Washakie Submittal Register.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
UNITED STATES FOREST SERVICE, ROCKY MOUNTAIN REGION 2, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
Solicitation number
1240LU25R0008
Issued by

About this file

This is a submittal register template and example spreadsheet for a USFS road construction project that tracks required contractor submissions and government reviews. The file contains two sections: an example completed register showing various submittals like safety plans, schedules, and test reports with their submission/review dates, and a blank template register specifically for the Washakie Road Work LRT project on the Shoshone National Forest.

The register outlines required submissions including quality control plans, traffic control plans, erosion control plans, material testing reports, as-built drawings, and various construction material specifications and test data. Each submittal is classified for either government approval or acceptance, with tracking columns for submission dates, review dates, and approval status. The document notes that contractors must submit their initial register within 14 days of Notice to Proceed and maintain updates throughout the project duration, with monthly updates required at minimum.

View the file

Other files

File Type Posted
Amendment 0002 1240LU25R0008.pdf PDF
RFIs as of 25 February.pdf PDF
R2MATOC_Site Visit Attendees Summary.pdf PDF
Cottonwood SOI_AMEND0001.xlsx XLSX spreadsheet
Cottonwood_Plans_Part_1_Amend001.pdf PDF
Amendment 0001 1240LU25R0008.pdf PDF
Berry Creek TOPR_AMEND0001.pdf PDF
Washakie TOPR_Amend0001.pdf PDF
Washakie SOI.xlsx XLSX spreadsheet
Cottonwood TOPR Amend0001.pdf PDF
Cottonwood_Plans_Part_2_Amend0001.pdf PDF
Cottonwood Geotechnical Report_Amend0001.pdf PDF
RFIs as of 6 February.pdf PDF
Berry Creek Submittal Reg.xlsx XLSX spreadsheet
R2 Fire Plan.pdf PDF
Equipment Cleaning Form_Fillable_20241203.pdf PDF
Cottonwood Submittal Reg.xlsx XLSX spreadsheet
Washakie SOI.xlsx XLSX spreadsheet
Washakie TOPR.pdf PDF
Berry Creek FSSS.pdf PDF
Cottonwood Plans 2.pdf PDF
Cottonwood SOI.xlsx XLSX spreadsheet
Berry Creek TOPR.pdf PDF
Cottonwood FSSS.pdf PDF
Berry Creek SOI.xlsx XLSX spreadsheet
Washakie FSSS.pdf PDF
Washakie Food Storage Order.pdf PDF
Washakie Plans.pdf PDF
Berry Creek Plans.pdf PDF
Past Performance Questionnaire.docx DOCX document
Cottonwood TOPR.pdf PDF
1240LU25R0008 Region 2 Road and Bridge MATOC.pdf PDF
Cottonwood Plans 1.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Reqd All ITOPs

EXAMPLE ITOP SUBMITTAL REGISTERProject Title: EXAMPLE ITOPContract Number:
Project Location: FOREST NAME, DISTRICT, AND/OR NFSRContractor: EXAMPLE Contractor
TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT
Item NumberSpecification Section
and Pargraph Number / Table NumberDESCRIPTION OF ITEM SUBMITTED
(include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.)CLASSIFICATIONContractor SubmissionGovernment ReviewREVIEW REMARKS
Government ApprovalGovernment AcceptanceDate Submitted to Government (QC Review of Submittal Performed Prior to Submission)Date Submittal Returned to ContractorSubmittal Review Code

Approved/Disapproved Accepted/Not Accepted

1Section HHazardous Conditions Safety PlanX9/9/239/15/23Accepted
2Section HProgress ScheduleX9/9/239/16/23Approved
3Section HDesignation of RepresetnativesX9/9/239/16/23Approved
4FAR 52.222-11SF1413 - ABC Co.C24, XKJ Interprises, TSI LabsX9/9/239/16/23Accepted
5Section H or C???Fire Prevention and Control PlanX9/9/239/16/23Accepted
6Section HTemporary Traffic Control PlanX9/9/239/16/23Approved
OSHA 1926.65 (4)Site Specific Safety and Healthy PlanXDue prior to start of work on site
8Section HErosion Control PlanX9/9/239/16/23Approved
FP 109.01Measurement Notes and RecordsXDue within 24 hours of completeing work that is in-place and complete according to contract.
9FP 157.14Erosion Control Inspection ReportsX9/9/239/16/23Accepted
10FP 107.10 / Section HSpill Prevention and Control Countermeasures Plan (SPCCP)9/9/239/16/23AcceptedDue 2 days before beginning work
FP 107.10Hazardous Spill PlanXRequired when SPCCP is not required by contract. Due 2 days before beginning work.
11FP 153.03Quality Control PlanX9/9/239/16/23Approved
12FP 153.07 (b)Testing Control Charts, November 2023X12/5/2312/7/23Accepted
13FP 153.07 (b)Testing Control Charts, December 2023X1/5/241/8/24Accepted
14FP 153.07 (b)Testing Control Charts, January 2024X2/5/242/9/24Accepted
15FP 204-1Select Borrow Material, Source Classification, Gradation, Liquid LimitX10/1/2310/14/23Accepted
16FP 204-1Select Borrow Material, Production, Classification, Gradation, Liquid Limit, Moisture-densityX10/1/23Accepted
17FP 204-1Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 1-5X10/21/23Accepted
18FP 204-1Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 6-10X11/15/23Accepted
18.1FP 204-1Topping Material, Source, ClassificationX10/25/23Not AcceptedSoil classification shall be A-1 or A-2-4.
19FP 204-1Resubmit: Topping Material, Source, ClassificationX10/25/23Accepted
20FP 201-1Topping Material, Production, Moisture-Density, ProcessedX11/21/23Accepted
21FP 201-1Topping Material,Production, Density, In-placeX11/30/23Accepted
22FP 251-1Riprap Material, Class 1, SourceX10/1/23Accepted
23FP 251-1Riprap Material, Class 1, ProductionX12/5/23Accepted
24FP 251-1Riprap Material, Class 2, SourceX10/1/23Accepted
25FP 251-1Riprap Material, Class 2, ProductionX1/15/24Accepted
26FP 301-1Surface Course Aggregate, Commercial Source, LA Abbrasion, Soundness, Fractured Faces, LLX10/1/23Accepted
27FP 301-1Surface Course Aggregate, Commercial Source, Plasticity IndexX10/1/23Accepted
28FP 301-1Surface Course Aggregate, Production, GradationX12/15/23Accepted
29FP 301-1Surface Course Aggregate, Production, Moisture-density, Density, Moisture Content, Fractured FacesX12/15/23Accepted
30FP 602.06Plastic Pipe, Corrugated Polyethelene, 12", Manufacturer's InstructionsX10/1/23Accepted
30.1FP 708Plastic Pipe, Corrugated Polyethelene, 12", Product DataX10/1/23Accepted
32FP 208Cofferdams DrawingsX10/15/2310/25/23Approved
33FP 104.03 (b)As-built Drawings, FinalX1/31/242/10/24Approved

NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by the Individual Project Task Orders. The contractor shall submit the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project.

Page &P of &N

Inital Submittal Register

SUBMITTAL REGISTERProject Title: Washakie Road Work LRTContract Number:
Project Location: Shoshone National Forest, Washakie Ranger DistrictContractor:
TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT
Item NumberSpecification Section
and Paragraph Number / Table NumberDESCRIPTION OF ITEM SUBMITTED
(include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.)CLASSIFICATIONContractor SubmissionGovernment ReviewSUBMITTAL NOTES &

REVIEW REMARKS

Government ApprovalGovernment AcceptanceDate Submitted to Government
(QC Review of Submittal Performed Prior to Submission)Date Submittal Returned to ContractorSubmittal Review Code

Approved/Disapproved Accepted/Not Accepted

Section H, FAR 52.236-15 & SCRsSchedules for Construction ContractsX
FP 104.03 (c)As-built Drawings and Revisions LogXNote: Required before final inspection
FP 107.02 & SCRSpecial Equipment Cleaning Requirements Inspection ReportXNote: Use provided form
FP 152.05 (g)Culverts Survey DataX
FP 153.02Quality Control Manager & Testers Qualifications
X
FP 153.03Quality Control Plan
X
FP 153.07Control ChartsX
FP 153.07Quality Control and Construction Operations Reports
XNote: Submit daily reports for the week no later than the Monday following week
FP 156.03Traffic Control PlanXNote: Required 30 days before intended use
FP 157.04Soil Erosion and Sediment Control PlanX
FP 157.14Soil Erosion and Sediment Control Inspection ReportsX
FP 209, Table 209-1Source Backfill Material Classification & Gradation TestsX
FP 209, Table 209-1Source Bedding Material Classification & Gradation TestsX
FP 209, Table 209-1Production Backfill Material Moisture-Density & Density TestsX
FP 209, Table 209-1Production Bedding Material Moisture-Density & Density TestsX
FP 209, Table 209-1Production Bedding Material Classification & Gradation TestsX
FP 209, Table 209-1Production Backfill Material Classification & Gradation TestsX
FP 301 Table 301-1Source Aggregate Quality Test Reports (LA Abrasion, Soundness, Fractured Faces, LL)X
FP 301 Table 301-1Source Surface Aggregate: Gradation, Fractured Faces, PI (Commercial Source)X
FP 301 Table 301-1Production Surface Course Aggregate: GradationX
FP 301 Table 301-1Production Surface Course Aggregate: Moisture-density, Density, Moisture Content (in-place), Fractured FacesX
FP 707 [104.03 (a) (1)]Metal Pipe Certifications and Product DataX

GENERAL NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by the Task Orders. The contractor shall submit their proposed revisions to the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project as submittals are progressed. Update atleast monthly.