This is Amendment 0001 to solicitation 1240LU25R0008, issued by the USDA Forest Service CSA Intermountain office in Ogden, UT. The amendment extends the proposal due date to February 27, 2025 at 4:00 PM Mountain time.
The amendment makes several revisions, primarily to the Cottonwood portion of the work: updates to the Schedule of Items including changes to pay item descriptions and numbers for silt fence, waterlines, and conduit; addition of a geotechnical report; revisions to the TOPR including removal of key personnel requirements, updates to NTP timelines, period of performance, camping information, and bypass road expectations; and modifications to the plans including quantity table updates and removal of certain details. Similar updates were made to the Berry Creek TOPR (revised wage determination, removed key personnel) and Washakie TOPR. For Berry Creek, the amendment also changes Item 20501 Optional Rock Blasting from CY to LS units and quantity from 10 to 1.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LU25R0008
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LU
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 9
02/18/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/17/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment is to extend the due date and time to 27 February 2025 at
4:00 PM Mountain and to capture the following:
1. The Cottonwood Schedule of Items has been revised. See attached replacement file. The updated Schedule shall be used if submitting a price for Cottonwood. The summary of changes are:
a. 15702 Silt Fence Pay item description, unit, and quantity have been revised. Pay
Item 15702 is now a lump sum pay item with description Soil Erosion and Sediment Control.
b. 61102 pay item number for 2 inch waterline, galvanized is now pay item number
61102-01
c. 61102 pay item number for Temporary Bypass 2 inch water line, HDPE is now pay item
61102-02
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
PAUL C. LARSEN
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240LU25R0008/0001
d. 63650 pay item number for Conduit, 2 inches, Steel is now pay item 63650-01.
e. 63650 pay item number for Temporary Bypass 2 inch conduit, steel is now pay item 63650-02
f. 63310 Removing sign pay item has been deleted.
g. 63306 Object Markers, type III has been deleted
i. See attached replacement file Cottonwood SOI_Amend0001.xls
2. The file Cottonwood Geotechnical Report PDF has been added for reference.
3. The Cottonwood TOPR.pdf has been revised to:
a. Revise the solicitation number in the header
b. Revise the wage determination
c. Remove Key Personnel
d. Include information on NTP timelines.
e. Revise the Period of Performance
f. Clarify camping information
g. Revise the Bypass Road expectations
i. See attached replacement file: Cottonwood TOPR Amend0001.pdf
4. The Cottonwood Plans are revised as follows:
a. The Summary of Quantities Table has been replaced. Item 63310 and 63306 will be removed, item 15702 updated, items 63650 and 61102 are renumbered to be unique.
b. Sheet 4, notes 5 is deleted and call out for Silt Fence is deleted
c. Sheet 13, the Object Marker detail is deleted
d. Sheet 18, the Relocated Object Marker detail is deleted.
e. Sheet 18, note 15 is deleted
i. See attached replacement files:Cottonwood_Plans_Part_1_Amend0001.pdf &
Cottonwood_Plans_Part_2_Amend0001.pdf
5. The Berry Creek TOPR.pdf has been revised to:
a. Update the solicitation number in the header
b. Revise the wage determination
c. Remove key personnel
i. See attached replacement file: Berry Creek TOPR_Amend0001.pdf
6. On the Berry Creek Plans.pdf file, sheet 3/G-02, Estimate of Quantities Table, make a pen and ink change to Item No. 20501 Optional Item:
Rock Blasting to change the Unit from CY to LS
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240LU25R0008/0001
and the Estimated Quantities from 10 to 1.
7. The Washakie TOPR.pdf has been revised to:
a. Update the solicitation number in the header
b. Revise the wage determination
c. Remove key personnel
i. See attached replacement files: Washakie TOPR_Amend0001.pdf