COMBINED.pdf

PDF 3 MB Posted

Attached to
REPAIR BUILDING ENVELOPE, BUILDING 1 Federal contract opportunity
Solicitation number
W91SMC-15-R-0005
Issued by
Department of the Army Illinois Army National Guard

About this file

Not Listed

View the file

Other files for this federal contract opportunity

Other files attached to REPAIR BUILDING ENVELOPE, BUILDING 1, newest first.
File Type Posted
RFI_2_Clarification_Repair_Building_Envelope _P-1.pdf PDF
RFI_2_Repair_Building_Envelope _P-1.pdf PDF
Exhibit_C1__Past_Performance_Questionaire.pdf PDF
Exhibit_C__info_FormsSSS__SA_and_UR_Mar_2013.pdf PDF
Soils_Exploration_Report_-_Bldg_1_Envelope.pdf PDF
RFI_1_Repair_Building_Envelope _P-1.pdf PDF
Site_Visit_Minutes_23_Jun_15.pdf PDF
Site_Visit_Sign-In_23_Jun_15.pdf PDF
Preproposal_slides_P1_Hangar_23_Jun_15.pdf PDF
W91SMC-15-R-0005-0001_Repair_Building_Envelope _P-1.pdf PDF
Site_Visit_Sign-in_18_JUNE_2015.pdf PDF
Preproposal_slides_P1_Hangar.pdf_18_June.pdf PDF
Site_Visit_Minutes_18_JUNE.pdf PDF
01_35_26.pdf PDF
02_82_14.00_10.pdf PDF
01_20_00.00_20.pdf PDF
01_73_29.pdf PDF
Amend_01.pdf PDF
01_22_00.pdf PDF
02_82_33.13_20.pdf PDF
01_21_00.pdf PDF
01_00_00.pdf PDF
SITE_VISIT.pdf PDF
SPECIFICATIONS_Section_012100-Allowances.pdf PDF
Combined Drawings.pdf PDF
Combined Drawings.pdf PDF
Combined Drawings.pdf PDF
EXHIBIT_B_consent_form__SSS_SA_and_UR_May_13.pdf PDF
Exhibit_C1__Past_Performance_Questionaire.pdf PDF
Exhibit_C__info_FormsSSS__SA_and_UR_Mar_2013.pdf PDF
EXHIBIT_F_Proposal_Inquiry_Format.pdf PDF
EXHIBIT_A_relevancy_SSS_SA_and_UR_Mar_13.pdf PDF
Combined Drawings.pdf PDF
W91SMC-15-R-0005_Repair_Building_Envelope _P1.pdf PDF
Sole_Source_Justification_Advantor-REDACTED.pdf PDF
Sole_Source_Justification_TAC_Direct_Digital_Controls_DDC-REDACTED.pdf PDF
BRAND_NAME_Justification_Best_Locks-REDACTED.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SAIC Energy, Environment & Infrastructure, LLC 622 Emerson Road, Suite 600 | St. Louis, MO 63141-6728 tel: 314.821.7017 | fax: 314.821.8499 | saic.com/EEandI SAIC Project Number 6150930331

183d FIGHTER WING (ACC)

ABRAHAM LINCOLN CAPITAL AIRPORT

SPRINGFIELD, ILLINOIS

ILLINOIS AIR NATIONAL GUARD

REPAIR BUILDING ENVELOPE, P-1 HANGAR

Contract Number: W90FYQ-09-D-0006-9E07 Project Number: DCFT092011

Type B-3 Final Submittal

SPECIFICATIONS

04 April 2014

THIS PAGE INTENTIONALLY LEFT BLANK

This Page Intentionally Left Blank

Illinois Air National Guard Repair Building Envelope, P-1 Hangar Abraham Lincoln Capital Airport Project No. DCFT092011 Springfield, Illinois W90FYQ-09-D-0006-9E07

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

012500 SUBSTITUTION PROCEDURES

012600 CONTRACT MODIFICATION PROCEDURES

013100 PROJECT MANAGEMENT AND COORDINATION

013200 CONSTRUCTION PROGRESS DOCUMENTATION

013300 SUBMITTAL PROCEDURES

013543 ENVIRONMENTAL PROTECTION

014000 QUALITY REQUIREMENTS

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015639 TEMPORARY TREE AND PLANT PROTECTION

016000 PRODUCT REQUIREMENTS

017300 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

017900 DEMONSTRATION AND TRAINING

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

042200 CONCRETE UNIT MASONRY

047200 CAST STONE MASONRY

DIVISION 05 - METALS

051200 STRUCTURAL STEEL FRAMING

053100 STEEL DECKING

054000 COLD-FORMED METAL FRAMING

055000 METAL FABRICATIONS

055213 PIPE RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061053 MISCELLANEOUS ROUGH CARPENTRY

061600 SHEATHING

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

070150.19 PREPARATION FOR REROOFING

04 April 2014 TABLE OF CONTENTS Type B-3 Final - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07

072100 THERMAL INSULATION

072419 WATER-DRAINAGE EXTERIOR INSULATION AND FINISH SYSTEM (EIFS)

072726 FLUID-APPLIED MEMBRANE AIR BARRIERS

074113.16 STANDING-SEAM METAL ROOF PANELS

074213.19 INSULATED METAL WALL PANELS

075419 POLYVINYL-CHLORIDE (PVC) ROOFING

075423 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

076200 SHEET METAL FLASHING AND TRIM

077253 SNOW GUARDS

079200 JOINT SEALANTS

DIVISION 08 - OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

083323 OVERHEAD COILING DOORS

083613 SECTIONAL DOORS

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

084523 FIBERGLASS-SANDWICH-PANEL ASSEMBLIES

087100 DOOR HARDWARE

088000 GLAZING

089119 FIXED LOUVERS

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING

092900 GYPSUM BOARD

096723 RESINOUS FLOORING

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

DIVISION 12 - FURNISHINGS

122113 HORIZONTAL LOUVER BLINDS

123661 WINDOW SILLS

DIVISION 13 - SPECIAL CONSTRUCTION

133423 FABRICATED STRUCTURES

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

230519 METERS AND GAGES FOR HVAC PIPING

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230700 HVAC INSULATION

230900 INSTRUMENTATION AND CONTROL FOR HVAC

Type B-3 Final - 2

232300 REFRIGERANT PIPING

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233713 DIFFUSERS, REGISTERS, AND GRILLES

238126 SPLIT-SYSTEM AIR-CONDITIONERS

238239 UNIT HEATERS

DIVISION 26 - ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING

260548 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

260923 LIGHTING CONTROL DEVICES

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

262913 ENCLOSED CONTROLLERS

264113 LIGHTNING PROTECTION FOR STRUCTURES

265100 INTERIOR LIGHTING

DIVISION 31 - EARTHWORK

311000 SITE CLEARING

312000 EARTH MOVING

DIVISION 32 - EXTERIOR IMPROVEMENTS

321313 CONCRETE PAVING

321373 CONCRETE PAVING JOINT SEALANTS

329200 TURF AND GRASSES

END OF TABLE OF CONTENTS

Type B-3 Final - 3

Springfield, Illinois W90FYQ-09-D-0006-9E07

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and drawing conventions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Government facilities.

1.2 PROJECT INFORMATION

A. Project Identification: Repair Building Envelope, Bldg 1.

1. Project Number: DCFT092011.

2. Project Location: Abraham Lincoln Capital Airport, Springfield, Illinois.

3. Contracting Officer: Jason Robbins, CIV.

NGIL-PFO P&C

1301 N. Macarthur Blvd.

Springfield, IL 62702

(217) 761-3450

4. Architect/ Engineer: SAIC Engineering, LLC 622 Emerson Road Suite 600 St. Louis, MO 63141

(314) 821-7017

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. This project will replace the existing heating and air conditioning system for Building 1 and upgrade the existing building envelope including all exterior doors and windows. The existing hangar door will be replaced to create an energy efficient and functional solution for Centralized Repair Facility (CRF) operations. The existing site access and utilities will be updated to accommodate user requirements. Interior spaces will be repaired as necessary as a result of

04 April 2014 SUMMARY Type B-3 Final 011000 - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07 exterior and HVAC improvements. This Project will be executed in two phases. The Government will occupy the remainder of the building not under construction.

B. The second phase of the Project will require a temporary wall be built to isolate the engine maintenance bay from the outdoors during construction of the new exterior wall.

C. Type of Contract.

1. Project will be constructed under a single prime contract.

1.4 PHASED CONSTRUCTION

A. The Work shall be conducted in two phases, with each phase substantially complete as indicated:

1. Phase 1 North and East Wings: Work of this phase shall commence within 10 days after Notice to Proceed and be substantially complete and ready for within 150 days after commencement of construction of this phase. Government shall use and possess Phase I during Phase II work.

2. Phase 2: The remaining Work shall be substantially complete and ready for occupancy at time of Substantial Completion for the Work. Start of Phase II work shall be (2) weeks after final inspection of Phase I work.

B. The contractor shall notify the contracting officer in writing no fewer than 15 working days prior to the Contractors intent to commence the next phase of work to allow the government sufficient time to accommodate the contractor’s construction operations.

1. Failure of the contractor to notify the contracting officer in writing as stated above shall not result in a change in the contract sum or schedule or result in future delay claims.

C. Before commencing Work of each phase, submit and receive approval of an updated copy of Contractor's construction schedule showing the sequence, commencement and completion dates, and move-out and -in dates of Government’s personnel for all phases of the Work.

Contractor must also submit and receive approval for completed punchlist items for previous phase before starting following phase.

1.5 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated by the Contracting Officer’s Representative and as indicated by requirements of this Section.

B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to those indicated in the contract documents.

2. In the case that the contractor requires construction operations outside of the limits indicated in the contract documents, the contractor shall notify the contracting officer in

Type B-3 Final 011000 - 2

Springfield, Illinois W90FYQ-09-D-0006-9E07 writing no less than 10 working days prior to commencement of work to allow the government sufficient time to accommodate the contractors request.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.6 COORDINATION WITH OCCUPANTS

A. Partial Occupancy: Government personnel will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Contracting Officer’s Representative during construction operations to minimize conflicts and facilitate usage.

Perform the Work so as not to interfere with ongoing operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer’s Representative and authorities having jurisdiction.

2. Provide not less than 72 hours’ notice to Contracting Officer’s Representative of activities that will affect facilities operations.

B. Limited Occupancy of Completed Areas of Construction: Contracting Officer’s Representative reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Obtain a Use and Possession notice from authorities having jurisdiction before limited occupancy.

2. Before limited occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Contracting Officer’s Representative will operate and maintain mechanical and electrical systems serving occupied portions of Work.

3. On occupancy, Contracting Officer’s Representative will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.7 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 5:00pm p.m., Monday through Thursday and 7:00a.m. to 12:00 p.m. Friday, unless otherwise indicated. No work shall be performed on Government holidays or down Fridays, unless otherwise indicated.

Type B-3 Final 011000 - 3

Springfield, Illinois W90FYQ-09-D-0006-9E07

1. Interruption to the Government occupied spaces may have to be done outside normal business working hours, and must be coordinated and approved by Contracting Officer’s Representative prior to executing such work with interruption, approved by Contracting Officer’s Representative.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Contracting Officer or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Contracting Officer’s Representative not less than three working days in advance of proposed utility interruptions.

2. Obtain Contracting Officer's Representative written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to occupancy with Contracting Officer’s Representative.

This includes cutting concrete and penetrating CMU walls.

1. Notify Contracting Officer’s Representative not less than three days in advance of proposed disruptive operations.

2. Obtain Contracting Officer's Representative written permission before proceeding with disruptive operations.

E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

F. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

Type B-3 Final 011000 - 4

Springfield, Illinois W90FYQ-09-D-0006-9E07

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Type B-3 Final 011000 - 5

Springfield, Illinois W90FYQ-09-D-0006-9E07

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use PFOIL 342 – clearly marked “SUBSTITUTION” in bold on both front and back page. Include original salient characteristics and how proposed substitution meets or exceeds each point.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Contracting Officer and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

04 April 2014 SUBSTITUTION PROCEDURES Type B-3 Final 012500 - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Contracting Officer will notify Contractor acceptance or rejection of proposed substitution within 30 calendar days of receipt of request.

a. Forms of Acceptance: Change Order or Contracting Officer’s Supplemental Instructions for minor changes in the Work.

b. Use product specified if Contracting Officer does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 working days prior to time required for preparation and review of related submittals.

1. Conditions: Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Requested substitution will not adversely affect Contractor's construction schedule.

c. Requested substitution has received necessary approvals of authorities having jurisdiction.

Type B-3 Final 012500 - 2

Springfield, Illinois W90FYQ-09-D-0006-9E07

d. Requested substitution is compatible with other portions of the Work.

e. Requested substitution has been coordinated with other portions of the Work.

f. Requested substitution provides specified warranty.

g. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Not allowed.

PART 3 - EXECUTION (Not Used)

END OF SECTION 012500

Type B-3 Final 012500 - 3

Springfield, Illinois W90FYQ-09-D-0006-9E07

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

1.2 MINOR CHANGES IN THE WORK

A. Contracting Officer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions."

1.3 PROPOSAL REQUESTS

A. Contracting Officer-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Contracting Officer are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use Cost Estimate Breakout form provided by Government.

B. Contractor-Initiated Work Change Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a proposal by submitting a request for a change to the Contracting Officer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

04 April 2014 CONTRACT MODIFICATION PROCEDURES Type B-3 Final 012600 - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Work Change Proposal Request Form: Use Cost Estimate Breakdown form provided by the Government, "Proposal Worksheet Summary," and Form 13.6C, "Proposal Worksheet Detail."

1.4 CHANGE ORDER PROCEDURES

A. On Contracting Officer's approval of a Work Changes Proposal Request, Contracting Officer will issue a Change Order for signatures of Contracting Officer and Contractor on SF30 Modification.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012600

04 April 2014 CONTRACT MODIFICATION PROCEDURES Type B-3 Final 012600 - 2

Springfield, Illinois W90FYQ-09-D-0006-9E07

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings.

2. Requests for Information (RFI).

3. Project meetings.

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 DEFINITIONS

A. RFI: Request for Information from Contractor seeking information or clarifications of the Contract Documents from the A&E and Government.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use CSI Form 1.5 or equal. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

04 April 2014 PROJECT MANAGEMENT AND COORDINATION Type B-3 Final 013100 - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Contracting Officer and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

9. Commissioning.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid.

Type B-3 Final 013100 - 2

Springfield, Illinois W90FYQ-09-D-0006-9E07

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Review: Contracting Officer will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.

1.6 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Contracting Officer will return RFIs submitted to Contracting Officer by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: Format acceptable to the Contracting Officer.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Allow 15 calendar days for Contracting Officer’s response for each RFI.

Type B-3 Final 013100 - 3

Springfield, Illinois W90FYQ-09-D-0006-9E07

RFIs received by Contracting Officer after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Contracting Officer’s actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer’s action may include a request for additional information, in which case Contracting Officer’s time for response will date from time of receipt of additional information.

3. Contracting Officer’s action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Contracting Officer in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Use format acceptable to the Contracting Officer. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Contracting Officer.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Contracting Officer’s response was received.

F. On receipt of Contracting Officers action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven calendar days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, or Proposal Request, as appropriate.

1.7 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

Type B-3 Final 013100 - 4

Springfield, Illinois W90FYQ-09-D-0006-9E07

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Contracting Officer, within three days of the meeting.

B. Preconstruction Conference: Before starting construction, the Contracting Officer will set the date, time, and location of the meeting.

1. Attendees: Authorized representatives of Contracting Officer, Contracting Officer’s Commissioning Authority, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference.

Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Procedures for processing field decisions and Change Orders.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of record documents.

l. Use of the premises and existing building.

m. Work restrictions.

n. Working hours.

o. Contracting Officer's occupancy requirements.

p. Responsibility for temporary facilities and controls.

q. Procedures for moisture and mold control.

r. Procedures for disruptions and shutdowns.

s. Construction waste management and recycling.

t. Parking availability.

u. Office, work, and storage areas.

v. Equipment deliveries and priorities.

w. First aid.

x. Security.

y. Progress cleaning.

3. Minutes: The Government will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Contracting Officer and Contracting Officer's Commissioning Authority of scheduled meeting dates.

Type B-3 Final 013100 - 5

Springfield, Illinois W90FYQ-09-D-0006-9E07

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility problems.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings twice a month at biweekly intervals.

1. Attendees: In addition to representatives of the Contracting Officer, Contracting Officer’s Commissioning Authority, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction

Type B-3 Final 013100 - 6

Springfield, Illinois W90FYQ-09-D-0006-9E07 behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Progress cleaning.

10) Quality and work standards.

11) Status of correction of deficient items.

12) Field observations.

13) Status of RFIs.

14) Status of proposal requests.

15) Pending changes.

16) Status of Change Orders.

17) Pending claims and disputes.

18) Documentation of information for payment requests.

3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

Type B-3 Final 013100 - 7

Springfield, Illinois W90FYQ-09-D-0006-9E07

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's construction schedule.

2. Construction schedule updating reports.

3. Daily construction reports.

4. Site condition reports.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

D. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Contracting Officer or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

1.3 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF electronic file.

B. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.

04 April 2014 CONSTRUCTION PROGRESS DOCUMENTATION Type B-3 Final 013200 - 1

Springfield, Illinois W90FYQ-09-D-0006-9E07

C. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

1. Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.

D. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

4. Earnings Report: Compilation of Contractor's total earnings from the Notice to Proceed until most recent Application for Payment.

E. Construction Schedule Updating Reports: Submit with Applications for Payment.

F. Daily Construction Reports: Submit at weekly intervals.

G. Site Condition Reports: Submit at time of discovery of differing conditions.

1.4 COORDINATION

A. Coordinate Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

Type B-3 Final 013200 - 2

Springfield, Illinois W90FYQ-09-D-0006-9E07

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Contracting Officer.

2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

3. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's construction schedule with submittal schedule.

4. Startup and Testing Time: Include no fewer than 15 days for startup and testing.

5. Substantial Completion: Indicate completion in advance of date established for

Substantial Completion, and allow time for Contracting Officer’s administrative procedures necessary for certification of Substantial Completion.

6. Punch List and Final Completion: Include not more than 30 days for completion of punch list items and final completion.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase.

2. Work under More Than One Contract: Include a separate activity for each contract.

3. Work by Contracting Officer: Include a separate activity for each portion of the Work performed by Contracting Officer.

4. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Limitations of continued occupancies.

c. Uninterruptible services.

d. Partial occupancy before Substantial Completion.

e. Use of premises restrictions.

f. Provisions for future construction.

g. Seasonal variations.

h. Environmental control.

5. Work Stages: Indicate important stages of construction for each major portion of the Work.

D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.

E. Progress Schedule Documentation: Schedule shall be updated in (2) week increments, at approximately the 15th calendar day and end of each month. Schedule update shall show both percentage of work completed for each work element and the total work for that period, as well as the planned amounts for each element and total. In addition, a separate row shall show both the actual and planned cumulative total of work by percentage, for each two week period, adding up to a total of 100% of the original contract amount. Format to be Excel spreadsheet or approved equal. It is suggested that the Contractor break large work elements into materials and labor for separate tracking.

F. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:

Type B-3 Final 013200 - 3

Springfield, Illinois W90FYQ-09-D-0006-9E07

1. Unresolved issues.

2. Unanswered Requests for Information.

3. Rejected or unreturned submittals.

4. Notations on returned submittals.

5. Pending modifications affecting the Work and Contract Time.

G. Recovery Schedule: When periodic update indicates the Work is 14 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule.

H. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.

1. Use Microsoft Project for Windows 7 operating system.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type or approved equal, Contractor's construction schedule within 30 days of date established for the Notice to Proceed.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1. For construction activities that require three months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.

2.3 REPORTS

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. List of separate contractors at Project site.

3. Approximate count of personnel at Project site.

4. Equipment at Project site.

5. Material deliveries.

6. High and low temperatures and general weather conditions, including presence of rain or snow.

7. Accidents.

8. Meetings and significant decisions.

9. Unusual events.

10. Stoppages, delays, shortages, and losses.

11. Meter readings and similar recordings.

12. Emergency procedures.

13. Orders and requests of authorities having jurisdiction.

14. Change Orders received and implemented.

15. Services connected and disconnected.

16. Equipment or system tests and startups.

Type B-3 Final 013200 - 4

Springfield, Illinois W90FYQ-09-D-0006-9E07

17. Partial completions and occupancies.

18. Substantial Completions authorized.

B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule Updating: A copy at the Schedule of Values for month end shall be submitted with each invoice and must match value of work shown as completed, regardless of actual amount invoiced. An updated copy of the Progress Schedule shall also be provided at mid-month and end-of-month in sufficient detail to support the Progress Report totals indicated by work element.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate final completion percentage for each activity.

B. Distribution: Distribute copies of approved schedule to Contracting officer, separate contractors, testing and inspecting agencies, and…