65 DD Specs.pdf
PDF 35 MB Posted
- Solicitation number
- 33330226RT0010015
- Issued by
-
Smithsonian Institution
About this file
Summary
This is a 65% Construction Documents Specification for Phase 2 of the Arabian Leopard Facility (ALF) at the Smithsonian Institution's National Zoological Park in Washington, DC. The project (OPDC Project No. 2533105) consists of constructing habitats and an animal care building to replace the former Bison Habitat and existing Zoo in Your Backyard exhibit. The contract is a firm fixed-price agreement estimated to exceed $10 million, with a total contract time of 578 calendar days beginning within ten days of the Notice to Proceed. The work encompasses comprehensive construction services including structural elements (cast-in-place concrete, masonry, metals, wood framing), building systems (HVAC, plumbing, electrical, fire suppression, communications, and security), interior finishes (gypsum board, ceramic tiling, resinous flooring, painting), specialized animal containment systems (caging, doors, transfer systems, fencing, and mesh structures), landscape improvements, and utility infrastructure. Critical qualifications required include experience working in occupied historic campuses with active public and animal operations, coordinating specialty trades in constrained spaces, installing animal-specific systems, implementing sound and vibration mitigation during construction, and coordinating construction activities with zoo operations and animal welfare protocols.
The specification establishes detailed administrative and operational requirements including a pre-bid conference and site visit, limited site access during restricted hours (6 a.m. to 3:30 p.m. Monday-Friday), coordination with adjacent panda habitats with anticipated stop-work notices for animal welfare, traffic control with certified personnel, comprehensive safety documentation and daily safety inspections, toxic substance approval through Material Safety Data Sheets, personal protective equipment requirements, and behavioral standards for contractor personnel on Smithsonian property. Contractors must submit a Schedule of Values, construction schedule, Job-Site Safety Plan within 30 days of award, Site-Specific Safety Plan, and certified payroll documentation. Applications for Payment are processed monthly by the 25th for work completion percentages through the month end, with stored materials requiring insurance certificates and bonded warehousing documentation. Contract modifications follow established procedures for minor changes via Architect's Supplemental Instructions and proposal-based changes for scope adjustments affecting contract sum or time.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
600 Maryland Avenue, S.W. USPS Mail: OPDC Capital Gallery Suite 5001 MRC 511 Washington, D.C. 20024 P.O. Box 37012 Voice: 202.633.6230 Fax: 202.633.6233 Washington, D.C. 20013-7012
SPECIFICATIONS
PROJECT NO.:
PROJECT TITLE:
FACILITY:
DATE:
This project is approved as being in conformance with applicable provisions of the Smithsonian Directive
(SD) 410.
Michael J. Carrancho, P.E., Deputy Director Date
Smithsonian Institution
Office of Planning, Design & Construction
PROJECT NO.: 2533105
PROJECT TITLE: Construct Arabian Leopard Habitat (ALF) Phase 2 - Habitat & Animal Care Building FACILITY: National Zoological Conservation Biology Institute (NZCBI)
PACKAGE: 65% Construction Documents - FOR REFERENCE ONLY
FOR R
EFERENCE O
NLY
June 15, 2026
Smithsonian OPDC Project No. 2533105
SmithGroup Project No. 00100084
National Zoological Conservation Biology Institute (NZCBI)
Construct Arabian Leopard Facility (ALF)
Phase 2 – Habitat & Animal Bldg
65% Construction Documents
TABLE OF CONTENTS
TOC - 1
COVER SHEET
NOTE: SECTIONS NOTED WITH ** ARE WRITTEN AND PROVIDED BY SMITHGROUP
CONSULTANTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 0107 - SEALS PAGE
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 1000 – SUMMARY (SI)
SECTION 01 2300 – ALTERNATES / OPTIONS (SI)
SECTION 01 2500 – SUBSTITUTION PROCEDURES (SI)
SECTION 01 2600 – CONTRACT MODIFICATION PROCEDURES (SI)
SECTION 01 2900 – PAYMENT PROCEDURES (SI)
SECTION 01 3100 – PROJECT MANAGEMENT AND COORDINATION (SI)
SECTION 01 3200 – CONSTRUCTION PROGRESS DOCUMENTATION (SI)
SECTION 01 3233 – PHOTOGRAPHIC DOCUMENTATION (SI)
SECTION 01 3250 – BIM REQUIREMENTS (SI)
SECTION 01 3300 – SUBMITTAL PROCEDURES (SI)
SECTION 01 3573 - DELEGATED DESIGN REQUIREMENTS AND PROCEDURES
SECTION 01 4000 – QUALITY REQUIREMENTS (SI)
SECTION 01 4200 – REFERENCES (SI)
SECTION 01 5000 – TEMPORARY FACILITIES AND CONTROLS (SI)
SECTION 01 5639 – TEMPORARY TEREE AND PLANT PROTECTION (SI)
SECTION 01 5715 – TEMPORARY NOISE AND VIBRATION CONTROLS (SI)
SECTION 01 6000 – PRODUCT REQUIREMENTS (SI)
SECTION 01 7300 – EXECUTION REQUIREMENTS (SI)
SECTION 01 7419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL (SI)
SECTION 01 7700 – CLOSEOUT PROCEDURES (SI)
SECTION 01 7823 – OPERATION AND MAINTENANCE DATA (SI)
SECTION 01 7839 – PROJECT RECORD DOCUMENTS (SI)
SECTION 01 7900 – DEMONSTRATION AND TRAINING (SI)
SECTION 01 8113.15 – SUSTAINABLE DESIGN REQUIREMENTS – LEED V4 BD+C
SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 4116 - STRUCTURE DEMOLITION
SECTION 02 4119 – SELECTIVE DEMOLITION **
FOR R
Phase 2 – Habitat & Animal Bldg
TOC - 2
DIVISION 03 - CONCRETE
SECTION 03 3000 - CAST-IN-PLACE CONCRETE **
SECTION 03 3500 – CONCRETE COLOR AND FINISHING **
SECTION 03 3713 – SHOTCRETE **
DIVISION 04 - MASONRY
SECTION 04 2200 – CONCRETE UNIT MASONRY
SECTION 04 4313.13 – ANCHORED STONE MASONRY VENEER
DIVISION 05 - METALS
SECTION 05 5000 – METAL FABRICATIONS
SECTION 05 5213 - PIPE AND TUBE RAILINGS
SECTION 05 7800 – DECORATIVE METAL BATTENS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
SECTION 06 1000 - ROUGH CARPENTRY
SECTION 06 1600 – SHEATHING
SECTION 06 4116 - PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 07 1326 - SELF-ADHERING SHEET WATERPROOFING
SECTION 07 1416 – COLD FLUID-APPLIED WATERPROOFING
SECTION 07 2100 - THERMAL INSULATION
SECTION 07 2600 - VAPOR RETARDERS
SECTION 07 2726 - FLUID-APPLIED MEMBRANE AIR BARRIERS
SECTION 07 3116 - METAL SHINGLES
SECTION 07 6200 - SHEET METAL FLASHING AND TRIM
SECTION 07 7253 – SNOW GUARDS
SECTION 07 9200 - JOINT SEALANTS
SECTION 07 9219 – ACOUSTICAL JOINT SEALANTS
SECTION 07 9513.16 - EXTERIOR EXPANSION JOINT COVER ASSEMBLIES
DIVISION 08 - OPENINGS
SECTION 08 1613 - FIBERGLASS (FRP) DOORS AND FRAMES
SECTION 08 3453 – ANIMAL ENCLOSURE CAGING AND DOORS **
SECTION 08 4313 - ALUMINUM-FRAMED STOREFRONTS
SECTION 08 4400 – GLAZED CURTAIN WALL
SECTION 08 7100 - DOOR HARDWARE **
SECTION 08 8000 – GLAZING
SECTION 08 8813 – GLASS VIEWING PANELS **
SECTION 08 8853 – SECURITY GLAZING
SECTION 08 9119 – FIXED LOUVERS
FOR R
Phase 2 – Habitat & Animal Bldg
TOC - 3
DIVISION 09 - FINISHES
SECTION 09 0561.13 - MOISTURE VAPOR EMISSION CONTROL
SECTION 09 2116.23 – GYPSUM BOARD SHAFT WALL ASSEMBLIES
SECTION 09 2216 - NON-STRUCTURAL METAL FRAMING
SECTION 09 2900 - GYPSUM BOARD
SECTION 09 3013 - CERAMIC TILING
SECTION 09 5113 - ACOUSTICAL PANEL CEILINGS
SECTION 09 6723 - RESINOUS FLOORING
SECTION 09 9123 – INTERIOR PAINTING
SECTION 09 9600 - HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
SECTION 10 2800 - TOILET, BATH, AND LAUNDRY ACCESSORIES
DIVISION 11 - EQUIPMENT
SECTION 11 1313 - LOADING DOCK BUMPERS
SECTION 11 3013 - RESIDENTIAL APPLIANCES
SECTION 11 4000 - FOODSERVICE EQUIPMENT
SECTION 11 9519 – ANIMAL EQUIPMENT **
DIVISION 12 - FURNISHINGS
SECTION 12 1423 – SIMULATED NATURE – ARTIFICIAL TREES AND PLANTS **
SECTION 12 3553.13 – METAL LABORATORY CASEWORK
SECTION 12 3661.16 – SOLID SURFACING COUNTERTOPS
DIVISION 13 – SPECIAL CONSTRUCTION
SECTION 13 3100 – SPECIAL STRUCTURES **
SECTION 13 3120 – CABLE SUPPORTED MESH STRUCTURES **
DIVISION 21 - FIRE SUPPRESSION
SECTION 21 3000 – FIRE SPRINKLER AND STANDPIPE SYSTEMS
Phase 2 – Habitat & Animal Bldg
TOC - 4
DIVISION 22 – PLUMBING
SECTION 22 0513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
SECTION 22 0516 - EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING
SECTION 22 0517 - SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
SECTION 22 0518 - ESCUTCHEONS FOR PLUMBING PIPING
SECTION 22 0519 - METERS AND GAGES FOR PLUMBING PIPING
SECTION 22 0523.12 - BALL VALVES FOR PLUMBING PIPING
SECTION 22 0523.14 - CHECK VALVES FOR PLUMBING PIPING
SECTION 22 0529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
SECTION 22 0553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
SECTION 22 0716 - PLUMBING EQUIPMENT INSULATION
SECTION 22 0719 - PLUMBING PIPING INSULATION
SECTION 22 0800 - COMMISSIONING OF PLUMBING
SECTION 22 1113 - FACILITY WATER DISTRIBUTION PIPING
SECTION 22 1116 - DOMESTIC WATER PIPING
SECTION 22 1119.1 - DOMESTIC WATER PIPING SPECIALTIES
SECTION 22 1119.2 - DOMESTIC WATER PIPING SPECIALTIES **
SECTION 22 1123 - DOMESTIC WATER PUMPS
SECTION 22 1313 - FACILITY SANITARY SEWERS **
SECTION 22 1316 - SANITARY WASTE AND VENT PIPING
SECTION 22 1319 - SANITARY WASTE PIPING SPECIALTIES
SECTION 22 1319.13 - SANITARY DRAINS
SECTION 22 1329 - SANITARY SEWERAGE PUMPS
SECTION 22 1413 - FACILITY STORM DRAINAGE PIPING
SECTION 22 1423 - STORM DRAINAGE PIPING SPECIALTIES
SECTION 22 3400 - FUEL-FIRED, DOMESTIC-WATER HEATERS
SECTION 22 4213.13 - COMMERCIAL WATER CLOSETS
SECTION 22 4216.13 - COMMERCIAL LAVATORIES
SECTION 22 4216.16 - COMMERCIAL SINKS
Phase 2 – Habitat & Animal Bldg
TOC - 5
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
SECTION 23 0100 - COMMON WORK RESULTS FOR HVAC
SECTION 23 0413 – COMMON SUBMITTAL REQURIEMENTS FOR HVAC
SECTION 23 0513 - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
SECTION 23 0516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING
SECTION 23 0517 - SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
SECTION 23 0518 - ESCUTCHEONS FOR HVAC PIPING
SECTION 23 0519 - METERS AND GAUGES FOR HVAC PIPING
SECTION 23 0523 - GENERAL-DUTY VALVES FOR HVAC PIPING
SECTION 23 0529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
SECTION 23 0548.13 - VIBRATION CONTROLS FOR HVAC
SECTION 23 0553 - IDENTIFICATION FOR HVAC, PIPING AND EQUIPMENT
SECTION 23 0593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC
SECTION 23 0713 - DUCT INSULATION
SECTION 23 0716 - HVAC EQUIPMENT INSULATION
SECTION 23 0719 - HVAC PIPING INSULATION
SECTION 23 0800 - COMMISSIONING OF HVAC
SECTION 23 0900 - INSTRUMENTATION AND CONTROL FOR HVAC
SECTION 23 1123 - FACILITY NATURAL-GAS PIPING
SECTION 23 2113 - HYDRONIC PIPING
SECTION 23 2116 - HYDRONIC PIPING SPECIALTIES
SECTION 23 2123 - HYDRONIC PUMPS
SECTION 23 2513 - WATER TREATMENT FOR CLOSED-LOOP HYDRONIC SYSTEMS
SECTION 23 3113 - METAL DUCTS
SECTION 23 3300 - AIR DUCT ACCESSORIES
SECTION 23 3346 - FLEXIBLE DUCTS
SECTION 23 3400 - HVAC FANS
SECTION 23 3433.13 – COMMERCIAL AIR CURTAINS
SECTION 23 3600 - AIR TERMINAL UNITS
SECTION 23 3713 - DIFFUSERS, REGISTERS, AND GRILLES
SECTION 23 5123 - GAS VENTS
SECTION 23 5216 - CONDENSING BOILERS
SECTION 23 6423.13 - AIR-COOLED, SCROLL WATER CHILLERS
SECTION 23 7313.19 - INDOOR, CUSTOM AIR-HANDLING UNITS
SECTION 23 8216.11 - HYDRONIC AIR COILS
SECTION 23 8219 - FAN COIL UNITS
SECTION 23 8233 - CONVECTORS
SECTION 23 8239.16 - PROPELLER UNIT HEATERS
SECTION 23 8316 - RADIANT-HEATING HYDRONIC PIPING
SECTION 23 8413 - HUMIDIFIERS
Phase 2 – Habitat & Animal Bldg
TOC - 6
DIVISION 26 – ELECTRICAL
SECTION 26 0400 - COMMON WORK RESULTS FOR ELECTRICAL
SECTION 26 0519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
SECTION 26 0523 – CONTROL VOLTAGE ELECTRICAL POWER CABLES
SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
SECTION 26 0533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
SECTION 26 0536 - CABLE TRAYS FOR ELECTRICAL SYSTEMS
SECTION 26 0543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL
SECTION 26 0544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND
CABLING
SECTION 26 0553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
SECTION 26 0573 - POWER SYSTEM STUDIES
SECTION 26 0800 - COMMISSIONING OF ELECTRICAL SYSTEMS
SECTION 26 0913 - ELECTRICAL POWER MONITORING AND CONTROL
SECTION 26 0923 - LIGHTING CONTROL DEVICES
SECTION 26 0936 - MODULAR DIMMING CONTROLS
SECTION 26 0943 - NETWORK LIGHTING CONTROLS
SECTION 26 2213 - LOW-VOLTAGE DISTRIBUTION TRANSFORMERS
SECTION 26 2416 - PANELBOARDS
SECTION 26 2726 - WIRING DEVICES
SECTION 26 2813 - FUSES
SECTION 26 2816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
SECTION 26 2913.01 – MANUAL AND MAGENTIC MOTOR CONTROLLERS
SECTION 26 2923 - VARIABLE-FREQUENCY MOTOR CONTROLLERS
SECTION 26 3213 - ENGINE GENERATORS
SECTION 26 3600 - TRANSFER SWITCHES
SECTION 26 3650 - GENERATOR DOCKING STATIONS
SECTION 26 4113 - LIGHTNING PROTECTION FOR STRUCTURES
SECTION 26 4313 – SURGE PROTECTION FOR L-V ELECTRICAL POWER CIRCUITS
SECTION 26 5100 - INTERIOR LIGHTING
SECTION 26 5600 - EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
SECTION 27 0500 - COMMON WORK RESULTS FOR COMMUNICATIONS **
SECTION 27 0526 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS **
SECTION 27 0528 - PATHWAYS FOR COMMUNICATIONS SYSTEMS **
SECTION 27 0528.10 – PATHWAYS FOR SECURITY SYSTEMS **
SECTION 27 0553 - IDENTIFICATION FOR COMMUNICATIONS SYSTEMS **
SECTION 27 1100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS **
SECTION 27 1500 - COMMUNICATIONS HORIZONTAL CABLING **
SECTION 27 1700 - TESTING OF STRUCTURED CABLING SYSTEMS **
Phase 2 – Habitat & Animal Bldg
TOC - 7
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
SECTION 28 0500.10 - COMMON WORK RESULTS FOR ELECTRONIC SECURITY**
SECTION 08 0507.10 – POWER SOURCES FOR ELECTRONIC SECURITY **
SECTION 28 0509.10 – SURGE PROTECTION FOR ELECTRONIC SECURITY **
SECTION 28 0531.10 - COMMUNICATIONS EQUIPMENT FOR ELECTRONIC SECURITY **
SECTION 28 0800.10 - COMMISSIONING ELECTRONIC SECURITY **
SECTION 28 1000 - ACCESS CONTROL **
SECTION 28 1515 - ELECTRIFIED LOCKING DEVICES AND ACCESSORIES **
SECTION 28 2000 – VIDEO **
SECTION 28 3100 - INTRUSION DETECTION **
SECTION 28 3111 – DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
DIVISION 31 - EARTHWORK
SECTION 31 1000 – SITE CLEARING **
SECTION 31 2300 – EARTHWORK **
SECTION 31 6333 – MICROPILES **
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 1313.1 – CONCRETE PAVING
SECTION 32 1313.2 – CONCRETE PAVING **
SECTION 32 1316 – DECORATIVE CONCRETE PAVING
SECTION 32 1373 – CONCRETE PAVING JOINT SEALANTS **
SECTION 32 1400 – UNIT PAVING
SECTION 32 1816.13 – PLAYGROUND PROTECTIVE SURFACING
SECTION 32 3100 – METAL FENCES AND GATES **
SECTION 32 3300 – SITE FURNISHINGS
SECTION 32 8400 – LANDSCAPE IRRIGATION
SECTION 32 9115 – PLANTING SOILS **
SECTION 32 9119 – LANDSCAPE GRADING **
SECTION 32 9280 – VEGETATION CONTROL
SECTION 32 9300 – EXTERIOR PLANTINGS
SECTION 32 9300 – PLANTS **
DIVISION 33 - UTILITIES
SECTION 33 1415 – SITE WATER DISTRIBUTION PIPING **
SECTION 33 4200 – STORMWATER CONVEYANCE **
END OF TABLE OF CONTENTS
June 15, 2026 Smithsonian OPDC Project No. 2533105
Phase 2 – Habitat & Animal Bldg
SEALS PAGE 00 0107 - 1
DOCUMENT 000107 - SEALS PAGE
Architect
SmithGroup, Inc.
Washington, DC
Structural Engineer
TYLin
Fire Protection Engineer
Mechanical Engineer
Electrical Engineer
Plumbing Engineer
Phase 2 – Habitat & Animal Bldg
SEALS PAGE 00 0107 - 2
Civil Engineer
Sorba Engineering
Dulles, VA
Landscape Architect
Habitat Designer
SHR Studios
Bainbridge Island, WA
Geotechnical Engineer
Haley Aldrich
Annapolis, MD
IT/AV/Telecom Engineer
BrightTree Studios
Pittsburgh, PA
Electronic Security
M2H Protection
Middletown, MD
Phase 2 – Habitat & Animal Bldg
SEALS PAGE 00 0107 - 3
Acoustic Engineer
Metropolitan Acoustics
Philadelphia, PA
Irrigation
Hines Inc.
END OF DOCUMENT
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 1
SECTION 01 1000 - SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Identification: Construct Arabian Leopard Facility (ALF)
SF Project No. 2533105
NZP-DC: Smithsonian’s National Zoo and Conservation Biology Institute (NZCBI)
3001 Connecticut Avenue, NW
Washington, D.C. 20008
B. Smithsonian Institution Contacts:
Contracting Officer (CO) address for Fed Ex and UPS delivery: Smithsonian Institution
Attn: Virginia Chan
Office of Contracting
600 Maryland Avenue, SW, Suite 500E
Washington, DC 20024
Contracting Officer (CO), address for USPS delivery: Smithsonian Institution
Office of Contracting
MRC 1200
P.O. Box 37012
Washington, DC 20013-7012
Contracting Officer's Technical Representative (COTR), address for Fed Ex, USPS, and UPS delivery:
Smithsonian Institution
Attn: Ryan Swanier
Office of Planning, Design & Construction
General Services Building
National Zoological Park
3001 Connecticut Avenue, NW
Washington, DC 2000
All references on drawings and in specifications to ‘Owner,’ ‘SI,’ ‘National Zoological
Park,’ ‘National Zoo,’ ‘Zoo,’ or ‘NZP’ refer to COTR.
1.2 SUMMARY OF WORK
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The Contractor shall furnish all supervision, labor, materials, and equipment needed to complete Phase 2 of the Construct Arabian Leopard Facility Project located at
Smithsonian Institution's National Zoological Park at 3001 Connecticut Avenue NW as set forth on the Drawings for OPDC Project No. 2533105 and in these specifications, anticipated final issue date in early October 2026 and as noted below.
The Work includes: The Phase 2 (Habitats and Animal Care Building) for the Arabian
Leopard Facility (ALF) that will be located southeast of the Connecticut Avenue entrance to the National Zoo. It will replace the former Bison Habitat and the existing Zoo in
Your Backyard, which is situated along the historic Olmsted Walk, across from the Africa
Trail Exhibit (currently under renovation), just north of the Elephant House, and abuts the east exit of the Panda Habitat.
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 2
2. Critical Elements of the Work: The successful Contractor shall be fully qualified to install critical elements of the Work. Upon request of the Contracting Officer, bidders shall submit a statement of qualifications to address the following critical elements of the Work:
a. Working within an occupied, historic campus active with public, staff and animals
b. Coordination of specialty trades within a small site footprint
c. Coordination and installation of specialty animal doors, transfer systems and manually operated remote door controls.
d. Coordination and installation of subsurface utility systems in a congested area
e. Coordination and installation of subsurface drainage and water conveying systems.
