Review Comments Compilation
470 Olde Worthington Road, Suite 325, Columbus, Ohio 43082
Ph: (614) 839-0250 Email: info@primeeng.com Fax: (614) 839-0251
Response to Review Comments
Project: Water and Sewer Capacity Study Ohio Air National Guard and Ohio Army National Guard Rickenbacker International Airport, Columbus, Ohio
Project No.: 01018-4-E61
OANG Project No. NLZG062005
Subject: Response to 95% Submittal Comments
Review Comments:
Air National Guard
1. Page 5, para 3.1. The Air National Guard Owns 162.982 Acres, not the 157.8 stated.
We have revised the report accordingly
2. Page 7, para 3.6: The Air National Guard and the Army National Guard are currently responsible for the water and sewer lines on their respective properties.
Corrected
3. Page 31, para 9.0: Just after table 9.1, it states that to replace the water lines on the installation would be $2,000,000. Not a problem there, but if we replace the water lines we will not have to make some of the improvements as stated in the above paragraph (I believe). So the total cost should not be $2,590,000.
Total cost corrected to remove replacement costs of transite pipe, which would be included in installation of new water loop. Corrected total cost is now $2,300,000.
Army National Guard
1. Locate the building in the correct locations according to plans and site picture provided by AGOH-FM-DP.
Correct building locations are now updated in plans according to aerial photographs provided by AGOH-FM-DP.
2. Use site picture listing to ensure that all building to date are represented
All buildings are now included in site plans as per aerial photographs provided by AGOH-FM-DP.
3. Use correct street names.
Correct street names are now added to site plans.
Review Comments Compilation
4. Locate water lines according to drawings provided by AGOH-FM-DP.
Water lines are now corrected as per AGOH-FM-DP.
5. Ensure correct fixture and people count for all facilities.
Fixture counts and population counts are now corrected.