B08 W9123822R0006 Attachment 1 Summary of Work dated 21 November 2021.pdf

PDF 66 KB Posted

Attached to
USACE SPK DB Construction - Building 1286 Steam Plant Upgrades at Hill AFB, UT
Solicitation number
W9123822R0006
Issued by

About this file

This document outlines requirements for a design-build construction contract opportunity with the U.S. Army Corps of Engineers Sacramento District to upgrade the steam plant at Building 1286 on Hill Air Force Base in Utah. The project scope includes replacing three existing boilers with two new dual-fuel boilers meeting best available control technology requirements, with emissions of nine parts per million of oxides of nitrogen. Additional work comprises replacing underground fuel oil storage tanks with above-ground tanks sized for seven days of peak storage, seismic retrofitting of buildings, and upgrading supporting equipment. Interested vendors must check SAM.gov for the list of interested vendors and changes to the solicitation. The magnitude of construction is estimated between $10 million to $25 million. The contractor will be selected through a two-phase solicitation to first develop designs and then perform construction.

View the file

Other files

File Type Posted
B08 W9123822R0006 Attachment 01 - HAFB B1286 Specifications Volume 1 - 20220726.pdf PDF
B08 W9123822R0006-0007 HAFB B1286 Steam Plant - 20220727.pdf PDF
B08 W9123822R00060006 Attachment 02 HAFB B1286 Specifications Volume 2 Appendices - 20220719.pdf PDF
B08 W9123822R00060006 Attachment 01 HAFB B1286 Specifications Volume 1 - 20220719.pdf PDF
B08 W9123822R0006-0006 - 20220721.pdf PDF
B08 W9123822R0006-0005 - 20220715.pdf PDF
B08 W9123822R0006-0004 - 20220714.pdf PDF
B08 W9123822R0006 Attachment 13 Appendix K_Hill AFB-Rpair Boilers-Final Feasability Report.pdf PDF
B08 W9123822R0006 Amendment 0003 BLDG1286 Steam Plant Upgrades.pdf PDF
B08 W9123822R0006 Attachment 06 Past Performance Questionaire 20220122.pdf PDF
B08 W9123822R0006 Attachment 05 Pre Award Survey Dated 20 January 2022.pdf PDF
B07 W9123822R0006 Site Visit Sign In Sheet.pdf PDF
B08 W9123822R0006 Attachment 06 Pre-Award Survey - 20220122.pdf PDF
B08 W9123822R0006 Attachment 4 Contractors Project Experience Dated 28 January 2022.pdf PDF
B08 W9123822R0006 Attachment 08 B1286 KRSM Drawings Part 2 pages 26-50 - 19840816.pdf PDF
B08 W9123822R0006 Attachment 11 Price Schedule - 20220527.pdf PDF
B08 - W9123822R00060002 - 20220527.pdf PDF
B08 W9123822R0006 Attachment 12 Site Visit Map.pdf PDF
B08 W9123822R0006 Attachment 02 HAFB B1286 Steam Plant Specifications Vol 1 - 20220318.pdf PDF
B08 W9123822R0006 Attachment 05 Pre-Award Survey Dated 20 January 2022.pdf PDF
B08 W9123822R0006 Attachment 07 CWRR UT20220083 - 20220401.pdf PDF
B08 W9123822R0006 Attachment 03 HAFB B1286 Steam Plant Specifications Vol 2 - 20220318.pdf PDF
B08 W9123822R0006 Attachment 01 HAFB B1286 Steam Plant Plans - 20220318.pdf PDF
B08 W9123822R0006 Attachment 09 B1286 KRSM Drawings pages 51 - 102 - 19660203.pdf PDF
B08 W9123822R0006 Attachment 10 B1286 Existing UST Drawings - 19921101.pdf PDF
B08 W9123822R0006 Attachment 08 B1286 KRSM Drawings Part 1 pages 1 - 25 - 19840816.pdf PDF
B08 W9123822R0006 Attachment 5 HAFB B1286 Concept Drawing Set.pdf PDF
B08 W9123822R0006-0001 B1286 Steam Plant - 20220328.pdf PDF
B08 W9123822R0006 Attachment 6 Pre-Award Survey Dated 20 January 2022.pdf PDF
B08 W9123822R0006 Attachment 4 Contractors Project Experience Dated 28 January 2022.pdf PDF
B08 - W9123822R0006 HAFB B1286 Steam Plant Upgrades - 20220302.pdf PDF
B08 W9213822R0006 Attachement 2 CWRR UT 20220083 02252022.pdf PDF
B08 W9123822R0006 Attachment 3 Past Performance Questionnaire Dated 28 January 2022.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 22 November 2021

Summary of Work

BUILDING 1286 STEAM PLANT BOILER UPGRADES

HILL AIR FORCE BASE (HAFB), UTAH (UT)

1. Scope of Work

The Government anticipates a requirement to improve and repair steam plant boilers in Building

1286 (B1286) at HAFB. This project will include the replacement of three (3) boilers in B1286 with two (2) new dual-fuel (natural gas/fuel oil) boilers that meet best available control technology (BACT), which requires phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants. The new boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of nine (9) parts per million

(ppm).

2. Description

The Contractor shall furnish and install all labor, materials, tools, equipment, and supervision necessary to provide a complete and usable project per the Specific Technical Engineering and

Design Criteria, Functional Design Criteria Requirements, including all attachments, Base

Facility Design Standard, Architectural Compatibility Guide and requirements specified in the contract.

This project will include the replacement of three (3) boilers in B1286 with two (2) new dual-fuel

(natural gas/fuel oil) boilers that meet best available control technology (BACT)The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) must be removed and replaced with appropriately sized above ground storage tanks that are sized for seven (7) days of storage during peak heating season, approximately December through February.

The building must be seismically retrofitted and have supporting equipment (deaerator, pumps, etc.) upgraded. The undersized emergency generator at B1286 will be replaced to accommodate larger blower motor sizes due to flue gas recirculation (FGR).

This is a design-build contract therefore the Contractor is required to perform design work prior to construction. The Contractor is responsible and liable for the complete design and shall not assume that the provided design criteria and drawings in this solicitation will alleviate him/her from performing any additional design as required to produce a complete set of construction documents.

The Government’s conceptual facility and site design provided in the RFP documents illustrates intent and functional relationships and does not indicate all necessary construction requirements or components. The Specific Technical Engineering and Design Criteria and Functional Design

Criteria Room by Room Requirements describes associated technical, performance and systems requirements. The Contractor is responsible for the complete project design, shall retain all responsibilities, and be recognized as the Designer of Record.

Contractor shall perform work as stated in this Attachment 1- Summary of Work, Attachment 2-

Construction Wage Rate Requirements, Attachment 3 – Past Performance Questionnaire, and

Attachment 4 – Contractor’s Project Experience. Contractor is highly encouraged to attend the

Attachment 1 22 November 2021 pre-proposal site visit and field verify all dimensions and layouts. (Please note: The site visit will be completed as part of phase 2 of this solicitation) The project shall be designed within the criteria prescribed, as well as other codes and standards specified in the contract.

3. General Project Requirements:

Contractor shall follow all security requirements for base access. All Contractor and subcontractor personnel will need to obtain badges for all access on base from the security office.

AT Level I Training: All Contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at http://jko.jten.mil/courses/atl1/launch.html

The Contractor shall be responsible for the coordination of work performed by their employees and all subcontractors. The Contractor should inspect all work areas prior to submitting a proposal in accordance with FAR 52.236-3, Site Investigation and Conditions Affecting the

Work. It shall be the Contractor’s responsibility to verify all current record drawings prior to the start of any and all design and/or construction work. The Contractor shall be responsible for the coordination and proper relationship of this work to the building premises and thoroughly familiarize themselves with all details of the work and working conditions, to verify all dimensions in the field, and advise the Administrative Contracting Officer (ACO) of any discrepancies before performing any work.

The Contractor is responsible for maintaining the site and all other Contractor controlled areas in such a manner as to minimize the risk of injury or accident to site personnel or others who may be in the area. The Contractor is also responsible for furnishing an identification badge/card to each individual working on the site.

4. After Award Administrative Contracting Officer (ACO) and Post Award POC and Work

Coordination:

An Administrative USACE point of contact, ACO, and Contracting Officer Representative will be responsible for verifying that the Contractors’ performance and completion of work is in accordance with applicable requirements.