f. Coordination and installation of radiant flooring
g. Coordination and installation of animal containment fencing and mesh
h. Coordination and installation of shotcrete faux rock and faux trees
i. Mitigation of sound and vibration during demolition and construction so as not to harm animals in adjacent habitats
j. Coordination of construction activities with Zoo operations to align with feeding schedules, DC zoning community noise regulations, Zoo hours, known and unknown animal welfare issues, veterinary care, and public events
3. Related Documents include:
a. Arabian Leopard Facility (ALF) - Preliminary Acoustic Narrative (FOR REF ONLY), dated 1/22/26
b. Arabian Leopard Facility (ALF) – Geotechnical Engineering Study (FOR REF ONLY), dated 3/13/26
c. Arabian Leopard Facility (ALF) Phase 1 – Early Site Dwgs w-Addendum 1 (FOR REF
ONLY), dated 5/11/26
d. Arabian Leopard Facility (ALF) Phase 1 – Early Site Dwgs w-Addendum 1
Clarifications (FOR REF ONLY), dated 5/12/26
e. Arabian Leopard Facility (ALF) Phase 1 – Early Site Specs w-Addendum 1 (FOR REF
ONLY), dated 5/11/26
f. Arabian Leopard Facility (ALF) Phase 1 – Early Site Bid RFI Responses (FOR REF
ONLY), dated 6/11/26
g. Arabian Leopard Facility (ALF) Phase 2 – Habitats & Animal Care Building 65%
Design Development Drawings (FOR REF ONLY), dated 6/15/26
h. Arabian Leopard Facility (ALF) Phase 2 – Habitats & Animal Care Building 65%
Design Development Specifications (FOR REF ONLY), dated 6/15/26
4. As-built documentation, previous project design drawings, geotechnical/soils reports, structural analysis, surveys, and other materials may be provided for supplemental reference only. Accuracy of any information provided is not guaranteed. Any information contained therein may affect the project and must be field verified.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
C. Contract Time for Completion:
1. Work under this contract shall begin by the Contractor within ten (10) calendar days after the Notice to Proceed, unless stated otherwise in the Notice to Proceed issued by the Contracting Officer and shall be completed within the total contract time of 578 calendar days. All work, including project close-out activities, shall be completed in every respect within the contract time.
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 3
2. The start date and completion date shall be as stated in the Notice to Proceed issued by the Contracting Officer.
1.3 BIDDER EXAMINATION OF SITE
A. Every effort has been made to indicate all work necessary to complete the project as identified. All bidders shall carefully examine the premises during the bid period and satisfy themselves as to the extent, nature, and location of the work, general and local conditions, particularly those bearing on transportation, disposal, handling and storage of materials, access routes, availability of labor, water, electric, uncertainties of the weather, type of equipment and facilities needed for the successful execution of the work.
B. Pre-Bid Conference and Site Visit. Before or during the bidding period, a scheduled pre-bid conference and site visit will be announced by the COTR. The purpose of the scheduled meeting is to provide an opportunity for all bidders to review the project site. Any comments, information or discussion during the site visit shall not modify the contract documents.
C. This project requires special arrangements for access to a non-public area. Access to the site may be restricted at times other than during the scheduled visit.
1.4 ACCESS TO SITE
General: Contractor shall have limited use of project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
A. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations as indicated on the contract drawings.
2. Driveways, Walkways and Entrances: Keep driveway, parking areas, and entrances serving premises clear and available to the Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.5 COORDINATION WITH OCCUPANTS
A. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to
Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Obtain a Certificate of Occupancy from authorities having jurisdiction before any partial Owner occupancy.
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 4
1. Comply with limitations on public use and with other requirements of authorities having jurisdiction.
B. Work Restrictions, Adjacent Panda Habitats
1. Anticipated Stop Work Events – Due to the proximity of active panda habitats and associated care facilities to the Arabian Leopards project area, the Contractor shall anticipate any Stop Work Notices issued by the Contracting Officer’s Technical
Representative (COTR) as required by animal care staff to protect animal welfare.
Stop Work Notices shall be considered a normal and expected part of project execution and shall not constitute grounds for additional cost or time.
2. Potential Panda Relocations – Depending on the nature, duration, and intensity of adjacent construction activities, pandas may require temporary relocation to alternate enclosure spaces. Such relocations require advance notice, schedule coordination, and enhanced communication between the Contractor and the animal care team. The Contractor shall plan work sequencing to support these relocations and shall incorporate required coordination into the project schedule.
3. Means and Methods Affecting Panda Behavior – The Contractor shall submit detailed means and methods for any construction activities that may influence panda behavior, including but not limited to noise, vibration, visual disturbance, equipment movement, or changes in access patterns.
4. Daily Coordination Requirements for Sensitive Work – In addition to standard two week look ahead schedules, the Contractor shall conduct a daily coordination meeting with designated animal care team members prior to the start of sensitive work. This requirement applies especially to but not limited to high decibel, high impact, or otherwise disruptive activities. The purpose of the meeting is to confirm planned work; review required mitigations and resolve any animal care concerns before work begins.
C. On-Site Work Hours: Limit work in the project area to normal business working hours of 6 a.m. to 3:30 p.m., Monday through Friday, unless otherwise indicated.
1. Weekend Hours: Contractor shall seek approval from COTR.
2. Early Morning Hours: Contractor shall seek approval from COTR
3. Hours for Utility Shutdowns: Shall occur during “OFF HOURS” as determined by the COTR.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and only after providing temporary utility services according to requirements indicated:
1. Shall occur during “OFF HOURS” as determined by the COTR.
2. Existing emergency generators are not available for contractor’s required power shutdowns.
E. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than three days in advance of proposed disruptive operations.
F. Smoking is only allowed in COTR approved designated contractor locations. Contractor shall keep the area clean.
G. Traffic Control. The GC is to provide a flagger with SI issued badge for controlling access and managing all traffic entering NZP property SI\NZP staff will need access to occupied areas adjacent to but outside of the project construction zone, such as the Kudu yard See drawing C140 for additional requirements. Contractor will provide at least one traffic control
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 5
professional at each unlocked project vehicle/staff entrance during construction operating hours. During off hours the entire work area shall be fenced off and locked.
1. TRAFFIC PERSONNEL. The Contractor shall provide all necessary personnel for traffic control. The following personnel shall be required:
(1) TRAFFIC SAFETY OFFICER. The Contractor shall provide a competent traffic safety officer. The traffic safety officer shall be thoroughly experienced in and qualified for maintenance of traffic safety control work. Prior to commencing work requiring traffic control management, the Contractor shall certify in writing that the proposed Traffic Control Officer, and any designated substitute, has been certified by the American Traffic Safety Services Association (ATSSA). The Contractor shall submit a certificate verifying successful completion of the ATSSA course and a summary of the Traffic Safety Officer's field experience in the operation of work zone traffic control. Training provided by DDOT, or private firm may be approved provided that the following minimum requirements are met:
a) Successful completion of a comparable work zone traffic control course including evidence of passing a written examination on the material presented in the course.
b) A minimum of one year of documented field experience in work traffic control.
The traffic safety officer or an approved substitute, in case of forced absence, is expected to perform the duties on a regular basis and ensure that all traffic maintenance operations are running smoothly at all times by conducting regular inspections for the duration of the project, particularly during peak hours. The traffic safety officer's prime duty but not sole duty shall be the responsibility for the Contractor's maintenance of traffic operations. Duties shall include, but not be limited to, the following:
(a) Understand the requirements of the contract provisions.
(b) Be responsible for assuring compliance of the Contractor's maintenance and protection of traffic relative to the requirements of the contract provisions.
(c) Be responsible for assuring that all deficiencies are corrected.
(d) Be responsible for coordinating maintenance of traffic operations with the COTR.
(e) Supervise the installation and removal of all temporary traffic control devices and pavement markings.
(f) Be responsible for daily inspection of the work zone traffic control devices.
Inspection results shall be recorded in a Traffic Control Device Inspection Log.
(g) Monitor traffic flows to confirm that delays in the work zone are kept to a minimal duration for Zoo traffic.
(2) FLAGGERS. Contractor shall provide all necessary flaggers required to properly maintain traffic through the work zone. Flaggers shall have completed flagger training and shall be certified by ATSSA or another approved agency or firm.
a) Contractor must submit certification of individuals prior to working on the site.
b) Flaggers shall properly use all required safety gear (vests, flags, cones, tape, flashlights, etc.)
4.2 USE OF PREMISES
C. Use of Site: During the construction period, the Contractor shall have full use of the majority of the premises for construction operations within the “Limits of Construction.”
The Contractor’s use of the premises will be limited by the Smithsonian Institution’s right to perform work as indicated below. Security of the construction site is the responsibility of the Contractor.
1. Staff operations within buildings surrounding the project site
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 6
2. Contractor Parking: One parking space will be assigned to the Contractor for use during the contract period. The space will be located as close to the project site as possible. Coordinate with COTR.
3. The assigned space can only be used by the company vehicle. The vehicle must be clearly marked with company name and/or logo. The permit shall be displayed on the vehicle dashboard on the driver's side. Vehicles not in compliance with this clause are subject to ticketing and towing by the NZP police. Costs associated with parking violations shall be the sole responsibility of the Contractor.
4. Parking spaces will not be provided for the Contractor’s employees. Employees will be required to comply with the NZP’s pay parking regulations.
5. Personnel Vehicles may not be parked on the jobsite or roadways.
6. The Contractor is expected to provide whatever means necessary to protect persons and property from work activities.
D. Use of Utilities: Existing utilities are available for the Contractor’s use. See Division
01 Section 01500 “Temporary Facilities and Controls.”
E. Off-Hours Work and Overtime: For each occasion, the Contractor chooses to work on
Saturdays, Sundays, or Smithsonian holidays, or during hours other than 6:00AM –
3:00PM, obtain written permission from the COTR at least 5 working days in advance. The
Zoo is located in neighborhood community surroundings, which greatly limits the option to work off hours.
F. Temporary Construction Barriers: The contractor shall coordinate installation with the
COTR at least 5 working days prior to the scheduled construction barrier installation.
G. Work Stoppages and Deferrals for Animal Issues: Any issue posing a risk to zoo animal welfare may be considered equivalent to a safety hazard for humans.
4.3 CONTRACTOR BEHAVIOR
C. Dress and Deportment: Contractors and subcontractors on SI-property shall conduct themselves in a manner appropriate to a public place and animal care facility, abiding by all federal, state, and local laws and ordinances, as well as Smithsonian Institution directives. Contractor and subcontractor personnel shall be fully and appropriately clothed at all times. The COTR may require immediate removal of any individual from the premises and Project for:
1. Unacceptable dress, demeanor, disruptive conduct or
2. Unauthorized interaction, feeding, or harassment of any zoo animals or
3. Unauthorized entry into animal containment or non-public area or
4. Tampering with any animal containment barrier, device, gate, or lock.
D. The consumption of alcoholic beverages by the Contractor's personnel is prohibited in/on all Smithsonian property, buildings, or leased space.
E. Smoking or carrying lighted tobacco products is prohibited in all Smithsonian buildings and exhibition/public spaces, in areas where hazardous materials are stored or handled.
Acceptable areas for smoking are outside of buildings as designated by the Smithsonian.
F. The possession, sale, or use of narcotic or other illegal substances or contraband by
Contractor employees is strictly prohibited in/on all Smithsonian property, facilities, and leased spaces. Working on the project under the influence of alcohol or illegal substances is strictly prohibited.
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 7
4.4 JOB-SITE SAFETY AND RELATED SUBMITTALS
C. Safety Coordinator: The Contractor shall designate a person responsible and accountable for personnel safety at both corporate and project level at the project site for the duration of the project. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications for the Safety Coordinator shall include the
OSHA 30-hour course or equivalent course.
D. SUBMITTALS:
1. Job-Site Safety Plan: Submit a Job-Site Safety Plan that addresses safe construction operations by the contractor within 30 calendar days of the Contract
Award and at least 10 calendar days prior to mobilization to the site for approval by the COTR. Detail the procedures, designated persons, instructions, and reports to be used to assure job-site safety for all contractors, subcontractors, Smithsonian personnel, the public, and others on the site. Safety plan shall include adherence to all applicable provisions of Smithsonian Directive 419 (SD419) and all safety standards issued by the Safety Officer of the National Zoological Park.
5. Site Specific Safety Plan: Upon award of this contract, the contractor shall provide a Site-Specific Safety Plan (SSSP). The SSSP is a safety and health policy and program document and outlines how the contractor will safely conduct their work. This plan shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written. The
SSSP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the employer’s overall safety and health program that is referenced in the SSSP shall be included as appropriate. The plan shall include but not limited to the following:
a. Signature Sheet that must include plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).
b. Background Information that must include Brief project description, description of work to be performed, and location; phases of work anticipated these will require a
Job Hazard Analysis (JHA’s). OSHA 3071
c. Statement of Safety and Health Policy
d. Responsibilities and lines of Authority
e. Subcontractors and Suppliers
f. Training
g. Safety and Health inspections that include assignment of responsibilities for a minimum daily/weekly job site safety and health inspection during periods of work activity level of technical proficiency needed to perform the inspections, proof of inspector’s training/ qualifications.
h. Accident Reporting
i. Plans (programs, procedures) required by the Safety Manual. Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans.
Using the 29 CFR 1926 and/or current and accepted procedures in the EM 385-1-1 as a guide.
j. Risk Management Processes Detailed project-specific hazards and controls shall be provided by a Job Hazard Analysis (JHA) for each major phase/activity of work, including but not limited to work involving confined space, fall protection, trenching/excavation, crane/rigging, steel erection, hot work, protection of the
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 8
public, scaffolding, and other activities that involve high risk potential.
k. Jobsite supervisor/superintendent shall sign safety plan and JHA submissions with a final approved copies kept on the jobsite for operational references.
l. Project Evaluation for OSHA's silica standard (29 CFR 1926.1153) focuses on reducing exposure to respirable crystalline silica 12.
Key requirements include:
i. Lowering the permissible exposure limit (PEL) from 250 ug/m3 TWA to 50 ug/m3
TWA.
ii. Implementing engineering controls, respiratory protection, a written plan, proper training, ongoing medical surveillance, and oversight by a competent person.
C. Occupational Safety and Health: This contract is subject to Title 29 of the Code of Federal
Regulations, Part 1910 "Occupational Safety and Health Standards" and Part 1926 "Safety and Health Regulations for Construction" pursuant to the Occupational Safety and Health
Act (OSHA) of 1970 administered by the US Department of Labor, Occupational Safety and Health Administration.
D. Emergency Assistance: Post at the site telephone numbers for reporting emergencies, including the Smithsonian Office of Protection Services (OPS), ambulance, police, fire department, gas utility, electric utility, water/sewer utility, poison prevention aid, and hazardous- waste handling. Post this information in a conspicuous location within the project area prior to the start of any work at the site.
E. Safety Signs: Post legible accident prevention signs in construction areas in accordance with OSHA standards. Safety signs shall conform to ANSI 235.1, and 235.2 Vehicular traffic control devices, barricades, and signals shall conform to ANSI D6.1.
F. Report of Accident or Illness: In the event of any accident or illness for which medical assistance is required, any criminal actions, or any fire, notify the appropriate authority
(ambulance, police, and fire department), Smithsonian Security, and the COTR.
G. Emergency Evacuation: Post evacuation routes and facility emergency/self-protection plans at the site and train all employees in emergency procedures. In the event of a fire, immediately activate the alarm at the nearest fire alarm pull station and notify Zoo Police at (202) 633-4111. Upon the activation of the audible alarm, the building will be evacuated.
No personnel shall reenter the facility until security personnel signal that the building is safe.
H. Contractor Personnel to be contacted: Submit a written list of 24-hour emergency telephone numbers and names of persons to contact for the General Contractor superintendent and for each major sub-contractor working on the project site. The initial list shall be submitted to the COTR at the Preconstruction Meeting. Update and resubmit this list to the COTR as changes occur.
1.10 TOXIC AND HAZARDOUS SUBSTANCES
A. Submit to the COTR, at least thirty (30) working days prior to their intended use, a written list of toxic and hazardous substances that will be used on the project and an NZP Material
Approval Form for each. Submit a "Material Safety Data Sheet" similar to OSHA Form No.
20 for these substances to identify the following information:
1. Product Identification
2. Hazardous Ingredients
3. Physical Data
4. Fire and Explosion Hazard Data
5. Health Hazard Data
6. Emergency and First Aid Procedures
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 9
7. Reactivity Data
8. Spill or Leak Procedures
9. Special Protection Information
10. Special Precautions
B. Monitor the use of all toxic and hazardous substances to ensure that the specified
Threshold Limit Values (TLV's) and/or Permissible Exposure Limits (PEL's) are not exceeded. Exposure of the Contractor's personnel and Smithsonian Institution employees and visitors to air-borne or any other physical contact with any substance shall not exceed allowable concentrations specified in:
1. "Threshold Limit Values and Biological Exposure Indices" of the American
Conference of Governmental Industrial Hygienists, and
2. Title 29 CFR Part 1910, Subpart Z - "Toxic and Hazardous
Substances" of the Occupational Safety and Health Standards.
C. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances and pollutants produced by construction operations. Remove contaminated waste in compliance with applicable laws and regulations.
D. All containers used for hazardous chemicals shall be properly labeled. Labels should list at least the chemical identity, appropriate hazard warnings, and the name and address of the manufacturer, importer, or other responsible party.
E. To achieve compliance with the requirements of this section, administration or engineering controls shall first be implemented whenever feasible. When such controls are not feasible to achieve full compliance, protective equipment or other protective measures shall be used to keep exposure of all persons within the prescribed limits. Descriptions of equipment or technical measures to be used for this purpose must be submitted to the COTR for approval. The Contractor's requirements for compliance with all applicable local, federal, and state regulations remain in force.
1.11 PERSONAL PROTECTIVE EQUIPMENT
A. Personal protective equipment for eyes, face, ears, nose, head, extremities, and/or full body shall be provided, used, and maintained by the Contractor whenever necessitated by reasons of hazards encountered in a manner capable of causing illness, injury, or impairment in the function of any part of the body.
B. Persons required to use personal protective equipment shall be thoroughly trained. Training programs shall, as a minimum, meet OSHA and EPA requirements where applicable. The
Contractor shall submit proof and criteria for employee training as requested.
1.12 GENERAL SECURITY REQUIREMENTS
A. Prior to the start of work on the site, submit to the COTR, a list of the names, and phone numbers of all Contractor and subcontractor employees. Identify the Prime Contractor and each subcontractor and trade. Update list as necessary to accurately identify all workers who will be working on the site during the Project.
B. Provide the name and telephone number of the Contractor's Superintendent and authorized alternate individual who can be reached on a 24-hour basis at the Preconstruction
Meeting.
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 10
C. After Beneficial Occupancy, Contractors working inside those areas of the project shall display SI- provided ID badges and sign - in and – out at the zoo police station and other appropriate security checkpoints.
1.13 DRILLING, WELDING, TORCH, AND ARC CUTTING, AND
OPERATIONS THAT PRODUCE AIRBORNE CONTAMINANTS
A. Daily Permit: When welding, torch or arc cutting, or other heating operations are to occur inside existing structures, the Contractor shall obtain a daily “Burn Permit.” When work produces dust or other airborne contaminants, e.g., spray painting that could impair existing fire suppression or detection system(s), the Contractor shall obtain a daily “Fire System
Impairment Permit.” Each permit must be obtained at least two working days in advance from the Building Manager’s Office through the COTR and posted at the job site prior to beginning the scheduled work.
B. Fire Watch: No welding, torch, or arc cutting shall be performed unless adequate fire protection is provided. The Contractor shall maintain a fire watch for the duration of welding, cutting, and heating operations and for at least 30 minutes after the ‘hot’ work has stopped. A fire extinguisher (minimum 10 pounds, dry-chemical type, typical) shall be on hand when drilling, welding, or cutting.
C. In lieu of SI’s Daily Permit, the Contractor may request the use of Contractor’s job site oversight permit process, confirming that it meets all SI oversight and safety requirements.
1.14 SAFETY
A. All operations shall be conducted in accordance with all national and local fire and safety codes, laws, rules, and regulations.
B. Warning Signs and Barricades: All roadways shall remain open to the public unless approved by the COTR. The Contractor shall provide, erect, and maintain all necessary signs, barricades, traffic cones, warning and danger signals and signs, and provide enough security guards and flaggers to insure the safe flow of traffic, protection of the work area and the safety of the public and staff.
1.15 SPECIFICATION, DRAWING CONVENTIONS, AND ELECTRONIC DATA
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications.
The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the
Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on the
Drawings to identify materials and products:
FOR R
Phase 2 – Habitat & Animal Bldg
SUMMARY 01 1000 - 11
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
1.16 MISCELLANEOUS PROVISIONS
A. Units of Measure: Perform all layout, construction, fabrication, and installation in accordance with the units of measure given in the Contract Documents. This project may be designed, dimensioned, and specified as an imperial project.
1. All Contractor and sub-contractor personnel working on the site shall possess and use appropriate measuring equipment for all work shown. Conversion of dimensions shown on contract documents for use of non-compliant measuring equipment is prohibited.
2. All submittals shall display appropriate measurements to ensure conformance with the Contract Documents. Project-specific shop drawings shall be prepared in preferred appropriate drawing scales and shall display appropriate dimensions.
3. All correspondence shall use appropriate units exclusively. All cost data submitted by the Contractor in a proposal or any other submission shall be in appropriate units.
4. All Operations and Maintenance (O&M) material shall be submitted with appropriate units and dimensions that clearly demonstrate conformance with the contract drawings and specifications.
5. When permits or approvals are required by outside state or local agencies and/or utilities, provide submittals to these authorities in the format, scale, and measurement system they require. Annotate these submittals with parenthetical equivalents of critical size and location dimensions to facilitate the review of the submittal in comparison to the Contract Documents.
B. Hazardous Materials: Notify the COTR immediately if any suspected asbestos-containing materials, lead paint, PCBs, or other hazardous materials other than those indicated in the construction documents are uncovered during Work.
1.17 CONSTRUCTION APPROVAL
A. Final approval and direction shall be provided by the Contracting Officer (CO) or
Contracting Officer’s Technical Representative-Construction Management (herein COTR).
The Authority Having Jurisdiction is SI-Office of Safety, Health, and Environmental
Management (OSHEM) and they shall provide direction through the CO or COTR. The owner’s agent is the COTR. All references within the construction documents to other entities providing approval shall mean initial approval or recommendation prior to COTR final approval.
END OF SECTION 011000
Phase 2 – Habitat & Animal Bldg
ALTERNATES / OPTIONS 01 2300 - 1
SECTION 01 2300 – ALTERNATES / OPTIONS
1.1 RELATED DOCUMENTS
A. The Contract Documents in their entirety, including the Drawings, Specifications, Construction
Contract Clauses, and any other documents issued as part of the Contract, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates/options.
1.3 DEFINITIONS
A. Alternate/Option: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Alternates/Options described in this Section are part of the Work only if enumerated in the Agreement.
2. The cost or credit for each alternate/option is the net addition to or deduction from the
Contract Sum to incorporate alternate/option into the Work. No other adjustments are made to the Contract Sum.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate/option into Project.
1. Include as part of each alternate/option, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate/option.
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate/option. Indicate if alternates/options have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to alternates/options.
C. Execute accepted alternates/options under the same conditions as other work of the Contract.
D. Schedule: A schedule of alternates/options is included at the end of this Section. Drawings and
Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate/option.
END OF SECTION 012300
Phase 2 – Habitat & Animal Care
SUBSTITUTION PROCEDURES 01 2500 - 1
SECTION 01 2500 - SUBSTITUTION PROCEDURES
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 016000 “Product Requirements” for requirements for submitting comparable product submittals for products by listed manufacturers.
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed
Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or COTR that are not required in order to meet other Project requirements but may offer advantage to
Contractor or COTR.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit each request electronically in Portable Document Format (.pdf) to the COTR for consideration. Identify product or fabrication or installation method to be replaced.
Include Specification Section number and title and Drawing numbers and titles.