Berry Creek Submittal Reg.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
UNITED STATES FOREST SERVICE, ROCKY MOUNTAIN REGION 2, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
Solicitation number
1240LU25R0008
Issued by

About this file

This is a submittal register template for road and bridge construction projects under a Forest Service MATOC contract, specifically showing required contractor submittals for the Berry Creek Culvert Replacement project on the White River National Forest. The register details approximately 50 required submittals including safety plans, quality control documentation, material testing reports, construction drawings, and environmental compliance documents.

Key submittal requirements include hazardous conditions safety plans, progress schedules, erosion control plans, quality control plans, material testing reports for aggregates and concrete, dewatering plans, traffic control plans, and as-built drawings. The template indicates specific timing requirements, such as submitting the quality control plan at the preconstruction conference, traffic control plans 30 days before intended use, and blasting plans 14 days before operations begin. The register is meant to be updated monthly and includes columns for tracking submission dates, government review status, and approval/acceptance documentation.

View the file

Other files

File Type Posted
Amendment 0002 1240LU25R0008.pdf PDF
RFIs as of 25 February.pdf PDF
R2MATOC_Site Visit Attendees Summary.pdf PDF
Cottonwood SOI_AMEND0001.xlsx XLSX spreadsheet
Cottonwood_Plans_Part_1_Amend001.pdf PDF
Amendment 0001 1240LU25R0008.pdf PDF
Berry Creek TOPR_AMEND0001.pdf PDF
Washakie TOPR_Amend0001.pdf PDF
Washakie SOI.xlsx XLSX spreadsheet
Cottonwood TOPR Amend0001.pdf PDF
Cottonwood_Plans_Part_2_Amend0001.pdf PDF
Cottonwood Geotechnical Report_Amend0001.pdf PDF
RFIs as of 6 February.pdf PDF
Washakie Submittal Register.xlsx XLSX spreadsheet
R2 Fire Plan.pdf PDF
Equipment Cleaning Form_Fillable_20241203.pdf PDF
Cottonwood Submittal Reg.xlsx XLSX spreadsheet
Washakie SOI.xlsx XLSX spreadsheet
Washakie TOPR.pdf PDF
Berry Creek FSSS.pdf PDF
Cottonwood Plans 2.pdf PDF
Cottonwood SOI.xlsx XLSX spreadsheet
Berry Creek TOPR.pdf PDF
Cottonwood FSSS.pdf PDF
Berry Creek SOI.xlsx XLSX spreadsheet
Washakie FSSS.pdf PDF
Washakie Food Storage Order.pdf PDF
Washakie Plans.pdf PDF
Berry Creek Plans.pdf PDF
Past Performance Questionnaire.docx DOCX document
Cottonwood TOPR.pdf PDF
1240LU25R0008 Region 2 Road and Bridge MATOC.pdf PDF
Cottonwood Plans 1.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Reqd All ITOPs

EXAMPLE ITOP SUBMITTAL REGISTERProject Title: EXAMPLE ITOPContract Number:
Project Location: FOREST NAME, DISTRICT, AND/OR NFSRContractor: EXAMPLE Contractor
TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT
Item NumberSpecification Section
and Pargraph Number / Table NumberDESCRIPTION OF ITEM SUBMITTED
(include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.)CLASSIFICATIONContractor SubmissionGovernment ReviewREVIEW REMARKS
Government ApprovalGovernment AcceptanceDate Submitted to Government (QC Review of Submittal Performed Prior to Submission)Date Submittal Returned to ContractorSubmittal Review Code

Approved/Disapproved Accepted/Not Accepted

1Section HHazardous Conditions Safety PlanX9/9/239/15/23Accepted
2Section HProgress ScheduleX9/9/239/16/23Approved
3Section HDesignation of RepresetnativesX9/9/239/16/23Approved
4FAR 52.222-11SF1413 - ABC Co.C24, XKJ Interprises, TSI LabsX9/9/239/16/23Accepted
5Section H or C???Fire Prevention and Control PlanX9/9/239/16/23Accepted
6Section HTemporary Traffic Control PlanX9/9/239/16/23Approved
OSHA 1926.65 (4)Site Specific Safety and Healthy PlanXDue prior to start of work on site
8Section HErosion Control PlanX9/9/239/16/23Approved
FP 109.01Measurement Notes and RecordsXDue within 24 hours of completeing work that is in-place and complete according to contract.
9FP 157.14Erosion Control Inspection ReportsX9/9/239/16/23Accepted
10FP 107.10 / Section HSpill Prevention and Control Countermeasures Plan (SPCCP)9/9/239/16/23AcceptedDue 2 days before beginning work
FP 107.10Hazardous Spill PlanXRequired when SPCCP is not required by contract. Due 2 days before beginning work.
11FP 153.03Quality Control PlanX9/9/239/16/23Approved
12FP 153.07 (b)Testing Control Charts, November 2023X12/5/2312/7/23Accepted
13FP 153.07 (b)Testing Control Charts, December 2023X1/5/241/8/24Accepted
14FP 153.07 (b)Testing Control Charts, January 2024X2/5/242/9/24Accepted
15FP 204-1Select Borrow Material, Source Classification, Gradation, Liquid LimitX10/1/2310/14/23Accepted
16FP 204-1Select Borrow Material, Production, Classification, Gradation, Liquid Limit, Moisture-densityX10/1/23Accepted
17FP 204-1Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 1-5X10/21/23Accepted
18FP 204-1Select Borrow Material, Production, Density, In Place, Sta. 1+50- 2+50, Layer 6-10X11/15/23Accepted
18.1FP 204-1Topping Material, Source, ClassificationX10/25/23Not AcceptedSoil classification shall be A-1 or A-2-4.
19FP 204-1Resubmit: Topping Material, Source, ClassificationX10/25/23Accepted
20FP 201-1Topping Material, Production, Moisture-Density, ProcessedX11/21/23Accepted
21FP 201-1Topping Material,Production, Density, In-placeX11/30/23Accepted
22FP 251-1Riprap Material, Class 1, SourceX10/1/23Accepted
23FP 251-1Riprap Material, Class 1, ProductionX12/5/23Accepted
24FP 251-1Riprap Material, Class 2, SourceX10/1/23Accepted
25FP 251-1Riprap Material, Class 2, ProductionX1/15/24Accepted
26FP 301-1Surface Course Aggregate, Commercial Source, LA Abbrasion, Soundness, Fractured Faces, LLX10/1/23Accepted
27FP 301-1Surface Course Aggregate, Commercial Source, Plasticity IndexX10/1/23Accepted
28FP 301-1Surface Course Aggregate, Production, GradationX12/15/23Accepted
29FP 301-1Surface Course Aggregate, Production, Moisture-density, Density, Moisture Content, Fractured FacesX12/15/23Accepted
30FP 602.06Plastic Pipe, Corrugated Polyethelene, 12", Manufacturer's InstructionsX10/1/23Accepted
30.1FP 708Plastic Pipe, Corrugated Polyethelene, 12", Product DataX10/1/23Accepted
32FP 208Cofferdams DrawingsX10/15/2310/25/23Approved
33FP 104.03 (b)As-built Drawings, FinalX1/31/242/10/24Approved

NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by the Individual Project Task Orders. The contractor shall submit the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project.

Page &P of &N

Inital Submittal Register

SUBMITTAL REGISTERProject Title: Berry Creek Culvert ReplacementContract Number:
Project Location: White River National Forest, Holy Cross Ranger District, NFSR 774Contractor:
TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT
Item NumberSpecification Section
and Paragraph Number / Table NumberDESCRIPTION OF ITEM SUBMITTED
(include if it is shop drawings, plans, product data, manufacturer's instructions, samples, test reports, certifications, etc.)CLASSIFICATIONContractor SubmissionGovernment ReviewSUBMITTAL NOTES &

REVIEW REMARKS

Government ApprovalGovernment AcceptanceDate Submitted to Government
(QC Review of Submittal Performed Prior to Submission)Date Submittal Returned to ContractorSubmittal Review Code

Approved/Disapproved Accepted/Not Accepted

FP 104.03 (c)As-built Drawings and Revisions LogXNote: Required before final inspection
FP 107.02 & SCRSpecial Equipment Cleaning Requirements Inspection ReportXNote: Use provided form
FP 107.10Spill Prevention, Control, & Countermeasure PlanX
FP 151Access Road Improvements PlanX
FP 152.03AMG Method Technology Statement, Personnel Qualifications, Contractor Quality Control PlanXNote: Required a the preconstruction conference
FP 152.05 (g)Culverts Survey DataX
FP 153.02Quality Control Manager & Testers Qualifications
X
FP 153.03Quality Control Plan
X
FP 153.07Control ChartsX
FP 153.07Quality Control and Construction Operations Reports
XNote: Submit daily reports for the week no later than the Monday following week
FP 156.03Traffic Control PlanXNote: Required 30 days before intended use
FP 157.04Soil Erosion and Sediment Control PlanX
FP 157.14Soil Erosion and Sediment Control Inspection ReportsX
FP 205.04Blaster QualificationsXNote: Required 14 days before drilling and blasting operations begin.
FP 205.05General Blasting PlanXNote: Required 14 days before drilling and blasting operations begin.
FP 205.05Site Specific Blasting PlansXNote: Required 14 days before drilling and blasting operations begin.
FP 205.06Pre-blast Condition Survey RecordsXNote: If optional item for blasting is exercised. Required 3 days following last blast
FP 205.09 (a)Post-blast ReportXNote: If optional item for blasting is exercised.
FP 205.09 (b)Vibration and Air-blasting ReportXNote: If optional item for blasting is exercised. Required 3 days following last blast
FP 205.09 (c)Close-out StatementXNote: If optional item for blasting is exercised.
FP 208 Table 208-1Foundation Fill Classification and Gradation Source Test ReportsX
FP 208 Table 208-1Foundation Fill Moisture-Density and Density Production Test ReportsXNote: Density in place reports are required for each layer, before placing next layer.
FP 208 Table 208-1Structural Backfill Moisture-Density and Density Production Test ReportsXNote: Density in place reports are required for each layer, before placing next layer.
FP 208 Table 208-1Structural Backfill Moisture-Density and Density Source Test ReportsX
FP 208..05 & 07 & 648.07Dewatering Plan, Cofferdams, Drawings, and Construction DetailsX
FP 208.03Excavation Sloping DesignX
FP 301 Table 301-1Aggregate Quality Source Test Reports (LA Abrasion, Soundness, Fractured Faces, LL)X
FP 301 Table 301-1Surface Aggregate Source PI (Commercial Source)X
FP 301 Table 301-1Surface Course Aggregate Production Gradation, PIX
FP 301 Table 301-1Surface Course Aggregate Production Moisture-density, Density, Moisture Content (in-place), Fractured FacesX
FP 301 Table 301-1Surface course Surface Tolerance & Grade ReportX
FP 301.02Material Submittals (105.01) & Commercial Certifications [106.03 (b)]XNote: Material submittals are applicable to materials required for project. They can be submitted under the technical spec division number or under the 700 Material section.
FP 301.03Aggregate Sieve Size Target Values and Aggregate SampleXNote: Required 12 days before incorporating aggregate into the work.
FP 552 / 104.03 (b) (1)Forms and Falsework Drawings (if electing to Cast-in-Place )XNote: Required if electing to Cast-in-Place
FP 552 Table 552-9 & FP 590Aggregate Production Test Reports (Gradation, Fineness, Moisture)X
FP 552 Table 552-9 & FP 590Concrete Compressive Strength Test ReportsX
FP 552 Table 552-9 & FP 590Concrete Production Test Reports (Density, Air, Slump, Temperature)X
FP 552 Table 552-9 FP 590Aggregate Source Test ReportsX
FP 552.03 & FP 590Structural Concrete Mix DesignXNote: Required 36 days prior to production. Use FHWA Form 1608
FP 552.09 & FP 590Quality Control of MixX
FP 552.10 & FP 590Hot and Cold Weather Concrete PlansXNote: These should be submitted if there is any potential for concrete placement or curing in hot or cold weather concreting conditions as per ACI and FP.
FP 552.20 & FP 590Cementitious Material CertificatesX
FP 554.02Material Submittals (105.01) & Commercial Certifications [106.03 (b)]X
FP 554.03Resteel Order ListsX
FP 590 / FP 104.03 (b) (1)Precast Fabrication and Installation DrawingsX
FP 590.02Material Submittals (105.01) & Commercial Certifications [106.03 (b)]XNote: Material submittals are applicable to materials required for project. They can be submitted under the technical spec division number or under the 700 Material section.
FP 603.02Material Submittals (105.01) & Commercial Certifications [106.03 (b)]XNote: Material submittals are applicable to materials required for project. They can be submitted under the technical spec division number or under the 700 Material section.
FP 603.03Structural Plate Arch, Headwalls, Wingwalls, and Tie Backs Design Drawings/Shop Drawings, Details, &CalculationsX
FP 603.04Structural Plate Arch Manufacturer's Assembly Instructions and SpecificationsXNote: Required before assembly
FP 648.02Material Submittals (105.01) & Commercial Certifications [106.03 (b)]XNote: Material submittals are applicable to materials required for project. They can be submitted under the technical spec division number or under the 700 Material section.
Section H, FAR 52.236-15 & SCRsSchedules for Construction ContractsX

GENERAL NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by the Task Orders. The contractor shall submit their proposed revisions to the initial submittal register to the CO within 14 days of Notice to Proceed and shall update the submittal register through the project as submittals are progressed. Update at least monthly.

Page &P of &N