About this file

Solicitation

View the file

Other files

File Type Posted
A21_W91QVN19R01840001.pdf PDF
209625_TITLE.pdf PDF
214261_STRUCTURAL-1.pdf PDF
209625_ARCH-2.pdf PDF
209625_MECH-2.pdf PDF
A02_214261_CONST-OFFICE-FIRE-STATION-K16-256_MMTL-ARCH.xlsx XLSX spreadsheet
214261_TITLE_R1.pdf PDF
214261_CIVIL-1.pdf PDF
A02_209625_CONST-BAYS-FIRE-STATION-K16-256_MMTL-CIVIL.xlsx XLSX spreadsheet
214261_ELEC_1.pdf PDF
214261_ARCH-2.pdf PDF
A02_209625_CONST-BAYS-FIRE-STATION-K16-256_MMTL-MECH.xlsx XLSX spreadsheet
A02_209625_CONST-BAYS-FIRE-STATION-K16-256_MMTL-ARCH.xlsx XLSX spreadsheet
209625_STRUC-2.pdf PDF
214261_ELEC_3.pdf PDF
214261_CIVIL-2.pdf PDF
209625_ELEC.PDF PDF
209625_STRUC-1.pdf PDF
A02_214261_CONST-OFFICE-FIRE-STATION-K16-256_MMTL-MECH.xlsx XLSX spreadsheet
214261_ARCH-3.pdf PDF
214261_ARCH-1.pdf PDF
A02_209625_CONST-BAYS-FIRE-STATION-K16-256_MMTL-ELEC.xlsx XLSX spreadsheet
214261_STRUCTURAL-2.pdf PDF
214261_STRUCTURAL-3.pdf PDF
214261_ELEC_2.pdf PDF
A02_214261_CONST-OFFICE-FIRE-STATION-K16-256_MMTL-CIVIL.xlsx XLSX spreadsheet
214261_MECH-2.pdf PDF
209625_STRUC-3.pdf PDF
214261_MECH-1.pdf PDF
A02_214261_CONST-OFFICE-FIRE-STATION-K16-256_MMTL-STRU.xlsx XLSX spreadsheet
209625_ARCH-1.pdf PDF
A02_214261_CONST-OFFICE-FIRE-STATION-K16-256_MMTL-ELEC.xlsx XLSX spreadsheet
A02_209625_CONST-BAYS-FIRE-STATION-K16-256_MMTL-STRU.xlsx XLSX spreadsheet
209625_MECH-1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE SCHEDULE

A. This is a Non-Work Plan Task Order for the follow ing MATOC Contractors only. Contract Numbers W91QVN-18-D-0021, 0022, 0023, 0025, 0026, 0027, 0028, 0030, 0031, 0042, 0044, 0045, 0046, 0050, 0051, and 0162.

B. Site Visit: All MATOC offerors w ho intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit clause in Section L for Schedule.

C. If the Contractor is unable to submit the proposal in response to this RFP, the Contractor shall submit the “No-Offer Letter” by date and time specif ied in this solicitation.

MS KWON, HYEUN 315-755-0649

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

17-Jun-2019

(RFP)

(IFB)

X

CALL:

Construct bays, off ices, and dormitory for new fire station, S-256, K-16

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______180 calendar days and complete it w ithin ________10 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________09 Jul 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______240 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

CONSTRUCTION & SUPPLY DIV, UNIT #15289

APO AP 96271

UNITED STATES

W91QVN

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

209625 & 214261

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W91QVN19R0184 38

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W91QVN19R0184

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Construct Offices and Dormitory

FFP

Phase 1 Work Class: K Construct Offices and Dormitory, S-256, K-16

PWO #214261

FOB: Destination

PURCHASE REQUEST NUMBER: 0011317997-0001

PSC CD: 5670

NET AMT

0002 1 Job Construct Offices and Dormitory

FFP

Phase 1 Work Class: L Construct Offices and Dormitory, S-256, K-16

PWO #214261

FOB: Destination

PURCHASE REQUEST NUMBER: 0011317997-0001

0003 1 Job Construct Bays for New Fire Station

FFP

Phase 2 Work Class: L Construct Bays for New Fire Station, S-256, K-16

PWO #209625

FOB: Destination

PURCHASE REQUEST NUMBER: 0011353643

Section C - Descriptions and Specifications

STATEMENT OF WORK

For CLIN 1 & 2 (Phase 1)

TECHINCAL PROVISION – I

STATEMENT OF WORK 13 May 2019

PWO TITLE LOCATION

214261 Construct Offices and Dormitory, S-256 K-16

1. Description: Contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.

1.1. Performance Period: The contractor shall complete this project within 180 days after NTP is issued.

2.1. Schedule #I, Repair (K): All works shall be in accordance with the attached drawings and specifications.

2.1.1. Civil work

2.1.1.1. Replace Asphalt Concrete (AC) pavement.

2.1.1.2. Replace concrete sidewalk.

2.1.1.3. Replace chain link fence (FE-5) including 3.0m width double swing gate with new.

2.1.1.4. Paint parking line with 150mm thickness reflective white.

2.1.1.5. Restore chain link fence (FE-10).

2.1.1.6. Restore solid sodding.

2.1.1.7. Relocate exist fuel tank w/dike and fuel dispenser, including underground power wiring.

2.2. Schedule #II, new construction (L): All work shall be in accordance with the attached

2.2.1. Civil work

2.2.1.1. Construct 0.3m width steel grating ditch.

2.2.1.2. Construct three (3) surface inlet (0.5m x 0.5m) and 0.3m diameter Reinforced Concrete Pipe (RCP) to connect to new box-culvert.

2.2.1.3. Construct concrete curb.

2.2.1.4. Construct 2.1m height chain link fence including 1.2m width single swing gate (FE- 5).

2.2.1.5. Construct 300mm thickness concrete pad 300mm higher than existing ground level.

2.2.2. Architectural work

2.2.2.1. Floor work

2.2.2.1.1. Install VCT including VCB as shown on floor plan and interior finish schedule.

2.2.2.1.2. Install rubber tiles including rubber tile base as shown on floor plans and interior finish schedule

2.2.2.1.3. Install concrete slab and stoops as shown on floor plan, existing and removal plan, floor plan, section, and interior finish schedule.

2.2.2.1.4. Apply epoxy coating with non-slip grits as shown on floor plan and interior finish schedule.

2.2.2.1.5. Install FT with new including cement bond coat, water proof membrane, mortar bed as shown on floor plans and detail drawings.

2.2.2.2. Interior and exterior wall work

2.2.2.2.1. Install all GWB walls including metal studs and insulation as shown on floor plans, sections and detail drawings.

2.2.2.2.2. Paint on all interior and exterior wall surfaces including other components (stair, steel handrail, and guardrail) as shown on interior finish schedule, elevations, and sections.

2.2.2.2.3. Install GCWT including bond coats, water proof membrane, plastering with metal lath, and waterproof FWB as shown on floor plans and sections.

2.2.2.2.4. Install pipe chases and pipe cover CMU, waterproof or ‘X’ type of GWB for mechanical piping system and duct as per floor plans, sections, and detail drawings.

2.2.2.2.5. Install protected wall siding including insulations with vapor barrier and protected metal wall lining as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.2.6. Install CMU wall with reinforcement bars and EIFS for exterior walls of extended building as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.3. Interior and exterior ceiling/roof work

2.2.2.3.1. Install acoustical ceiling tile including metal suspension systems as shown on floor plan and interior finish schedule.

2.2.2.3.2. Install ceiling GWB (Normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.

2.2.2.3.3. Paint on all interior ceiling surfaces as shown on interior finish schedule and section.

2.2.2.3.4. Install protected metal roof and protected metal siding including insulations w/vapor barrier and protected metal roofs and metal wall linings as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.3.5. Install protected metal canopies with new including rain gutter and downspout as shown on elevation and detail.

2.2.2.4. Miscellaneous work

2.2.2.4.1. Install doors and door frames including new hardware sets as shown on new floor plan and door schedule.

2.2.2.4.2. Install windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations, and window schedule.

2.2.2.4.3. Install aluminum louver as shown on floor plans and louver schedule.

2.2.2.4.4. Install metal shelf with mop rack in janitor room as shown on floor plans and detail drawing.

2.2.2.4.5. Install window horizontal mini blinds, fireproof type.

2.2.2.4.6. Install Fire Extinguisher Cabinet (FEC) as shown on new floor plans and detail drawing.

2.2.2.4.7. Install all toilet accessories as shown on floor plans and detail drawings.

2.2.2.4.8. Install kitchenette including base cabinet and upper cabinet as shown on floor plan, elevation, and detail drawings.

2.2.2.4.9. Install interior and exterior signage with new for all rooms as shown on floor plan, elevations and signage schedule.

2.2.2.4.10. Install SST laundry shelves room as shown on floor plan and detail drawing.

2.2.2.4.11. Install access doors on wall and ceiling as required.

2.2.2.4.12. Install bulletin board as shown on floor plan and detail drawing.

2.2.2.4.13. Install protected metal rain gutters and downspouts including concrete splash blocks as shown on floor plans and elevations.

2.2.3. Mechanical work

2.2.3.1. HVAC system

2.2.3.1.1. Install outdoor and indoor split system heat pump units, outside air unit, piping, concrete pad ductworks, diffusers, control and accessories as indicated on plans.

2.2.3.1.2. Install gas fired hot water boiler, flue vent, combustion air intake, gas leak detection control panel, gas gong, gas leak detector, shut up valve, gas meter cabinet, gas meter, gas regulator, valve cabinet gas filter, automatic shut off valve, concrete pad, and gas piping as indicated on plans.

2.2.3.1.3. Install electric wall heaters, electric unit heaters, range hood, unit heaters, hose reel with fan, heat destratification fan, air pressure filter-regulator lubricator, split air conditioning unit hot water circulation pump, air separator, expansion tank, concrete pad, associated piping and accessories as indicated on plans..

2.2.3.1.4. Install exhaust fans associated ductworks, backflow preventer and pressure reducing station, outside air (OA) intake louver with bird screen and motorized damper, hot water piping, insulation, and accessories as indicated on plans.

2.2.3.2. Plumbing system

2.2.3.2.1. Install gas fired domestic hot water heater, flue vent, combustion air intake, domestic hot water circulation pump, domestic hot water re-circulation pump, concrete pad, associated piping and accessories as indicated on plans.

2.2.3.2.2. Install hot and cold water piping including valves, hose bibbs, water hammer arrests, insulation, and accessories as indicated on plans.

2.2.3.2.3. Install sewer, vent piping, floor drain, floor cleanout, and accessories as indicated on plans.

2.2.3.2.4. Install electric water cooler, emergency shower and eyewash, domestic hot water storage tank, expansion tank, associated piping and accessories as indicated on plans.

2.2.3.2.5. Install plumbing fixtures, associated piping and accessories as indicated on plans.

2.2.3.3. Sprinkler work

2.2.3.3.1. Install wet type sprinkler system and associated piping as indicated on plans.

2.2.4. Electrical work

2.2.4.1. Install new interior lighting fixtures, exit lights, exterior lights, lighting switches, lighting contractor and photo control, wires and conduits.

2.2.4.2. Install new panel boards, dry type transformer, receptacles including cover plates, and associated wiring and conduits.

2.2.4.3. Install new safety switch, motor controllers, junction boxes, control and power wires and conduits for mechanical HVAC system.

2.2.4.4. Install addressable fire alarm control and mass notification system devices such as fire alarm mass notification booster panel, manual pull station, smoke detector and relay module, building transmitter, antenna, visual and signal strobes (15 or 75 candela), microphone, speaker (wattage as required) device, and associated wiring and conduit.

2.2.4.5. Install new telephone system devices such as telephone and data outlets including cover plates, telephone terminal board, equipment rack accessories, and associated wire and conduit.

2.2.4.6. Install new grounding system including grounding rods, wire and test wells.

2.2.4.7. Install new CATV system including CATV outlets including cover plates, accessories and associated wire and conduit.

2.2.4.8. Install new PA system including speakers with accessories, and associated wire and conduit.

2.2.5. Structural Work

2.2.5.1. Install new foundation, column, beam, truss, purlin, girt, bracing, and canopy including all necessary works as shown on the drawings.

2.2.5.2. Install new first floor, second floor, wall, ramp, and stair including all necessary works as shown on the drawings.

2.2.5.3. Dispose removed all construction debris to outside of compound.

NOTE: Contractor shall submit detail shop drawings to COR and get approval prior to the start of work including performance method and schedule.

TECHNICAL PROVISIONS – II

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx.

The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

STANDARD TECHNICAL SPECIFICATIONS FOR O&MA

PROJECT TABLE OF CONTENTS

http://www.usfk.mil/Resources/ContractingwithUSFK.aspx

DIVISION 01 – GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED

MATERIAL

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS

MATERIALS

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT, TARGET

HOUSING & CHILD OCCUPIED FACILITIES

DIVISION 03 – CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 MASONRY

DIVISION 05 - METALS

05 05 23 WELDING, STRUCTURAL

05 12 00 STRUCTURAL STEEL

05 21 23 STEEL JOIST GIRDER FRAMING

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 50 14 STRUCTURAL METAL FABRICATIONS

05 51 00 METAL STAIRS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 14 00 FLUID-APPLIED WATERPROOFING

07 22 00 ROOF AND DECK INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 31 13 ASPHALT SHINGLES

07 41 13 METAL ROOF PANELS

07 42 13 METAL WALL PANELS

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 33 23 OVERHEAD COILING DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 87 16 FRAGMENT RETENTION FILM FOR GLASS

08 91 00 METAL WALL AND DOOR LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 22 36 LATH

09 29 00 GYPSUM BOARD

09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 01 EXTERIOR SIGNAGE

10 14 02 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 28 13 TOILET ACCESSORIES

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 32 00 MANUFACTURED WOOD CASEWORK

12 36 00 COUNTERTOPS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST

SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 23 00 REFRIGERANT PIPING

23 52 00 HEATING BOILERS

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT

DIVISION 26 – ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 23 00 SWITCHBOARDS AND SWITCHGEAR

26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-300 KW, STANDBY

APPLICATIONS

26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION

SWITCH

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 – COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 33.00 10 FIRE ALARM REPORTING SYSTEM, RADIO TYPE

28 31 49 CARBON MONOXIDE DETECTORS

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTH WORK

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

33 40 00 STORM DRAINAGE UTILITIES

33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays:

Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). The contractor will not be permitted any construction work during scheduled (15 days in March and 15 days in August) and unscheduled training/exercises. The contractor shall remove heavy equipment and field offices from CP Tango and K-16 training sites during the training/exercises periods.

3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor.

These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.

4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn. Any individual removed from this installation will not be authorized further access to this installation.

5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.

6. AT/FP TRAINING REQUIREMENTS OF CONTRACTOR:

a. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

b. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

c. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.

e. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

7. SUBMITTALS: The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES. Specific submittal requirements are shown on attached document entitled, “MMTL (MASTER MATERIAL TRACKING LOG)”, Enclosure 1.

For CLIN 3 (Phase 2) http://jko.jten.mil/

TECHINCAL PROVISION – I

STATEMENT OF WORK 13 May 2019

PWO TITLE LOCATION

209625 Construct Bays for New Fire Station, S-256 K-16

1. Description: Contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the

1.2. Performance Period: The contractor shall complete this project within 180 days after NTP is issued.

2.1. Schedule #I, Repair (K): All works shall be in accordance with the attached drawings and

2.1.1. Civil work: None

2.2. Schedule #II, new construction (L): All work shall be in accordance with the attached

2.2.1. Civil work: None

2.2.2. Architectural work

2.2.2.1. Floor work

2.2.2.1.1. Install VCT including VCB as shown on floor plan and interior finish schedule.

2.2.2.1.2. Install concrete slab and stoops as shown on floor plan, and interior finish schedule.

2.2.2.1.3. Apply epoxy coating with non-slip grits as shown on floor plan and interior finish schedule.

2.2.2.1.4. Install trenches including trench covers in Apparatus as shown on floor plans and detail drawings.

2.2.2.2. Interior and exterior wall work

2.2.2.2.1. Install all GWB walls including metal studs and insulation as shown on floor plans, sections and detail drawings.

2.2.2.2.2. Paint on all interior and exterior wall surfaces on interior finish schedule, elevations, and sections.

2.2.2.2.3. Install protected wall siding including insulations with vapor barrier and protected metal wall lining as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.2.4. Install CMU wall with reinforcement bars and EIFS for exterior walls of extended building as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.3. Interior and exterior ceiling/roof work

2.2.2.3.1. Install acoustical ceiling tile including metal suspension systems as shown on floor plan and interior finish schedule.

2.2.2.3.2. Paint on all interior ceiling surfaces as shown on interior finish schedule and section.

2.2.2.3.3. Install protected metal roof including insulations w/vapor barrier and protected metal roof liner panels as shown on floor plans, elevations, sections, and detail drawings.

2.2.2.3.4. Install protected metal canopies with new including rain gutter and downspout as shown on elevation and detail.

2.2.2.4. Miscellaneous work

2.2.2.4.1. Install doors and door frames including new hardware sets as shown on new floor plan and door schedule.

2.2.2.4.2. Install windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations, and window schedule.

2.2.2.4.3. Install aluminum louver as shown on floor plans and louver schedule.

2.2.2.4.4. Install window horizontal mini blinds, fireproof type.

2.2.2.4.5. Install Fire Extinguisher Cabinet (FEC) as shown on new floor plans and detail drawing.

2.2.2.4.6. Install interior and exterior signage with new for all rooms as shown on floor plan, elevations and signage schedule.

2.2.2.4.7. Install roll up doors including manual hand chain and wire remote controller as shown on floor plans and door schedule.

2.2.2.4.8. Install access doors on wall and ceiling as required.

2.2.2.4.9. Install guard posts as shown on floor plans and detail drawing.

2.2.2.4.10. Install protected metal rain gutters and downspouts including concrete splash blocks as shown on floor plans and elevations.

2.2.3. Mechanical work

2.2.3.1. HVAC system

2.2.3.1.1. Install unit heaters, hose reel with fan, heat destrafification fans, air pressure filter-regulator lubricators associated piping with insulation control and accessories as indicated on plans.

2.2.3.1.2. Install exhaust fans associated ductworks, O.A intake louver with birdscreen and motorized damper, CO sensor AMD control as indicated on plans.

2.2.3.2. Plumbing system

2.2.3.2.1. Install hot and cold water piping including valves, hose bibbs, water hammer arrests, insulation, and accessories as indicated on plans.

2.2.3.2.2. Install sewer, vent piping, floor drain, floor cleanout, and accessories as indicated on plans.

2.2.4. Electrical work

2.2.4.1. Install new interior lighting fixtures, exit lights, exterior lights, lighting switches, lighting contractor and photo control, wires and conduits.

2.2.4.2. Install new panel boards, dry type transformer, receptacles including cover plates, and associated wiring and conduits.

2.2.4.3. Install new safety switch, motor controllers, junction boxes, control and power wires and conduits for mechanical HVAC system and roll-up doors control system.

2.2.4.4. Relocate existing weather sensors, a weather sensor pole, lighting protection, guy wire with concrete foundation.

2.2.4.5. Relocate existing radio antenna with new concrete pole and cable.

2.2.5. Structural Work

2.2.5.1. Install new foundation, column, beam, truss, purlin, girt, bracing, and canopy including all necessary works as shown on the drawings.

2.2.5.2. Install new first floor, second floor, wall, ramp, and stair including all necessary works as shown on the drawings.

2.2.5.3. Dispose removed all construction debris to outside of compound.

NOTE: Contractor shall submit detail shop drawings to COR and get approval prior to the start of work including performance method and schedule.

TECHNICAL PROVISIONS – II

TECHNICAL DETAIL SPECIFICATIONS

GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

STANDARD TECHNICAL SPECIFICATIONS FOR O&MA

PROJECT TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED

MATERIAL

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS

MATERIALS

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT, TARGET

HOUSING & CHILD OCCUPIED FACILITIES

DIVISION 03 – CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 MASONRY

DIVISION 05 - METALS

05 05 23 WELDING, STRUCTURAL

05 12 00 STRUCTURAL STEEL

05 21 23 STEEL JOIST GIRDER FRAMING

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 50 14 STRUCTURAL METAL FABRICATIONS

05 51 00 METAL STAIRS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 14 00 FLUID-APPLIED WATERPROOFING

07 22 00 ROOF AND DECK INSULATION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 31 13 ASPHALT SHINGLES

07 41 13 METAL ROOF PANELS

07 42 13 METAL WALL PANELS

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 33 23 OVERHEAD COILING DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 87 16 FRAGMENT RETENTION FILM FOR GLASS

08 91 00 METAL WALL AND DOOR LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 22 36 LATH

09 29 00 GYPSUM BOARD

09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 01 EXTERIOR SIGNAGE

10 14 02 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 28 13 TOILET ACCESSORIES

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 32 00 MANUFACTURED WOOD CASEWORK

12 36 00 COUNTERTOPS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST

SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 23 00 REFRIGERANT PIPING

23 52 00 HEATING BOILERS

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT

DIVISION 26 – ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 23 00 SWITCHBOARDS AND SWITCHGEAR

26 32 14.00 10 DIESEL-GENERATOR SET, STATIONARY 15-300 KW, STANDBY

APPLICATIONS

26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION

SWITCH

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 – COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 33.00 10 FIRE ALARM REPORTING SYSTEM, RADIO TYPE

28 31 49 CARBON MONOXIDE DETECTORS

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTH WORK

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

33 40 00 STORM DRAINAGE UTILITIES

33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.

2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays:

Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). The contractor will not be permitted any construction work during scheduled (15 days in March and 15 days in August) and unscheduled training/exercises. The contractor shall remove heavy equipment and field offices from CP Tango and K-16 training sites during the training/exercises periods.

3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor.

These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.

4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn. Any individual removed from this installation will not be authorized further access to this installation.

5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.

6. AT/FP TRAINING REQUIREMENTS OF CONTRACTOR:

a. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

b. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for http://jko.jten.mil/ background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

c. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

d. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.

e. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

7. SUBMITTALS: The Contractor shall process submittals in accordance with Section 013300 – SUBMITTAL PROCEDURES. Specific submittal requirements are shown on attached document entitled, “MMTL (MASTER MATERIAL TRACKING LOG)”, Enclosure 1.

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days after notice to proceed (NTP) is issued. The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

DRAWINGS

For CLIN 1 & 2 (Phase 1)

LIST OF APPLICABLE CONTRACT DRAWINGS

GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx all of which form a part of the

PWO 214261

Ring No. Sheet No. Description Date

CIVIL

1 C-1 LOCATION PLAN AND GENERAL

NOTES

2 C-2 REMOVAL PLAN

3 C-3 SITE LAYOUT PLAN AND SCOPE OF

WORK

4 C-4 UTILITY PLAN AND SCOPE OF WROK

5 C-5 GRADING SECTION

6 C-6 2.1M CHAIN LINK FENCE AND

SINGLE GATE-1

7 C-7 2.1M CHAIN LINK FENCE AND

SINGLE GATE-2

8 C-8 GAS VALVE W/BOX

9 C-9 CHAIN LINK FENCE AND GATE

10 C-10 SEWER M/H

11 C-11 SURFACE INLET AND STEEL

GRATING DITCH

12 C-12 MISC DETAILS-1

13 C-13 MISC DETAILS-2

14 C-14 CONC PAD DETAIL

STRUCTURAL

1 S-1 STRUCTURAL ABBREVIATIONS

LEGEND AND GENERAL NOTES

2 S-2 STRUCTURAL DESIGN CRITERIA

3 S-3 FOUNDATION AND FIRST FLOOR

FRAMMING PLAN

4 S-4 SECOND FLOOR FRAMING PLAN

5 S-5 ROOF FLAMING PLAN

6 S-6 BUILDING ELEVATIONS-1

7 S-7 BUILDING ELEVATIONS-2

8 S-8 BUILDING SECTIONS-1

9 S-9 BUILDING SECTIONS-2

10 S-10 BUILDING SECTIONS-3

11 S-11 BUILDING SECTIONS-4

12 S-12 TRUSS AND FRAME DETAILS

13 S-13 RIGID FRAME ELEVATION,

SECTIONS AND DETAIL

14 S-14 STAIR-1 PARTIAL PLANS SECTIONS

AND DETAILS

15 S-15 STAIR-2 PARTIAL PLANS SECTIONS

16 S-16 TYPICAL CONCRETE DETAILS

17 S-17 TYPICAL CMU DETAILS

18 S-18 TYPICAL STEEL DETAILS-1

19 S-19 TYPICAL STEEL DETAILS-2

20 S-20 DETAILS-1

21 S-21 DETAILS-2

22 S-22 FOOTING, GRADE BEAM SCHEDULE

23 S-23 PEDESTAL, CONCRETE COLUMN,

STEEL COLUMN AND BASE PLATE

SCHEDULE

24 S-24 STEEL BEAM SCHEDULE

ARCHITECTURA

1 A-1 NEW 1ST FLOOR PLAN & GENERAL

2 A-2 NEW 2ND FLOOR PLAN SCOPE OF

3 A-3 NEW ROOF PLAN

4 A-4 ELEVATIONS

5 A-5 SECTIONS AND DETAIL

6 A-6 EXTERIOR WALL SECTIONS AND

DETAIL

7 A-7 EXTERIOR AND INTERIOR WALL

SECTIONS

8 A-8 INTERIOR WALL SECTIONS-1

9 A-9 INTERIOR WALL SECTIONS-2

10 A-10 ENLARGED STAIR PLANS PARTIAL

SECTIONS AND DETAILS

11 A-11 ENLARGED FLOOR PLANS AND

INTERIOR ELEVATIONS

12 A-12 ROOF AND CANOPY DETAILS

13 A-13 METAL ROOF PANEL DETAILS

14 A-14 CABINET DETAILS AND COUNTER

TABLE DETAILS

15 A-15 COLUMN DETAILS

16 A-16 MISC DETAILS-1

17 A-17 MISC DETAILS-2

18 A-18 MISC DETAILS-3

19 A-19 MISC DETAILS-4

20 A-20 STAIR DETAILS

21 A-21 INTERIOR EXTERIOR FINISH

SCHEDULE AND MATERIAL AND

COLOR SCHEDULE

22 A-22 INTERIOR EXTERIOR FINISH

COLOR SCHEDULE AND NOTES

23 A-23 DOOR, WINDOW, LOUVER

SCHEDULE AND ELEVATIONS

24 A-24 HARDWARES SCHEDULE AND

25 A-25 SIGNAGES SCHEDULE

MECHANICAL

1 M-1 MECHANICAL MATERIAL

INDICATIONS AND SYMBOLES AND

ABBREVIATIONS

2 M-2 GENERAL NOTES AND SCOPE OF

3 M-3 EQUIPMENT SCHEDULE-1

4 M-4 EQUIPMENT SCHEDULE-2

5 M-5 EQUIPMENT SCHEDULE-3

6 M-6 NEW 1ST FL HVAC PLAN-1,

ENLARGED MECH ROOM PLAN,

CONITROGEN AND NOTES

7 M-7 NEW 2ND FL HVAC PLAN-2 AND

8 M-8 NEW 1ST FL HVAC PLAN-3 AND

9 M-9 NEW 2ND FL HVAC PLAN-4 AND

10 M-10 NEW 1ST FL HVAC PLAN-5 AND

11 M-11 NEW 2ND FL HVAC PLAN-6 AND

12 M-12 NEW 1ST FL PLUMBING PIPING PLAN-

1 AND 2, ENLARGED MECH ROOM

AND NOTES

13 M-13 NEW 2ND FL PLUMBING PIPING

PLAN-3, PLUMBING FIXTURE SCH,

WATER HAMMER ARRESTER SCH

AND NOTES

14 M-14 ELECTRIC UNIT HEATER CONTROL

DIAGRAM, MECH RM VENT SYS

CONTROL DIA, COMPRESSED AIR

PIPING SYSTEM DIA

15 M-15 MECH RM GAS PIPING DIAGRAM

AND GAS LEAK DETECTION ALARM

SEQUENCE DIA

16 M-16 CONNECTION POINT DIA FOR NEW

HOT WATER BOILER, SEQUENCE OF

OPERATION, BOILER SYSTEM

CONTROL EQUIPMENT SCH AND

MECH RM GAS PIPING ISOMETRIC

DIA

17 M-17 DOMESTIC HOT WATER SYSTEM

CONTROL DIA

18 M-18 FIRE PROTECTION LEGEND AND

ABBREVIATION AUTOMATIC FIRE

SUPPRESSION GENERAL NOTES,

SPRINKLER Q’TY LIST AND NOTE

19 M-19 1ST FL FIRE PROTECTION PIPING

PLAN-1

20 M-20 2ND FL FIRE PROTECTION PIPING

PLAN-1

21 M-21 MECH RM FIRE PROTECTION PIPING

PARTIAL PLAN

22 M-22 DETAILS-1

23 M-23 DETAILS-2

24 M-24 DETAILS-3

25 M-25 DETAILS-4

26 M-26 DETAILS-5

27 M-27 DETAILS-6

ELECTRICAL

1 E-1 LEGEND, GENERAL NOTES AND SCOPE OF

WORK

2 E-2 NEW 1ST AND 2ND FLOOR LIGHTING PLAN

3 E-3 LIGHTING FIXTURE DETAIL

4 E-4 LIGHTING FIXTURE SCHEDULE AND

EXTERIOR LIGHTING CONTACTOR

CONNECTION DIAGRAM

5 E-5 NEW 1ST AND 2ND FLOOR POWER PLAN

6 E-6 NEW 1ST AND 2ND FLOOR POWER CONTROL

PLAN FOR MECHANICAL SYSTEM

7 E-7 EXIST/NEW POWER ONE-LINE DIAGRAM

8 E-8 NEW PANELBOARD “L1”, “L2”, “M3’ AND

“P3” LOAD SCHEDULE

9 E-9 NEW 1ST AND 2ND FLOOR FIRE ALARM AND

MASS NOTIFICATION SYSTEM PLAN

10 E-10 FIRE ALARM/MASS NOTIFICATION

SYSTEM SEQUENCE OF OPERATION

11 E-11 FIRE ALARM/MASS NOTIFICATION

SYSTEM DIAGRAM

12 E-12 NEW 1ST FL GROUNDING SYSTEM PLAN

AND GROUND TEST WELL DETAIL

13 E-13 NEW 1ST AND 2ND FL PA AND CATV

SYSTEM PLAN/CATV SYSTEM DIAGRAM

14 E-14 NEW 1ST AND 2ND FLOOR LAN/TEL SYSTEM

PLAN

15 E-15 EXIST/NEW TELECOMMUNICATION

SYSTEM DIAGRAM

For CLIN 3 (Phase 2)

LIST OF APPLICABLE CONTRACT DRAWINGS

GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx all of which form a part of the specifications.

PWO 209625

Ring No. Sheet No. Description Date

STRUCTURAL

1 S-1 STRUCTURAL ABBREVIATIONS

LEGEND AND GENERAL NOTES

2 S-2 STRUCTURAL DESIGN CRITERIA

3 S-3 FOUNDATION AND FIRST FLOOR

FRAMMING PLAN

4 S-4 SECOND FLOOR FRAMING PLAN

5 S-5 ROOF FLAMING PLAN

6 S-6 BUILDING ELEVATIONS-1

7 S-7 BUILDING ELEVATIONS-2

8 S-8 BUILDING SECTIONS-1

9 S-9 BUILDING SECTIONS-2

10 S-10 BUILDING SECTIONS-3

11 S-11 BUILDING SECTIONS-4

12 S-12 TRUSS AND FRAME DETAILS

13 S-13 RIGID FRAME ELEVATION,

SECTIONS AND DETAIL

14 S-14 STAIR-1 PARTIAL PLANS SECTIONS

15 S-15 STAIR-2 PARTIAL PLANS SECTIONS

16 S-16 TYPICAL CONCRETE DETAILS

17 S-17 TYPICAL CMU DETAILS

18 S-18 TYPICAL STEEL DETAILS-1

19 S-19 TYPICAL STEEL DETAILS-2

20 S-20 DETAILS-1

21 S-21 DETAILS-2

22 S-22 FOOTING, GRADE BEAM SCHEDULE

23 S-23 PEDESTAL, CONCRETE COLUMN,

STEEL COLUMN AND BASE PLATE

SCHEDULE

24 S-24 STEEL BEAM SCHEDULE

ARCHITECTURA

1 A-1 NEW 1ST FLOOR PLAN & GENERAL

2 A-2 NEW 2ND FLOOR PLAN SCOPE OF

3 A-3 NEW ROOF PLAN

4 A-4 ELEVATIONS

5 A-5 SECTIONS AND DETAIL

6 A-6 EXTERIOR WALL SECTIONS AND

DETAIL

7 A-7 EXTERIOR AND INTERIOR WALL

SECTIONS

8 A-8 INTERIOR WALL SECTIONS-1

12 A-12 ROOF AND CANOPY DETAILS

13 A-13 METAL ROOF PANEL DETAILS

15 A-15 COLUMN DETAILS

16 A-16 MISC DETAILS-1

17 A-17 MISC DETAILS-2

18 A-18 MISC DETAILS-3

19 A-19 MISC DETAILS-4

21 A-21 INTERIOR EXTERIOR FINISH

COLOR SCHEDULE

22 A-22 INTERIOR EXTERIOR FINISH

COLOR SCHEDULE AND NOTES

23 A-23 DOOR, WINDOW, LOUVER

SCHEDULE AND ELEVATIONS

24 A-24 HARDWARES SCHEDULE AND

25 A-25 SIGNAGES SCHEDULE

MECHANICAL

1 M-1 MECHANICAL MATERIAL

INDICATIONS AND SYMBOLES AND

ABBREVIATIONS

2 M-2 GENERAL NOTES AND SCOPE OF

3 M-3 EQUIPMENT SCHEDULE

4 M-4 NEW 1ST FL HVAC PLAN-1, AND

5 M-5 NEW 2ND FL HVAC PLAN-2 AND

6 M-6 NEW 1ST FL PLUMBING PIPING PLAN-

1 &2 AND NOTES

7 M-7 HEAT DESTRATIFICATION FAN AND

UNIT HEATER CONTROL

8 M-8 DETAILS-2

9 M-9 DETAILS-3

10 M-10 DETAILS-4

11 M-11 DETAILS-5

12 M-12 DETAILS-6

ELECTRICAL

1 E-1 LEGEND, GENERAL NOTES AND SCOPE OF

WORKS

2 E-2 EXIST/NEW EXTGERIOR ELECTRICAL

DISTRIBUTION PLAN

3 E-3 NEW GROUND FLOOR LIGHTING PLAN

4 E-4 LIGHTING FIXTURE DETAILS

5 E-5 NEW LIGHTING FIXTURE SCHEDULE &

EXTERIOR LIGHTING CONTACTOR “LC”

DIAGRAM

6 E-6 NEW GROUND FLOOR POWER PLAN

7 E-7 NEW GROUND FLOOR POWER/CONTROL

PLAN FOR MECHANICAL ROOM

8 E-8 EXIST/NEW POWER ONE-LINE DIAGRAM

9 E-9 NEW POWER ONE-LINE DIAGRAM

Section K - Representations, Certifications and Other Statements of Offerors

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by…