FY14 MCA PN67157 USARPAC Command and Control Facility (C2F) Phase 2, Fort Shafter, Oahu, Hawaii

Award Notice Posted

Solicitation number
W9128A-15-B-0001
Agency
Awarded
to Watts Constructors LLC
Set-aside
No set-aside

Opportunity facts

Contract number
W9128A15C0003 Federal contract award
PSC
Not on record
Place of performance
Usace District, Honolulu Building 230, Fort Shafter HI 96858 US

Notice details come from SAM.gov. Updated .

Notice text

7 versions

Update #7 · Latest ·

In accordance with Federal Acquisition Regulations (FAR) Subpart 5.2, the U.S. Army Corps of Engineers, Honolulu District issues the below pre-synopsis of work. This announcement is not a solicitation and represents upcoming construction work.

This pre-synopsis is for a firm-fixed price construction requirement at Fort Shafter, Hawaii. Solicitation for this work is anticipated to be issued on or about April 28, 2015. This work will be competitively issued as an unrestricted procurement utilizing the Sealed Bidding procedures prescribed at FAR Part 14. The NAICS Code for this project is 236220: Commercial and Institutional Building Construction. The Small Business size standard for this NAICS code is $36.5 Million average annual revenue.

Project Description: This project will construct a portion of the USARPAC Command and Control (C2F) Facility. It is Phase 2 (PN 67157 Main Operations) of a now 3-phase project. The project meets requirements in the UFC 4-0140-03 for Command and Control Facilities (Division through Command (ACOM) Levels) Standard Design.

This phase includes construction of administrative and special use spaces divided into specified security zones. Facility construction includes redundant mechanical and electrical systems with backup power for designated areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, Energy Monitoring connection, special foundations, and ATFP measures. Sustainable Design and Development and Energy Policy Act of 2005 (EPAct05) features will be provided. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, signage and minimal landscaping. Air conditioning will be provided by connection to the complex central utility plant (constructed in phase 1) through a utility tunnel (portions constructed in every phase). Access for individuals with disabilities will be provided. There is also a secured driveway situated at the back of the building to provide access to the central plant and generator yard (built in Ph 1) and SCIF facility (in Ph 3). The project design and cost reflects the user of traditional construction materials and practices.

Phase 2 of the C2F consists of a total of 88,237 SF in a four story bldg, with a mechanical penthouse. The following spaces are included Phase 2 Main Operations: Safety, Operational Protection Directorate (OPD), Operations and Plans/Civil Affairs (G-3/5/7/9), Fires and Effects (FXD), Command, Control, Communications, Computers and Intelligence (G-6), Intelligence and Security (G-2), loading dock and Destruct Room.

Materials used in this project are standard materials for the spaces being built. Major architectural portions of the project include:
Ceramic tile, resilient linoleum flooring, concrete floors, carpet, raised access floors, gypboard walls, sound absorbing wall panels, tackable wall panels, suspended ceilings, painted ceilings, door signs (adhesive back with Braille), exterior CMU block, stucco exterior, standing seam metal roofing.

The estimated performance of period is 24 months. Magnitude is $25M - $100M.

Traditional hard copies of plans and specifications will NOT be available for this project. Drawings and specifications will be made available for viewing and/or downloading on the Federal Business Opportunities (FedBizOpps) website at https://www.fbo.gov on or about April 28, 2015. An amendment to this notice will provide advance notice of the target pre-bid conference and site visit date.

It is the bidder's responsibility to check for any posted changes to the solicitation. Solicitation documents will not be issued on compact disc (CD) unless the Government determines that it is necessary. Bidders must have and/or maintain an active registration with the System for Award Management (SAM) website to be eligible for a Government contract award. To register in SAM, go to https://www.sam.gov. All Bidders are encouraged to visit the FedBizOpps website to view other business opportunities.

Update #6 ·

The solicitation, W9128A-15-B-0001, is issued.  Please see attachments.

Update #5 ·

Personal protective equipment (PPE) will be required if attending the site visit. PPE includes safety glasses, hard hat, safety vest, and safety shoes. The C2F Phase 1 Safety Officer will be giving a safety brief prior to the site visit. You will not be allowed to attend the site visit if you do not have the appropriate PPE.

An advance copy of the pre-bid conference and site visit map is also issued and will be included in the solicitation. 

Update #4 ·

1. The following drawings files that were not issued in the previous announcement are being issued - V2a5R.pdf and V4a6R.pdf.

2. The Government has determined that there is no Public Labor Agreement for this solicitation.


3. A pre-bid conference will be conducted by the Government on May 14, 2015 starting at 1000 hrs Hawaii Standard Time (HST) at Hale Ikena, Fort Shafter, Hawaii. All interested parties (prime contractors, subcontractors, and suppliers) are encouraged to attend this conference. A copy of the map to Hale Ikena will be provided by a separate announcement and will also be included in the solicitation.


Tentative Schedule:


9:00 am Contractor's "Meet and Greet" at Hale Ikena (Pikake 1 & 2). Informal time for contractors to meet others & exchange business information. Tables will be available from 9:00am on a first come first serve basis.


10:00 am Pre-Bid Conference Starts


Potential attendees should notify the Government with the number of attendees before the date of the conference. Please email all three individuals the number of attendees.


Tristin Suetsugu, #808-835-4382; Tristin.N.Matsuki@usace.army.mil
Kent Tamai, #808-835-4377; Kent.A.Tamai@usace.army.mil
Dayna Matsumura, #808-835-4379; Dayna.N.Matsumura@usace.army.mil


4. An organized site visit has been scheduled for May 15, 2015 at 1000 hrs HST. Participants will meet at the Phase 1 Contractor's Trailer. Parking is limited near the site. Attendees are encouraged to arrive early to secure parking. Parking is available on base. Please do not park in a marked or reserved stall. A copy of the map to Contractor's trailer will be provided by a separate announcement and will also be included in the solicitation.

Update #3 ·

Advance copies of the drawings and technical specifications are issued. All interested firms are encouraged to review the drawings and technical specifications prior to the pre-bid conference and site visit. The same drawings and technical specifications will also be included when the solicitation is issued. Any changes to the drawings and technical specifications will be addressed by amendment(s) to the solicitation.

The following drawings are issued -
V1 a1 - a13
V2 a1 - a14
V3 a1 - a6
V4 a1 - a11


The following specifications are issued -
V1
V2

Update #2 ·

In accordance with Federal Acquisition Regulations (FAR) Subpart 5.2, the U.S. Army Corps of Engineers, Honolulu District issues the below pre-synopsis of work. This announcement is not a solicitation and represents upcoming construction work.

This pre-synopsis is for a firm-fixed price construction requirement at Fort Shafter, Hawaii. Solicitation for this work is anticipated to be issued on or about April 28, 2015. This work will be competitively issued as an unrestricted procurement utilizing the Sealed Bidding procedures prescribed at FAR Part 14. The NAICS Code for this project is 236220: Commercial and Institutional Building Construction. The Small Business size standard for this NAICS code is $36.5 Million average annual revenue.

Project Description: This project will construct a portion of the USARPAC Command and Control (C2F) Facility. It is Phase 2 (PN 67157 Main Operations) of a now 3-phase project. The project meets requirements in the UFC 4-0140-03 for Command and Control Facilities (Division through Command (ACOM) Levels) Standard Design.

This phase includes construction of administrative and special use spaces divided into specified security zones. Facility construction includes redundant mechanical and electrical systems with backup power for designated areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, Energy Monitoring connection, special foundations, and ATFP measures. Sustainable Design and Development and Energy Policy Act of 2005 (EPAct05) features will be provided. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, signage and minimal landscaping. Air conditioning will be provided by connection to the complex central utility plant (constructed in phase 1) through a utility tunnel (portions constructed in every phase). Access for individuals with disabilities will be provided. There is also a secured driveway situated at the back of the building to provide access to the central plant and generator yard (built in Ph 1) and SCIF facility (in Ph 3). The project design and cost reflects the user of traditional construction materials and practices.

Phase 2 of the C2F consists of a total of 88,237 SF in a four story bldg, with a mechanical penthouse. The following spaces are included Phase 2 Main Operations: Safety, Operational Protection Directorate (OPD), Operations and Plans/Civil Affairs (G-3/5/7/9), Fires and Effects (FXD), Command, Control, Communications, Computers and Intelligence (G-6), Intelligence and Security (G-2), loading dock and Destruct Room.

Materials used in this project are standard materials for the spaces being built. Major architectural portions of the project include: Ceramic tile, resilient linoleum flooring, concrete floors, carpet, raised access floors, gypboard walls, sound absorbing wall panels, tackable wall panels, suspended ceilings, painted ceilings, door signs (adhesive back with Braille), exterior CMU block, stucco exterior, standing seam metal roofing.

The estimated performance of period is 24 months. Magnitude is $25M - $100M.

Traditional hard copies of plans and specifications will NOT be available for this project. Drawings and specifications will be made available for viewing and/or downloading on the Federal Business Opportunities (FedBizOpps) website at https://www.fbo.gov on or about April 28, 2015. An amendment to this notice will provide advance notice of the target pre-bid conference and site visit date.

This is advance notice the pre-bid conference will conducted in the morning of May 14, 2015 at Fort Shafter, Oahu, Hawaii. The site visit will be conducted in the morning of May 15, 2015. More information will be provided in the solicitation.

It is the bidder's responsibility to check for any posted changes to the solicitation. Solicitation documents will not be issued on compact disc (CD) unless the Government determines that it is necessary. Bidders must have and/or maintain an active registration with the System for Award Management (SAM) website to be eligible for a Government contract award. To register in SAM, go to https://www.sam.gov. All Bidders are encouraged to visit the FedBizOpps website to view other business opportunities.

Update #1 ·

In accordance with Federal Acquisition Regulations (FAR) Subpart 5.2, the U.S. Army Corps of Engineers, Honolulu District issues the below pre-synopsis of work. This announcement is not a solicitation and represents upcoming construction work.

This pre-synopsis is for a firm-fixed price construction requirement at Fort Shafter, Hawaii. Solicitation for this work is anticipated to be issued on or about April 28, 2015. This work will be competitively issued as an unrestricted procurement utilizing the Sealed Bidding procedures prescribed at FAR Part 14. The NAICS Code for this project is 236220: Commercial and Institutional Building Construction. The Small Business size standard for this NAICS code is $36.5 Million average annual revenue.

Project Description: This project will construct a portion of the USARPAC Command and Control (C2F) Facility. It is Phase 2 (PN 67157 Main Operations) of a now 3-phase project. The project meets requirements in the UFC 4-0140-03 for Command and Control Facilities (Division through Command (ACOM) Levels) Standard Design.

This phase includes construction of administrative and special use spaces divided into specified security zones. Facility construction includes redundant mechanical and electrical systems with backup power for designated areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, Energy Monitoring connection, special foundations, and ATFP measures. Sustainable Design and Development and Energy Policy Act of 2005 (EPAct05) features will be provided. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, signage and minimal landscaping. Air conditioning will be provided by connection to the complex central utility plant (constructed in phase 1) through a utility tunnel (portions constructed in every phase). Access for individuals with disabilities will be provided. There is also a secured driveway situated at the back of the building to provide access to the central plant and generator yard (built in Ph 1) and SCIF facility (in Ph 3). The project design and cost reflects the user of traditional construction materials and practices.

Phase 2 of the C2F consists of a total of 88,237 SF in a four story bldg, with a mechanical penthouse. The following spaces are included Phase 2 Main Operations: Safety, Operational Protection Directorate (OPD), Operations and Plans/Civil Affairs (G-3/5/7/9), Fires and Effects (FXD), Command, Control, Communications, Computers and Intelligence (G-6), Intelligence and Security (G-2), loading dock and Destruct Room.

Materials used in this project are standard materials for the spaces being built. Major architectural portions of the project include:
Ceramic tile, resilient linoleum flooring, concrete floors, carpet, raised access floors, gypboard walls, sound absorbing wall panels, tackable wall panels, suspended ceilings, painted ceilings, door signs (adhesive back with Braille), exterior CMU block, stucco exterior, standing seam metal roofing.

The estimated performance of period is 24 months. Magnitude is $25M - $100M.

Traditional hard copies of plans and specifications will NOT be available for this project. Drawings and specifications will be made available for viewing and/or downloading on the Federal Business Opportunities (FedBizOpps) website at https://www.fbo.gov on or about April 28, 2015. An amendment to this notice will provide advance notice of the target pre-bid conference and site visit date.

It is the bidder's responsibility to check for any posted changes to the solicitation. Solicitation documents will not be issued on compact disc (CD) unless the Government determines that it is necessary. Bidders must have and/or maintain an active registration with the System for Award Management (SAM) website to be eligible for a Government contract award. To register in SAM, go to https://www.sam.gov. All Bidders are encouraged to visit the FedBizOpps website to view other business opportunities.

Files

File Type Posted
15b1-bid_abstract.pdf PDF
15b1_am8_10june15.pdf PDF
C2F-am8__27_10_00.pdf PDF
C2F-am7_09_69_13.pdf PDF
C2F_am7_EP_Plans.pdf PDF
C2F_am7_IG202.pdf PDF
C2F_am7_A-431.pdf PDF
C2F_am7_10_21_13.pdf PDF
C2F_am7_A-433.pdf PDF
C2F-am7_01_45_00.pdf PDF
C2F-am7__09_90_00.pdf PDF
C2F_am7_IN601.pdf PDF
C2F_am7_IG601.pdf PDF
C2F_am7_S-123.pdf PDF
15b1_am7_9june15.pdf PDF
C2F_am6_A-421.pdf PDF
C2F_am6_TS101.pdf PDF
C2F_am6_A-416.pdf PDF
15b1_am6_5june15.pdf PDF
C2F_am6_A-422.pdf PDF
C2F_am6_A-122.pdf PDF
C2F_am5_A-622.pdf PDF
C2F_am5_ES110.pdf PDF
C2F_am5_A-621.pdf PDF
C2F_am5_A-655.pdf PDF
C2F_am5__09_69_13.pdf PDF
15b1_am5_3june15.pdf PDF
C2F_am5_08_34_73.pdf PDF
C2F_am5_EP702.pdf PDF
C2F_am5_IN601.pdf PDF
15b1_am4_29may15.pdf PDF
15b1_am3_22may15.pdf PDF
Amend_2_-_01_57_20.pdf PDF
15b1_am2_21may15.pdf PDF
Amend_2_-_PH2_-_Electrical_Sheet.pdf PDF
Amend_2_-_PH2_-_Civil_Site_Sheets.pdf PDF
Amend_2_-_01_90_00.pdf PDF
15b1_am1_13may15.pdf PDF
Dwgs_V2_a2.pdf PDF
Dwgs_V1_a13.pdf PDF
Dwgs_V1_a1.pdf PDF
Dwgs_V1_a3.pdf PDF
Dwgs_V1_a4.pdf PDF
Dwgs_V4_a2.pdf PDF
Dwgs_V2_a7.pdf PDF
Dwgs_V4_a3.pdf PDF
Dwgs_V4_a10.pdf PDF
Specs_V2.pdf PDF
Dwgs_V4_a11.pdf PDF
Dwgs_V3_a1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

Notice history

Notice Type Posted
FY14 MCA PN67157 USARPAC Command and Control Facility (C2F) Phase 2, Fort Shafter, Oahu, Hawaii Latest Award Notice
This notice Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors