Repair Interiors 505 TRS and 705 TRS, Bldg 90021
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- FA441720R0015
- Agency
-
Air Force Special Operations Command
Air Force, Department of Defense
- Responses due
- Set-aside
- HUBZone
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Hurlburt Field FL 32544 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals for repair and interior construction work at Building 90021 located at Hurlburt Field, Florida. The Department of the Air Force Special Operations Command requires partial demolition and new construction of first and second floor interior spaces. The selected contractor shall provide new bathrooms, mechanical rooms, classrooms, laboratories, break rooms, offices, and training conference rooms. Proposals will be evaluated based on technical qualifications, past performance, and price. The deadline for proposals is August 11, 2020.
The solicitation is set aside for HUBZone small businesses. The primary NAICS code is 236220 and PSC code S206. The place of performance is Hurlburt Field, Florida. The work includes partial demolition of approximately 5,000 square feet of existing floor slabs and construction of 7,500 square feet of new interior spaces. The period of performance is 380 calendar days from the notice to proceed. A pre-proposal site visit was held on July 14, 2020 and two amendments have extended the closing date and provided revised specifications and drawings.
Notice text
6 versions
Update #6 · Latest ·
* 06 Aug 2020 - Issue attached Amendment 0001 to incorporate Addendum 1, associated updated Specifications, Drawings and revise response to question #60 of site visit questions.
* 03 Aug 2020 - Remaining responses to Site Visit Questions (60-64)attached
* 29 Jul 2020 - Responses to Site Visit questions attached.
* 28 Jul 2020 - Issue attached Amendment 0001 to extend proposal due date to 11 Aug 2020.
* 14 July 2020 - Pre-Bid Site Visit MFR and Sign-In Sheet attached.
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Update #5 ·
* 03 Aug 2020 - Remaining responses to Site Visit Questions (60-64)attached
* 29 Jul 2020 - Responses to Site Visit questions attached.
* 28 Jul 2020 - Issue attached Amendment 0001 to extend proposal due date to 11 Aug 2020.
* 14 July 2020 - Pre-Bid Site Visit MFR and Sign-In Sheet attached.
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Update #4 ·
* 29 Jul 2020 - Responses to Site Visit questions attached.
* 28 Jul 2020 - Issue attached Amendment 0001 to extend proposal due date to 11 Aug 2020.
* 14 July 2020 - Pre-Bid Site Visit MFR and Sign-In Sheet attached.
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Update #3 ·
* 28 Jul 2020 - Issue attached Amendment 0001 to extend proposal due date to 11 Aug 2020.
* 14 July 2020 - Pre-Bid Site Visit MFR and Sign-In Sheet attached.
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Update #2 ·
* 14 July 2020 - Pre-Bid Site Visit MFR and Sign-In Sheet attached.
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Update #1 ·
The work includes the partial demolition and new construction for a 1st and 2nd floor interior build out of existing south end warehouse of building 90021. 1st floor will have partial demolition of the existing warehouse floor slab for both new plumbing and foundation support for the new 2nd floor deck above. 1st floor work includes new bathrooms, mechanical room, classroom, labs and support spaces. 2nd floor demolition includes partial demolition of the existing mezzanine area for tie in of the new 2nd floor slab. 2nd floor new work includes the partial renovation of existing areas within the existing building and new areas allowed by installation of a new floor slab above the existing warehouse area below. The new 2nd floor area will include Breakrooms, Bathrooms, Mechanical Room, Offices, Classrooms and Training Conference Rooms along with other supporting spaces. New work includes a prefabricated metal stairway with precast treads and landings on the south side of the existing building. Demolition for both floors include new penetrations through existing interior and exterior walls.
Files
Show all 16
Notice history
| Notice | Type | Posted |
|---|---|---|
| Repair Interiors 505 TRS and 705 TRS, Bldg 90021 | Award Notice | |
| This notice | Solicitation | |
| Repair Interiors 505 TRS and 705 TRS, Bldg 90021 | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Design-Build Renovation of Building 164, Outdoor Recreation Center, Homestead Air Reserve Base, Florida | Reserve Command | No set-aside | |
| WWYK260004 - repair structural integrity, B1134, post 34 & north wall | Air Force Sustainment Center | Total Small Business | |
| Armed Forces Recruiting Building 25 Tenant Improvement and Renovation Project- Sources Sought Notice | — | No set-aside | |
| WWYK250063 - install react VII facility, B9001, post V19 | Air Force Sustainment Center | Woman-Owned Small Business |