About this opportunity
This solicitation seeks proposals to repair HVAC systems at Building 2032 aboard Marine Corps Base Quantico in Virginia. The scope of work includes providing heating, cooling and ventilation load calculations and systems per UFC requirements, replacing existing HVAC equipment units with new units, upgrading zoning efficiency by consolidating existing ductwork, installing new wall thermostats, upgrading the boiler plant output to accommodate a new system configuration, and providing vibration isolators for new HVAC equipment. Offerors must submit proposals by February 2, 2022 for consideration by the Department of the Navy Naval Facilities Engineering Command. Evaluation criteria include the offeror's experience, past performance, technical approach, and pricing.
This opportunity is set aside for total small business concerns. The primary NAICS code is 238220 - Plumbing, Heating, and Air-Conditioning Contractors and the PSC code is R499. The period of performance is 320 calendar days from award. Work will be performed at Building 2032, Marine Corps Base Quantico, Quantico, VA 22134. The total estimated value is between $2-5 million to repair the HVAC systems as defined in the solicitation and associated documents.
Notice text
6 versions
Update #6 · Latest ·
Amendment 0005 is issued to provide (1) Answers to RFIs received; (2) Update Box 11 and 12b of Section 00 10 00 of the Solicitation.
****************************************************************************
Amendment 0004 is issued to extend the proposal due date and add a requirement for the bid bond as stated in Section 00 21 13- Instructions to Bidders, Paragraph B. 3)Tab 2 and in FAR Clause 52.228-1 of the RFP.
*****************************************************************************
Amendment 0003 is issued to provide (1) Answers to RFIs received; (2) Update Proposal Due Date
*****************************************************************************
Amendment 0002 is issued to provide updated Wage Determination, Answers RFIs, add Attachments F & G, and Extending Proposal Due Date.
****************************************************************************
Amendment 0001 Issued to provide a corrected Attachment E.
******************************************************************************
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Update #5 ·
Amendment 0004 is issued to extend the proposal due date and add a requirement for the bid bond as stated in Section 00 21 13- Instructions to Bidders, Paragraph B. 3)Tab 2 and in FAR Clause 52.228-1 of the RFP.
*****************************************************************************
Amendment 0003 is issued to provide (1) Answers to RFIs received; (2) Update Proposal Due Date
*****************************************************************************
Amendment 0002 is issued to provide updated Wage Determination, Answers RFIs, add Attachments F & G, and Extending Proposal Due Date.
****************************************************************************
Amendment 0001 Issued to provide a corrected Attachment E.
******************************************************************************
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Update #4 ·
Amendment 0003 is issued to provide (1) Answers to RFIs received; (2) Update Proposal Due Date
*****************************************************************************
Amendment 0002 is issued to provide updated Wage Determination, Answers RFIs, add Attachments F & G, and Extending Proposal Due Date.
****************************************************************************
Amendment 0001 Issued to provide a corrected Attachment E.
******************************************************************************
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Update #3 ·
Amendment 0002 is issued to provide updated Wage Determination, Answers RFIs, add Attachments F & G, and Extending Proposal Due Date.
****************************************************************************
Amendment 0001 Issued to provide a corrected Attachment E.
******************************************************************************
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Update #2 ·
Amendment 0001 Issued to provide a corrected Attachment E.
******************************************************************************
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Update #1 ·
The general scope of this project is to provide all labor, material, equipment, transportation and supervision
necessary to repair the HVAC systems at Bldg. 2032 aboard MCB Quantico, VA. The contractor shall
perform all work as necessary to complete the contract in a satisfactory and acceptable manner; and adhere to all
applicable federal, state and local regulations.
Work shall include the following, but not limited to:
Provide heating, cooling and ventilation rates, heating and cooling load calculations and systems per the latest UFC requirements. Provide new HVAC equipment units for in-kind replacements. Upgrade zoning efficiency by consolidating existing ductwork to meet new equipment manufacturers specifications and load calculation requirements. Provide new wall thermostat(s). Boiler(s) plant MBH output shall be upgraded to accommodate new system configuration and meet equipment manufacturer specifications. Provide vibration isolators/absorbers for new HVAC equipment.
Attachments
Show all 18
Notice history
| Notice | Type | Posted |
|---|---|---|
| Amendment 0005 Answer RFIs & Update Solicitation | Solicitation | |
| B2032 Repair HVAC Systems | Pre-Solicitation |