Phase 2 Construct Arabian Leopard Exhibit at the National Zoological Park

Closed Solicitation Posted

Solicitation number
33330226RT0010015
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Washington, District of Columbia 20008, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Smithsonian Institution seeks offers to construct Phase 2, the Habitats & Animal Care Building, of the Arabian Leopard Facility under Solicitation 33330226RT0010015, with bids due November 20, 2026, at 3:00 PM EST. No set-aside is used. The solicitation carries a minimum 40% small business subcontracting goal of planned subcontracting dollars, with no separate SDVOSB or HUBZone subgoals.

Work is performed at the National Zoological Park, 3001 Connecticut Ave NW, Washington, DC 20008, on an occupied, historic campus with active public, staff, and animal presence. Normal work hours are 6:00 AM to 3:30 PM, and weekend or night work requires special approval.

Offerors must be capable of performing all described work and must demonstrate experience coordinating specialty trades in a constrained site footprint. Scope includes specialty animal doors, transfer systems, and manually operated remote door controls; radiant flooring; animal containment fencing, mesh, and transfer chutes; shotcrete faux rock and faux trees; and sound and vibration mitigation so as not to harm animals in adjacent habitats. Construction must align with Zoo operations, including feeding schedules. A 12% self-performance requirement applies with no reduction allowed. Buy American requirements apply with no exceptions, and Davis-Bacon wage determinations apply. Proposals are limited to 250 pages and must not include assumptions or qualifications affecting the firm fixed price.

The contract is a firm fixed-price construction award, with the Smithsonian estimating the total fixed price will exceed $10 million. The period of performance is 578 calendar days from Notice to Proceed through final completion, anticipated September 2028. Funding is $4 million for FY 2027, with additional FY 2028 funding subject to appropriations availability. Micropile unit prices under Specification Section 31 6333 are excluded from the Total Firm Fixed Price and incorporated for authorized change orders.

Amendment 0005 moved the bid due date from November 13 to November 20, 2026, and Amendment 0009, the latest, confirms that deadline. The question period closed September 30, 2026, and the second site visit was scheduled for October 23, 2026. The NAICS code is 236220, Commercial and Institutional Building Construction, and the PSC is Y1JA, Construction of Museums and Exhibition Buildings.

Notice text

10 versions

Update #10 · Latest ·

Amendment 0009 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Response to RFI’s for Question 574

------------------------------------------------------------------------------------------------

Amendment 0008 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 554-573

------------------------------------------------------------------------------------------------

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 553

Updated 100% Final IFM Spec Vol 2

------------------------------------------------------------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 227-552

-------------------------------------------------------------------------------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extension

RFI Due Date

CAD & Revit File

-------------------------------------------------------------------------------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #9 ·

Amendment 0008 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 554-573

------------------------------------------------------------------------------------------------

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 553

Updated 100% Final IFM Spec Vol 2

------------------------------------------------------------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 227-552

-------------------------------------------------------------------------------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extension

RFI Due Date

CAD & Revit File

-------------------------------------------------------------------------------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #8 ·

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 553

Updated 100% Final IFM Spec Vol 2

------------------------------------------------------------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 227-552

-------------------------------------------------------------------------------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extension

RFI Due Date

CAD & Revit File

-------------------------------------------------------------------------------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #7 ·

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 227-552

-------------------------------------------------------------------------------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extension

RFI Due Date

CAD & Revit File

-------------------------------------------------------------------------------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #6 ·

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extension

RFI Due Date

CAD & Revit File

-------------------------------------------------------------------------------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #5 ·

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

100% Bid Documents

Responses to RFI’s for Questions 225-226

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #4 ·

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 53-224

Revised Bid Schedule

2nd Site Visit

-------------------------------------------------------------------------------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #3 ·

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1-52

Revised Bid Schedule

-------------------------------------------------------------------------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #2 ·

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following change to the Solicitation:

Preproposal Meeting Sign-In sheet

-----------------------------------------------------------------------------------------------------------------------

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Update #1 ·

The Smithsonian Institution is seeking offers to construct Phase 2 - Habitats & Animal Care Building for the Arabian Leopard Facility (ALF) at the Smithsonian National Zoological Park, located at 3001 Connecticut Ave NW, Washington, DC 20008, as described herein and the Contract Documents, including, without limitation, in the Specifications and Drawings for SF Project No. 2533105 both dated June 14, 2026.

All of the requirements which the successful Offeror must meet concerning this project are set forth in detail in the solicitation Documents included with this Request for Proposal. Upon the receipt of Technical and Cost Proposals and the selection of a successful Offeror, the Smithsonian Institution will execute a Firm Fixed Price construction contract. The Smithsonian currently estimates that the fixed price for the entire project will exceed $10 Million.

The Work includes but is not limited to Construction Services for Phase 2 – Habitats and Animal Care Building. This solicitation is for Phase 2 – Habitats and Animal Care Building only. Successful offerors must be capable of performing all work described and contemplated by this solicitation.

Critical Elements of the Work: The successful Contractor shall be experienced and fully qualified with critical elements of the project, as listed, but not limited to, the items below:

  1. Working within an occupied, historic campus active with public, staff and animals
  2. Coordination of specialty trades within a small site footprint
  3. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
  4. Coordination and installation of radiant flooring
  5. Coordination and installation of animal containment fencing, mesh and transfer chutes
  6. Coordination and installation of shotcrete faux rock and faux trees
  7. Mitigation of sound and vibration during construction so as not to harm animals in adjacent habitats
  8. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
  9. Procedures and documentation to ensure compliance with the established LEED building criteria
  10. Use of Building Information Modeling (BIM).

The following firms were prequalified in solicitation 33330226FT0010005 and are the only firms from which offers will be accepted:

Grunley

15020 Shady Grove Road, Suite 500

Rockville, MD 20850

Consigli

1825 K Street, Suite 1000

Washington, DC 20006

The Whiting-Turner Contracting Company

4600 River Road, Suite 200

College Park, MD 20737

PRE-BID TOUR OF THE SITE

The Pre-proposal meeting is scheduled for Friday, September 18, 2026, at 9:00 AM Eastern Time.

REQUEST FOR CLARIFICATIONS

Itis requested that all questions be sent in no later than September 30, 2026.

THE PROPOSAL DUE DATE IS FRIDAY, NOVEMBER 13, 2026, AT 3:00 PM EASTERN STANDARD TIME (EST).

The subcontracting goals for this project are: 40% with small business concerns.

Davis Bacon Building Wage Determination DC20260002 and DC20260001 shall apply.

The Period of Performance for the Base Contract is 578 calendar days from the date of Notice to Proceed.

Files

Show all 18

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors