USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9123822R0006
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Hill AFB, Utah 84056, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks two-phase design-build construction services to upgrade three boilers and complete seismic retrofitting at Building 1286 on Hill Air Force Base in Utah. The U.S. Army Corps of Engineers Sacramento District will replace the existing boilers with new dual-fuel boilers capable of achieving ultra-low NOx emissions of 9 parts per million. Offerors must propose to design and construct the upgrades, including replacing underground fuel oil storage tanks with aboveground tanks sized for seven days of peak storage, by the response deadline of August 1, 2022. Price and technical factors will be considered in selecting the best value proposal for award anticipated in September 2022.

The requirement is set aside for total small business concerns. The NAICS code is 237110 with a PSC code of W912. The estimated value ranges from $10-25 million for construction to be completed within 910 calendar days at Hill Air Force Base in Utah. Interested vendors must check the System for Award Management website for the interested vendors list, plans, specifications and any amendments to the solicitation.

Notice text

10 versions

Update #10 · Latest ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

____________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicitation proposal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0004 - Add feasibility study Attachment 13, and extend the solicitation proposal due date from 1:00 PM PST, 15 July 2022 to 9:00  PM PST 25 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0005 - Update sections, 00 21 00; 00 22 00; 00 73 00 and incorporate Government Furnished Property (GFP) provisions and clauses.  

________________________________________________________________________________________________________

SAM Posting Amendment 0006 - Incorporates revised V1 Specifications dated 20220719 and V2 Appendices dated 20220719; Adds FAR 52.236-14-Availability and Use of Utility Services; Updates drawing E-603; Changes PoP from 730 days to 910 days; Extends solicitation closing date from 0900 PST, 25 July 2022 to 0900 PST, 01 August 2022; Updates GFP Generator Information.

________________________________________________________________________________________________________

SAM Posting Amendment 0007 - Incorporates revised Specifications Volume 1 to correct availabile utilty information and updates CLIN 0002 period of perforamnce to match other contract line items. 

Update #9 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

____________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicitation proposal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0004 - Add feasibility study Attachment 13, and extend the solicitation proposal due date from 1:00 PM PST, 15 July 2022 to 9:00  PM PST 25 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0005 - Update sections, 00 21 00; 00 22 00; 00 73 00 and incorporate Government Furnished Property (GFP) provisions and clauses.  

________________________________________________________________________________________________________

SAM Posting Amendment 0006 - The purpose of this amendment is to: Incorporate revised V1 Specifications dated 20220719 and V2 Appendices dated 20220719; Add FAR 52.236-14-Availability and Use of Utility Services; Update drawing E-603; Change PoP from 730 days to 910 days; Extend solicitation closing date from 0900 PST, 25 July 2022 to 0900 PST, 01 August 2022; Update GFP Generator Information.

Update #8 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

____________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicitation proposal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0004 - Add feasibility study Attachment 13, and extend the solicitation proposal due date from 1:00 PM PST, 15 July 2022 to 9:00  PM PST 25 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0005 - Update sections, 00 21 00; 00 22 00; 00 73 00 and incorporate Government Furnished Property (GFP) provisions and clauses.  

Update #7 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicition propsal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0004 - Add feasiblity study Attachement 13, and extend the solicition propsal due date from 1:00 PM PST, 15 July 2022 to 9:00  PM PST 25 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0005 - Update sections, 00 21 00; 00 22 00; 00 73 00 and incorperate Government Furnished Property (GFP) provisions and clauses.  

Update #6 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicition propsal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

________________________________________________________________________________________________________

SAM Posting Amendment 0004 - Add feasiblity study Attachement 13, and extend the solicition propsal due date from 1:00 PM PST, 15 July 2022 to 9:00  PM PST 25 July 2022.

Update #5 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Sam Posting - Upload the site visit sign-in sheet and site visit agenda. 

________________________________________________________________________________________________________

SAM Posting Amendment 0003 - Extend the solicition propsal due date from 1:00 PM PST,  27 June 2022 to 1:00 PM PST 15 July 2022.

Update #4 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

________________________________________________________________________________________________________Updated Sam Posting - The puropose of the this updated posting is to upload the site visit sign-in sheet and site visit agenda. 

Update #3 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

________________________________________________________________________________________________________

SAM Posting Amendment 0002 - Establish Phase II proposal date and time submission;  Update sections 00 21 00 and  00 22 00; issue updated attachments for Phase II; reopen Projnet; require bid guarantee for phase II proposals; add site visit information; revise line item structure.  

Update #2 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.

________________________________________________________________________________________________________

SAM Posting Amendment 0001 - Changes NAICS code from 238220 to 236220; Update sections 00 21 00 and  00 22 00.  

Update #1 ·

The U.S. Army Corps of Engineers (USACE) Sacramento District (SPK) has a new requirement to complete two-phase design-build construction services to upgrade the Steam Plant at B1286 on Hill AFB, UT.

This project will include the replacement of three (3) existing boilers in B1286 with new dualfuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. 

The boilers in B1286 will be replaced with two (2) new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. The Contractor shall develop and complete the designs and construct the facility. The Contractor will be given a "buildable area" boundary, to best locate/layout the proposed facility.

The solicitation, plans, and specifications are available for inspection without charge when accessed through the GPE or when requested and delivered by electronic mail and/or data interchange. 

In accordance with DFARS 236.204(i), the magnitude of construction for this requirement is estimated to be between $10,000,000 and $25,000,000

The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov. Contractors are responsible for self-identifying as interested vendors and contacting other interested vendors. USACE-SPK will not review capabilities statements submitted in response to this solicitation or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and the solicitation. 

PLEASE NOTE: THIS PROJECT AND/OR THE PROPOSED CONTRACT ACTION MAY BE CHANGED, DELAYED, OR CANCELED AT ANY TIME.
 

Files

File Type Posted
B08 W9123822R0006 Attachment 01 - HAFB B1286 Specifications Volume 1 - 20220726.pdf PDF
B08 W9123822R0006-0007 HAFB B1286 Steam Plant - 20220727.pdf PDF
B08 W9123822R00060006 Attachment 02 HAFB B1286 Specifications Volume 2 Appendices - 20220719.pdf PDF
B08 W9123822R0006-0006 - 20220721.pdf PDF
B08 W9123822R00060006 Attachment 01 HAFB B1286 Specifications Volume 1 - 20220719.pdf PDF
B08 W9123822R0006-0005 - 20220715.pdf PDF
B08 W9123822R0006-0004 - 20220714.pdf PDF
B08 W9123822R0006 Attachment 13 Appendix K_Hill AFB-Rpair Boilers-Final Feasability Report.pdf PDF
B08 W9123822R0006 Attachment 06 Past Performance Questionaire 20220122.pdf PDF
B08 W9123822R0006 Attachment 05 Pre Award Survey Dated 20 January 2022.pdf PDF
B08 W9123822R0006 Amendment 0003 BLDG1286 Steam Plant Upgrades.pdf PDF
B07 W9123822R0006 Site Visit Sign In Sheet.pdf PDF
B08 - W9123822R00060002 - 20220527.pdf PDF
B08 W9123822R0006 Attachment 03 HAFB B1286 Steam Plant Specifications Vol 2 - 20220318.pdf PDF
B08 W9123822R0006 Attachment 06 Pre-Award Survey - 20220122.pdf PDF
B08 W9123822R0006 Attachment 07 CWRR UT20220083 - 20220401.pdf PDF
B08 W9123822R0006 Attachment 11 Price Schedule - 20220527.pdf PDF
B08 W9123822R0006 Attachment 01 HAFB B1286 Steam Plant Plans - 20220318.pdf PDF
B08 W9123822R0006 Attachment 4 Contractors Project Experience Dated 28 January 2022.pdf PDF
B08 W9123822R0006 Attachment 05 Pre-Award Survey Dated 20 January 2022.pdf PDF
B08 W9123822R0006 Attachment 08 B1286 KRSM Drawings Part 1 pages 1 - 25 - 19840816.pdf PDF
B08 W9123822R0006 Attachment 10 B1286 Existing UST Drawings - 19921101.pdf PDF
B08 W9123822R0006 Attachment 02 HAFB B1286 Steam Plant Specifications Vol 1 - 20220318.pdf PDF
B08 W9123822R0006 Attachment 08 B1286 KRSM Drawings Part 2 pages 26-50 - 19840816.pdf PDF
B08 W9123822R0006 Attachment 09 B1286 KRSM Drawings pages 51 - 102 - 19660203.pdf PDF
B08 W9123822R0006 Attachment 12 Site Visit Map.pdf PDF
B08 W9123822R0006-0001 B1286 Steam Plant - 20220328.pdf PDF
B08 W9123822R0006 Attachment 6 Pre-Award Survey Dated 20 January 2022.pdf PDF
B08 W9123822R0006 Attachment 5 HAFB B1286 Concept Drawing Set.pdf PDF
B08 W9213822R0006 Attachement 2 CWRR UT 20220083 02252022.pdf PDF
B08 W9123822R0006 Attachment 4 Contractors Project Experience Dated 28 January 2022.pdf PDF
B08 - W9123822R0006 HAFB B1286 Steam Plant Upgrades - 20220302.pdf PDF
B08 W9123822R0006 Attachment 1 Summary of Work dated 21 November 2021.pdf PDF
B08 W9123822R0006 Attachment 3 Past Performance Questionnaire Dated 28 January 2022.pdf PDF
Show all 34

Notice history

Notice Type Posted
USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT Award Award Notice
This notice Latest solicitation Solicitation
USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
16292 Steam Boiler Replacement Hill AFB, Utah 84056, United States · NAICS 238220 Air Force Sustainment Center Total Small Business
F-35 Composite Repair and Training Facility / F-35 Maintenance Facility, Hill Air Force Base, Utah Hill Air Force Base, Utah, United States · NAICS 236210 ENDIST Sacramento No set-aside
HAFB Multiple Award Construction Contract V (MACC V) Hill AFB, UT (Davis County) Utah Test and Training Range (Uttr) Little Mountain Test Facility (Lmtf) Utah Air National Guard (Utang) Base Boulder Seismic Site, WY Other: Geographically separated units (GSU) under the responsibility of 75 ABW/CC · NAICS 236220 Air Force Sustainment Center Total Small Business
Renovate Building 1203-DOAS/AHU and Fire Suppression Water System, March Air Reserve Base, California California 92518, United States · NAICS 236220 ENDIST Louisville Total Small Business
Renovate Building 1203-DOAS/AHU and Fire Suppression Water System, March Air Reserve Base, California 1250 Graeber St Building 1203March Air Reserve Base, CA 92518 · NAICS 236220 ENDIST Louisville Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors