The Department of Veterans Affairs is soliciting comprehensive fire suppression and alarm system maintenance services for their Jackson Regional Office located at 1600 E. Woodrow Wilson Avenue in Jackson, Mississippi. The contract requires a qualified Service-Disabled Veteran-Owned Small Business to perform annual and monthly inspections, testing, and maintenance of fire alarm systems, fire suppression systems, backflow preventers, fire pumps, fire extinguishers, and related safety equipment in accordance with NFPA and Joint Commission standards. Evaluation will be based on two primary factors: Technical Qualifications and Relevant and Recent Past Performance. Critical dates include the Request for Information deadline of September 9, 2025 at 12:00 PM EST, a second mandatory site visit scheduled for September 4, 2025 at 9:00 AM CST, and the final quote submission deadline of September 18, 2025 at 12:00 PM EDT. The contract requires the successful offeror to repair 14 fire pull stations in the parking structure, replace two malfunctioning backflow preventers, and maintain comprehensive fire safety systems throughout the multi-story facility.
This opportunity is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses under NAICS code 541350 with a size standard of $11.5 million. The contract includes a base year from October 1, 2025 to September 30, 2026, with four additional one-year option periods that could extend the contract through September 30, 2030, creating a potential five-year engagement. The facility features three elevators serving three floors, two standpipes, multiple types of fire extinguishers including 10-pound dry chemical and 22-pound units, and various backflow preventers manufactured by Watts and Wilkins requiring inspection and testing. The work will be performed at the VA Regional Office building which includes basement, ground floor, three upper floors, and multiple garage levels with comprehensive fire detection and suppression systems throughout. No incumbent contractor information was provided in the solicitation materials, and while no specific contract value was disclosed, the extensive scope of services and five-year potential duration suggest a substantial maintenance contract for this critical federal facility.
Notice text
5 versions
Update #5 · Latest ·
Solicitation 36C10D25Q0129
Fire Suppression Maintenance at VBA Jackson Regional Office
Questions and Answers
Set #3
Can you please specify each element of performance from the Joint Commission standard EC.02.03.05 is required to be performed and documented under this contract? Referring to NFPA 25 and 72 does not provide the clarification needed.
Please refer to the updated SOW.
Which CLIN should the cost for fire alarm monitoring services be applied to?
It is included in the contract. Please refer to the SOW.
Which CLIN should the cost of the internal 5-year obstruction inspection be applied to? Please note, this is to occur in only 1 of the 5 years of the contract.
Refer to the SOW.
Can you please provide a complete inventory of fire extinguishers requiring inspection? This list should be broken down by type and size to determine appropriate inspection costs. Gathering an inventory of the fire extinguishers is not something that can be done during a site visit as that would require building drawings and access to every room to verify fire extinguishers. A previous inspection report will also provide us with the quantities and each type.
I have requested the list.
Previous responses to the RFI s included a fire alarm inspection report. Can you please provide the previous annual fire sprinkler, standpipes, fire pump, backflow preventers, kitchen suppression, and fire extinguisher inspection reports? These reports will help clear up uncertainty within the scope of work and as required by the joint commission they should be available.
I have requested the list.
Previous question 13.8, response stated see number 7 above. These 2 items are not same. CLIN 0011 is to replace 14 pull stations which the host of the site visit was under the impression this work was already completed. Please confirm if this work is completed or needed to remain in this scope of work.
Remain in the scope but changed from replaced to repair 14 pull station.
The scope of work for fire alarm and detection/monitoring services Paragraph a.vi states the monitoring service needs to be at a minimum NICET certified. This does not exist, NICET certifies individual technicians in fire protection related disciplines. Companies and facilities are not provided with NICET certifications for anything. Can you please remove or revise this requirement to ensure offerors will not be deemed unacceptable because of this? Remove the language for the NICET requirement. The contractor will provide the minimum NFPA 72 requirement. SOW has been updated.
(Does this mean that the monitoring service should be UL listed).
No
Relating to the RFI above, please confirm the intention for the NICET requirement is for technicians performing the inspection, testing, and maintenance to be NICET certified. Typically, NICET Level II technicians perform the inspection, testing, and maintenance work, and are overseen by NICET III or IV technicians. We would recommend qualification requirements such as this consistent amongst most fire protection and life safety solicitations we see through the VA. The Technician can be NICET certified but require per NFPA 72 requirements.
(This needs more clarification. In the past, the technicians were required to have NICET II license to perform inspections on site. This answer makes that sound optional, but I'm not sure that is what the customer meant. NFPA 72 has nothing to do with the license requirement. We need to confirm that all inspectors performing the inspections need to have NICET II certifications. We also need to confirm if that goes for all systems, (Fire alarm, sprinkler, extinguisher, suppression etc.), or if it only applies to fire and sprinkler).
Please look at the revise statement of work.
When were each of the required 5-year inspection services last performed? We need to know this for allocating resources for each contract year. The last five-year inspection was completed September 4, 2024.
(I have paperwork showing a 5-year internal/obstruction inspection was just completed on the sprinkler system in August this year. Is this in reference to another 5-year inspection? And which system is this 5-year referring to if it's not sprinkler?)
Please look at the revise statement of work. 5 year annual inspection is 5 years from September 4, 2024
The following questions are regarding the Price/Cost Schedule.
Item 0001: Is this two 100% inspections each year or two 50% inspections each year? Please read the information by Please refer to NFPA 25 standards.
(This seems to be very vague and leaves it up for interpretation by each vendor. The item refers to fire alarm, so it would be NFPA 72, not NFPA 25. I would say 100% annual once a year, (including smoke detector cleaning), and a simple panel battery inspection/test & visual of the rest of the system for the semi-annual requirement. Please confirm).
Please look at the revise statement of work.
Item 0002: Exactly what is to be included in monthly inspections? Just notification devices (A/Vs)? 100% or 1/12? Please refer to NFPA 25 standards
(This seems to also be referring to NFPA 72, since it's fire alarm. The monthly inspections are visual only for control equipment & system status checks according to NFPA 72. Please confirm).
Please look at the revise statement of work.
Item 0003: Exactly what is to be included in monthly inspections? 100% or 1/12? Please refer to NFPA 25 standards.
(Also for fire alarm, NFPA 72. This item also notes a monthly inspections. Item 0002 & 0003 seem to be the same thing Please confirm).
Please look at the revise statement of work.
Item 0006: Is this 100% each month or 1/12 each month? Please refer to NFPA 25 standards.
(Monthly is running the fire pump for 10 minutes each week, and visually checking valves & gauges on all sprinkler and standpipe systems once a month ..Please confirm).
Please look at the revise statement of work.
Item 0007: The specifications mention backflow to be inspected monthly, but this item specifies once per year. Can you please clarify? Please read the information from SOW and the CLIN again. Fire suppression (a)(x) shows a monthly inspection. CLNN 0007states that the backflow preventor will be TESTED annually.
(If the SOW calls for monthly backflow inspections, which CLIN should we put the price for that? 0006 mentions sprinkler, standpipe, and fire pump, but not backflow.. Please confirm).
I don t see a line item to provide pricing for monitoring services or for 5-year Internal Obstruction inspections listed in the specifications. There is no line item for that.  That is part of the contract when the contract is awarded.Â
(If there is no line for that, and this is part of the contract when it is awarded, does this mean we provide that price separately at the time these items are needed, or should the price be included in one of the CLIN. If we should include the price in a CLIN, which CLIN should we include it under?)
Please reference the Updated SOW.
Item 0011: Site visit guide was under the assumption that this item may have already been completed. Please clarify. See number 7 above.
(The SOW for 0011 is for replacing 14 pull stations. Was that completed? Number 7 only notes the backflow.)
Please reference the Updated SOW.
Do the devices already have unique identifiers or is this a new feature added to the scope this year? If they already have them, are they barcodes? And will the listing be provided to the winning bidder? Yes (The device names are listed on the points list provided. If they are already named and in the panel programming, I'm not sure what this CLIN is for. What is item 0009 exactly requesting?)
Please reference the Updated SOW.
In the section referencing the suppression (Ansul) system, it specifies that the contractor shall provide inspection & maintenance . including installation, maintenance, and testing of the system. Please define what is to be included with the terms installation and maintenance . Please refer to NFPA 72.
(Assuming this is NFPA 96, since it's referencing kitchen hood. We need to confirm if we are responsible for installing a brand new kitchen hood system, or any 'adds moves changes', in our quoted price, or if those larger items would be quoted outside of this initial price.)
Please review NFPA standard that applies to what you are doing relating to kitchen hood. Please refer to the SOW (repairs and Repair Charges) of once a problem is identified.
In the section referencing monthly preventative maintenance of the fire sprinkler system, what is considered preventative maintenance ? Preventative maintenance is a proactive approach to ensuring that equipment and facilities run smoothly, avoiding the high costs and disruptions of unplanned breakdowns. This will be related to the sprinkler system.
(I've always understood preventative maintenance to be inspections and testing, since that is the way to prevent issues in advance when possible. This would not normally include labor or materials to actually make the repairs Please confirm.
Please refer back to the SOW (repairs and Repair Charges) of once a problem is identified.
Can you please provide the make/model and location of the flame detector? Another site visit is required for that.
(During walkthrough, all agreed there is not a flame detector, and it should be removed from the RFQ in the device list .Please confirm.)
Yes, agreed No flame detector listed.
Update #4 ·
Solicitation 36C10D25Q0129 Amendment 0003 to Revise Contract Line Item Numbers (CLINs)
Update #3 ·
Solicitation 36C10D25Q0129
Fire Suppression Maintenance at VBA Jackson Regional Office
Questions and Answers
Set #2
September 4, 2025
On the two malfunctioning backflow preventers, can you please provide the type, size, make, and data from the data placard or the last inspection report/deficiency notation? See attached photos for specifics
Make: watts Model: 909 4 RP Serial No: 200465
Make: Wilkins Mode: 375 RP 4 Serial No: L09323
Can you please provide the make, model, and size of the other backflow preventers requiring inspection and testing? See attached photos for specifics
Make: watts Model: 909 4 RP Serial No: 200465
Make: Wilkin Model: 375A 3 RP Serial No: X00891
Make: Wilkins Mode: 375 RP 4 Serial No: L09323
Can you provide additional information for the fire pump? What is the make and model, size (rated flow and pressure), and diesel or electric? See attached photos of the fire pump data plate
Centrifugal Fire Pump: Split Case
Make: 4 1844F Serial#: 14-2429323
The equipment list shows fire extinguishers. What are the types and sizes of fire extinguishers requiring inspection?
Model 10MB-6H Dry Chemical 10lBS
Model: AA108339 22lbs
What type of monitoring communicator is used, POTs (plain old telephone service) or cellular? Dual Path Dire Alarm Cell/IP communicator. See the photo attached of the communicator.
How many elevators are there in total, and how many floors does each elevator serve? There are 3 elevators. There are 3 floors.
How many standpipes are there? There are 2 standpipes.
Can you please provide the make/model and location of the flame detector? Please refer to the list provided for the flame detectors. The location is listed on the custom label list that is covered under the fire suppression fire alarm.
Update #2 ·
Preparation and Submission Instructions
Quote Requirements - The following items shall be included in your submission:
Cover Page with Solicitation Number, Project Title, points of contact, address, phone numbers, etc., and SAM Unique Entity ID Number (Contractors shall be registered in SAM - Home | SAM.gov)
Response to Evaluation Factors:
Factor 1 Technical Qualifications
Factor 2 Relevant and Recent Past Performance
Signed offer (SF 1449) and Signed Acknowledgement of all Amendments (SF30) (if any are executed)
Pricing Schedule completed
Copy of current SDVOSB certification from VetCert (Small Business Administration - Veteran Small Business Certification (sba.gov))
Ensure the appropriate NAICS code (541350) is listed in the company s SAM Representations and Certifications
Site Visit:
A Second Site Visit is scheduled for September 4, 2025 at 9:00am CST. All contractors will meet at the front of the building s double glass door to enter the regional office at 1600 E. Woodrow Wilson Avenue, Jackson, MS 39216.
The contractors can park in the parking garage (the arm will be up).  We will meet at the entrance door to the Regional Office exiting the parking garage. When you park in the parking garage proceed to the ground floor. The parking garage is connected to the building. Wait at the double glass door to enter the regional office.Â
Request for Information (RFI):
All RFIs are due no later than September 9, 2025 no later than 12:00pm EST. All RFIs shall be submitted to the Contracting Officer via email at tiffany.garfield@va.gov
Update #1 ·
Please see attached solicitation.
Attachments
| File | Type | Posted |
|---|---|---|
| 36C10D25Q0129 0004.docx | DOCX document | |
| 36C10D25Q0129 0003.docx | DOCX document | |
| Initial Site Visit Attendees 8-14-2025.pdf | ||
| 36C10D25Q0129 0002.docx | DOCX document | |
| Second Site Visit Attendees 9-4-2025.pdf | ||
| Photos for RFIs.zip | ZIP file | |
| Fire Alarm and Fire Suppression Labels.pdf | ||
| 36C10D25Q0129 0001.docx | DOCX document | |
| Fire Alarm Inspection Report.pdf | ||
| 36C10D25Q0129.docx | DOCX document | |
| Wage Determination Jackson.pdf |
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| J042--Jackson Fire Suppression Maintenance | Solicitation | |
| J042--Jackson Fire Suppression Maintenance | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity