Aug 22 - Following Documents Added

Bid Abstract W50S9C-22-B-0004 Replace B-120 Chiller

Bid Attendance Sheet  W50S9C-22-B-0004 Replace B-120 Chiller

****

Update #4 ·

This project includes replacement of the existing 81-ton, roof-mounted Chiller on Building 120 with a ground-mounted Chiller, including all electrical/mechanical/plumbing piping, controls and wiring required for a complete system as indicated in project drawings and specifications.

This project will include sitework to modify the flightline fence to maintain security between construction area and the flightline. The proposed work will require a sequenced work flow with new chiller construction first, a maximum of 2 week transfer of existing to new, and finally demolition/removal of the existing chiller afterwards.

Included in this work, as detailed in the specifications and drawings, is the preparation and delivery of any redline/ markup drawings by the construction contractor to be submitted to the government. Operation and Maintenance manuals will also be provided to the government by the construction contractor.

****

27 Jul 22 - Following Documents Added

Pre-Bid and Site Visit Attendance - Replace B-120 Chiller

W50S9C-22-B-0004 Replace B-120 Chiller Pre-Bid Slides

****

2 Aug 22 - Following Documents Added

Q and A as of 2Aug22 W50S9C22B0004

WALL TYPES-BI ADD_072922

****

3 Aug 22 - Following Document Added

Q and A as of 3Aug22 W50S9C22B0004

****

9 Aug 22 - Following Document Added

Amendment 0001 Incorporating Question & Answers into Solicitation

****

Update #3 ·

This project includes replacement of the existing 81-ton, roof-mounted Chiller on Building 120 with a ground-mounted Chiller, including all electrical/mechanical/plumbing piping, controls and wiring required for a complete system as indicated in project drawings and specifications.

This project will include sitework to modify the flightline fence to maintain security between construction area and the flightline. The proposed work will require a sequenced work flow with new chiller construction first, a maximum of 2 week transfer of existing to new, and finally demolition/removal of the existing chiller afterwards.

Included in this work, as detailed in the specifications and drawings, is the preparation and delivery of any redline/ markup drawings by the construction contractor to be submitted to the government. Operation and Maintenance manuals will also be provided to the government by the construction contractor.

****

27 Jul 22 - Following Documents Added

Pre-Bid and Site Visit Attendance - Replace B-120 Chiller

W50S9C-22-B-0004 Replace B-120 Chiller Pre-Bid Slides

****

2 Aug 22 - Following Documents Added

Q and A as of 2Aug22 W50S9C22B0004

WALL TYPES-BI ADD_072922

****

3 Aug 22 - Following Document Added

Q and A as of 3Aug22 W50S9C22B0004

****

Update #2 ·

This project includes replacement of the existing 81-ton, roof-mounted Chiller on Building 120 with a ground-mounted Chiller, including all electrical/mechanical/plumbing piping, controls and wiring required for a complete system as indicated in project drawings and specifications.

This project will include sitework to modify the flightline fence to maintain security between construction area and the flightline. The proposed work will require a sequenced work flow with new chiller construction first, a maximum of 2 week transfer of existing to new, and finally demolition/removal of the existing chiller afterwards.

Included in this work, as detailed in the specifications and drawings, is the preparation and delivery of any redline/ markup drawings by the construction contractor to be submitted to the government. Operation and Maintenance manuals will also be provided to the government by the construction contractor.

****

27 Jul 22 - Following Documents Added

Pre-Bid and Site Visit Attendance - Replace B-120 Chiller

W50S9C-22-B-0004 Replace B-120 Chiller Pre-Bid Slides

****

2 Aug 22 - Following Documents Added

Q and A as of 2Aug22 W50S9C22B0004

WALL TYPES-BI ADD_072922

****

Update #1 ·

This project includes replacement of the existing 81-ton, roof-mounted Chiller on Building 120 with a ground-mounted Chiller, including all electrical/mechanical/plumbing piping, controls and wiring required for a complete system as indicated in project drawings and specifications.

This project will include sitework to modify the flightline fence to maintain security between construction area and the flightline. The proposed work will require a sequenced work flow with new chiller construction first, a maximum of 2 week transfer of existing to new, and finally demolition/removal of the existing chiller afterwards.

Included in this work, as detailed in the specifications and drawings, is the preparation and delivery of any redline/ markup drawings by the construction contractor to be submitted to the government. Operation and Maintenance manuals will also be provided to the government by the construction contractor.

Files

Show all 11

Notice history

Notice Type Posted
VTANG Replace B-120 Chiller Award Award Notice
This notice Latest solicitation Solicitation
VTANG Replace B-120 Chiller Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
C221--402-27-001 Repair Chiller 3 (AE) Veterans Affairs Medical Center Augusta ME 04330, United States · NAICS 541330 Veterans Integrated Service Network 1 Service-Disabled Veteran-Owned Small Business
Rental of two chillers for one year Asheville, North Carolina 28805, United States · NAICS 238220 Veterans Integrated Service Network 6 Service-Disabled Veteran-Owned Small Business
CON | Z2DA | replace chiller 1 B104 | 580-24-111 | solicitation Houston, Texas 77030, United States · NAICS 238220 Veterans Integrated Service Network 16 Service-Disabled Veteran-Owned Small Business
Z2NZ--Turn Key Chiller Equipment (Purchase and Install) NAICS 238220 Veterans Integrated Service Network 16 No set-aside
CON | Z1DA | replace or chillers | 580-23-105 | solicitation Houston, Texas 77030, United States · NAICS 238220 Veterans Integrated Service Network 16 Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors