W912WJ18B0016
Construct Waterline
Durham Meadows, Durham, Connecticut
Construction Solicitation and Specifications
May 2018
Construct Water Line, Durham Meadows, Durham, Connecticut
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 PROJECT MEETINGS
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 39 00 PRE- AND POST-CONSTRUCTION SURVEYS
01 41 00 SAMPLING PROCEDURES AND LABORATORY SERVICES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 71 23 FIELD ENGINEERING
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Soil and Groundwater Contamination
1.1.2 Winter Shutdown
1.2 SUBMITTALS
1.3 Quality Assurance Project Plan (QAPP)
1.4 MAINTENANCE AND PLAN OF OPERATION (MAPO)
1.5 SUPERINTENDENCE BY THE CONTRACTOR
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
1.7 PUBLIC RELATIONS LIAISON
1.8 PROJECT/SITE CONDITIONS
1.8.1 Site Security
1.9 WORK SEQUENCE AND SCHEDULING
1.9.1 Hours of Operations
1.9.2 Restrictions During Annual Durham Fair
1.9.3 Restrictions in School Area
1.9.4 General Work Sequence
1.9.4.1 Project Schedule
1.9.4.2 Two-Week Schedule of Work Activities
1.9.5 Organization at the Site
1.9.5.1 General
1.9.5.2 Rate of Progress
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site
1.11.2 Temporary Facilities and Utilities, and Storage Areas
1.11.3 Work Limits
1.11.4 Work Restrictions
1.11.5 Occupying Private Land
1.11.6 Protection and Security
1.11.7 Work By Other Contractors
1.11.8 Emergency Contacts
1.11.9 Damaged Property
1.11.10 Contractor's Receipt of Supplies
1.11.11 Daily Clean Up
1.11.12 Government Sanitary Facilities
1.11.13 Existing Utility Interruptions
1.11.14 Contractor Employee Identification
1.11.15 Pipe Locations
1.11.16 Dimensions of Existing Structures
1.11.17 Open Excavations
1.11.18 Test Pits
1.11.19 Interference with and Protection of Streets
1.12 PROGRESS REPORTS AND PROGRESS PHOTOGRAPHS
1.13 CARE AND PROTECTION OF PROPERTY
1.14 INTERFERENCE WITH EXISTING WORKS
1.15 MAINTAINING FLOWS
SECTION 01 11 00 Page 1
1.16 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND UTILITIES
1.17 INSPECTION OF WORK AWAY FROM THE SITE
1.18 COOPERATION WITHIN THIS CONTRACT
1.19 CLEANUP AND DISPOSAL OF EXCESS MATERIAL
1.20 LOCATION OF UNDERGROUND FACILITIES
1.20.1 Notification Prior to Excavation
1.21 BURIED UTILITY WARNING AND IDENTIFICATION TAPE
1.22 PROTECTION AGAINST ELECTROLYSIS
1.23 CULTURAL RESOURCES
1.24 MISCELLANEOUS PROVISIONS
1.24.1 Green Remediation
1.25 EPA OFF-SITE RULE
1.26 QUALITY ASSURANCE
1.27 CERTIFICATION
1.28 GENERAL SAFETY REQUIREMENTS
1.28.1 General
1.28.2 Contractor's Project Superintendent
1.29 ENVIRONMENTAL PROTECTION
1.30 PRECONSTRUCTION CONFERENCE
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
Work of this project shall include, but not limited to, the following major items:
1. Construction of a new 0.8 million gallon prestressed concrete water storage tank, access roadway, site improvements, and appurtenances off Talcott Ridge Drive in the City of Middletown.
2. Modifications at the Long Hill Pump Station in the City of Middletown.
3. Installation of approximately 31,200 linear feet water main (20-inch to 6-inch diameter) and appurtenances in Town of Durham and CTDOT roadways, including but not limited to:
(1) South Main Street (Route 17) in Middletown from Talcott Ridge Drive to the town line with Durham,
(2) Main Street (Route 17) in Durham from the town line to Mill Pond Lane,
(3) Talcott Lane in Durham,
(4) Maple Avenue in Durham from Talcott Lane south to the Allyn Brook crossing and from the south point of the crossing near John’s Way to connect to the existing water main,
(5) Wallingford Road from Main Street west past Maple Avenue to near No. 47 Wallingford Road,
(6) Maiden Lane from Main Street to the intersection with Pickett Lane,
(7) Pickett Lane; and
(8) Main Street service extensions (limited lengths) at; Royal Oak Drive, Littleton Lane, Parson Lane, Winsome Road, Middlefield Road, Haddam Quarter Road, Maiden Lane and Pickett Lane.
4. Installation of approximately 500 linear feet of 12-inch water main and appurtenances on Town of Durham property west of Maple Avenue and crossing Allyn Brook.
5. Installation of approximately 206 water service connections (from corporation to curb stops) of which approximately 115 will be installed
SECTION 01 11 00 Page 3 into the building structure to establish a new water supply.
Components of approximately 114 existing private water supply systems to be abandoned include existing wells and appurtenances, including pressure tanks and water treatment devices to be removed, as specified, including property restoration. Six supply wells shall be converted to monitoring wells.
6. Construction of a booster pump station on South Main Street, including site improvements and appurtenances, in Middletown on the northern portion of the CT DOT property across from the intersection of Talcott Ridge Road.
7. Construction of a water meter station, including site improvements and appurtenances, in the City of Middletown on City-owned property on South Main Street at the corner of Acorn Drive.
See Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES, Subpart TRAFFIC PROVISIONS AND TRAFFIC CONTROL PLAN for requirements and restrictions relative to traffic control and diversions on this project.
1.1.1 Soil and Groundwater Contamination
While most of the work will occur within the public roadways or other areas outside of the Durham Meadows Superfund Site source areas, installation of a water service connection to the Durham Manufacturing Company at 201 and 203 Main Street will involved trenching in an area of known contamination.
Known site soil and groundwater contaminants in the work area, as shown on Contract Drawing C-21, include volatile organic compounds (VOCs), particularly TCE, PCE, methylene chloride. Additionally, well abandonment throughout the project area will involve potential contact with groundwater contaminated with VOCs. A summary of Site contamination is included in Appendix D of this specification.
1.1.2 Winter Shutdown
A mandatory winter shutdown period extending from 1 December to 31 March, inclusive, of any year, will be enforced during the performance period of this contract. During the winter shutdown periods, the Contractor will not be permitted to perform on-site construction work of any kind.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Maintenance and Plan of Operation (MAPO); G, RO
The Contractor shall submit a Maintenance and Plan of Operation (MAPO). The MAPO shall consist of a written narrative describing the proposed sequence of construction and proposed temporary equipment to be utilized to maintain operation of the force main, all services, and all hydrants during construction. No site work will be allowed until acceptance of the MAPO by the Contracting Officer.
SECTION 01 11 00 Page 4
Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks).
Progress Report; G, RO
Quality Assurance Project Plan (QAPP); G, DO
Public Relations Liaison; G, DO
Green Remediation Practices
SD-07 Certificates
Request Application; G, RO
Request Application to work outside the hours of operation.
SD-11 Closeout Submittals
CT DPH Certificate
1.3 Quality Assurance Project Plan (QAPP)
The Contractor is required to prepare a Quality Assurance Project Plan (QAPP) to describe the steps that will be taken to ensure that environmental data collected are of the correct type and quality required, and that presents an organized and systematic description of the ways in which QA and QC will be applied to the collection and use of environmental data. The QAPP shall be submitted for reiew and approval by the Contracting Officer. The Contractor shall follow the guidance provided by the Environmental Protection Agency (EPA) document entitled "Uniform Federal Policy for Quality Assurance Project Plans", dated March 2005.
This document is available at the following internet address:
https://www.epa.gov/sites/production/files/documents/ufp_qapp_v1_0305.pdf
1.4 MAINTENANCE AND PLAN OF OPERATION (MAPO)
A. Contractor shall submit a Maintenance and Plan of Operation (MAPO) for requirements of this section and as specified herein.
B. MAPO shall consist of a proposed sequence of construction and proposed temporary equipment to be utilized to maintain operation of the force main during construction.
1. Contractor shall develop a detailed narrative to address the following:
a. Sequence of construction, testing, and start-up. Particular attention shall be paid to ensuring that there is no loss of fire protection for structures existing fire protection; that loss of water service shall not exceed 2 hours at any time.
b. The plan shall address the Contractor's approach to minimizing
SECTION 01 11 00 Page 5 residence time of the water in the system, with particular attention paid to the residence time in the Cherry Hill Storage Tank.
c. The plan shall address work during anticipated periods of high traffic, including daily as well as annual events, including the Durham Fair.
d. The plan shall include work schedules and proposed detours required during high traffic periods.
2. The MAPO shall include a schedule addressing the above.
C. No site work will be allowed until acceptance of the MAPO by the Contracting Officer.
1.5 SUPERINTENDENCE BY THE CONTRACTOR
a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.
1.6 COORDINATION AND DIRECTION DURING CONSTRUCTION
a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.
b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.
SECTION 01 11 00 Page 6
1.7 PUBLIC RELATIONS LIAISON
The Contractor shall include in the staffing for this project a Public Relations Liaison employee. The Contractor shall submit the qualifications of this Public Relations Liaison employee to the Contracting Officer for approval. This person's qualifications and duties shall be as listed below:
Qualifications:
1. Five years' experience in water line or other utility work.
2. Technical knowledge of utility projects.
3. Skill in oral and written communications.
Duties:
1. Coordinate with home/property owners for access, work activities, water service start-up, and testing of water service connections.
2. Coordinate with Connecticut DEP, U.S. Army Corps of Engineers, and USEPA. Prepare agendas, meeting minutes, and reports for weekly and monthly meetings and other reports as required in the specifications.
3. Coordinate with Durham and Middletown Water Departments for water line connections, valve openings and closings, outages, chlorination, pressure testing, coliform testing, and other related issues not otherwise noted.
4. Coordinate road and lane closures with all stakeholders including notifications.
5. Work with the U.S. Army Corps of Engineers to resolve disputes and complaints from home/property owners.
6. Support the EPA by attendance at four EPA run public meetings per year, held in the evening, approximately three hours in duration per meeting.
The Public Liaison position shall be a dedicated, full-time position, requiring a full-time presence on the project site. The person in this position shall not serve as QC Manager, SSHO, Site Superintendent, Project Manager, or any other position, and shall have no duties except Public Liaison.
1.8 PROJECT/SITE CONDITIONS
1.8.1 Site Security
The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible. The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment and grounds while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.
SECTION 01 11 00 Page 7
1.9 WORK SEQUENCE AND SCHEDULING
1.9.1 Hours of Operations
Normal work hours are from 7:00 a.m. through 4:00 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer.
The exclusion of work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:
January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December
When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work outside the normal hours of operation requires Contracting Officer approval and, in general, will only be permitted if required (and coordinated) by private property owners for water service connections and/or well abandonment work. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.9.2 Restrictions During Annual Durham Fair
The Contractor shall be aware that special restrictions on allowed work areas and work tasks will apply during the the period five days prior to the start of, during, and one day after the completion of the Durham Fair, held annually in late September on a Thursday through Sunday.
Specifically, during this annual 10 day period (Saturday before through the second following Monday), no road construction will be allowed and all roads shall be fully open for traffic flow, with equipment not restricting flow at any location. Work activities that may be allowed, subject to the Contracting Officer's approval, include; activity at the tank site and access road, Middletown pump station, and inside individual homes.
Multiple deliveries of equipment or supplies will also not be allowed during this annual period.
Established dates for the Durham fair are as follows:
2018: 26 through 29 September
2019: To be determined
SECTION 01 11 00 Page 8
2019: To be determined
1.9.3 Restrictions in School Area
Contractor work in the school area involving excavation, pipe installation, paving, connection, testing, and certification activities shall only occur during the summer school break period. The school area is defined as all of Pickett Lane (Route 17 to Maiden Lane).
1.9.4 General Work Sequence
There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress schedule. Variations shall be approved by the Contracting Officer prior to implementation.
1.9.4.1 Project Schedule
See Section 01 32 01 PROJECT SCHEDULE.
1.9.4.2 Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks). The schedule of work activities shall be updated and submitted by the Contractor to the Contracting Officer on a weekly basis, by noon on every Thursday during the prosecution of work period. The schedule of work activities will be used as the basis for coordinating the Contractor's work with base activities, officials, and occupants. Failure to provide the two-week schedule of work activities may result in a stop work order being issued by the Contracting Officer. The denial of work activities due to the contractor's failure to submit the two-week schedule of work activities shall not be the basis for a government caused delay claim.
1.9.5 Organization at the Site
1.9.5.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause 1.
1.9.5.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.
SECTION 01 11 00 Page 9
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
The Contractor shall be responsible for the following:
(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.
(3) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site
Access to the project site is available for construction traffic. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.
1.11.2 Temporary Facilities and Utilities, and Storage Areas
The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
1.11.3 Work Limits
Work shall be restricted to the limits of work as shown on the contract drawings, to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, and as indicated by the Contracting Officer.
Do not disturb portions of the Project site beyond areas in which the Work is indicated. Work in roadways is limited to public right of ways unless otherwise indicate.
Work on private property is limited to building exteriors unless private plumbing work is required inside basements. All work on private property is limited to the written access agreement provided and as coordinated with the Private Property Owner and Occupant.
1.11.4 Work Restrictions
Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
2. All work on private property to be pre-scheduled with the Private Property Owner and Contracting Officer.
1.11.5 Occupying Private Land
The Contractor shall confirm with the Contracting Officer that access has
SECTION 01 11 00 Page 10 been obtained before entering private property. When working on private property, the Contractor's personnel shall wear corporate identification tags
1.11.6 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.11.7 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors.
1.11.8 Emergency Contacts
The Contractor shall provide a list of emergency contacts in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.11.9 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.11.10 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.11.11 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.11.12 Government Sanitary Facilities
Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
1.11.13 Existing Utility Interruptions
Do not interrupt utilities serving facilities occupied by the Municipalities (Town of Durham/Middletown) or others unless permitted under the following conditions and then only after providing temporary utility
SECTION 01 11 00 Page 11 services according to requirements indicated:
1. Notify Contracting Officer not less than five working days days in advance of proposed utility interruptions.
2. Obtain Contracting Officer's written permission before proceeding with utility interruptions.
The Contractor shall confirm with the Contracting Officer that access has been obtained before entering private property. When working on private property, the Contractor's personnel shall wear corporate identification tags.
1.11.14 Contractor Employee Identification
Provide corporate identification tags (i.e., company name and logo) for Contractor personnel working on Private Property. The Contractor’s personnel shall provide Access Consent Form and wear corporate identification tags at all times.
1.11.15 Pipe Locations
A. Exterior pipelines will be located substantially as indicated on the contract drawings, but the right is reserved to the Owner, acting through the Contracting Officer, to make such modifications in location as may be found desirable to avoid interference with existing structures or for other reasons. Where fittings, etc., are noted on the contract drawings, such notation is for the Contractor's convenience and does not relieve him from laying and jointing different or additional items where required.
B. Small interior piping is indicated diagrammatically on the contract drawings, and the exact location is to be determined in the field. Piping shall be arranged in a neat, compact, and workmanlike manner, with a minimum of crossing and interlacing, so as not to interfere with equipment or access ways, and, in general, without diagonal runs.
1.11.16 Dimensions of Existing Structures
The Contractor shall verify the dimensions and locations of existing structures in the field before the fabrication of any material or equipment which is dependent on the correctness of such information.
1.11.17 Open Excavations
All open excavations shall be adequately safeguarded by providing temporary barricades, fencing, caution signs, lights, and other means to prevent accidents to persons and damage to property, and in accordance with applicable occupational health and safety regulations. The Contractor shall, at his own expense, provide suitable and safe bridges and other crossings for accommodating travel by pedestrians and workmen. Bridges provided for access during construction shall be removed when no longer required. The length or size of excavation will be controlled by the particular surrounding conditions, but shall always be confined to the limits prescribed by the Contracting Officer. If the excavation becomes a hazard, or if it excessively restricts traffic at any point, the Contracting Officer may require special construction procedures such as limiting the length of the open trench, prohibiting stacking excavated material in the street, and requiring that the trench shall not remain open overnight.
SECTION 01 11 00 Page 12
The Contractor shall take precautions to prevent injury to the public due to open trenches. All trenches, excavated material, equipment, or other obstacles which could be dangerous to the public shall be well lighted at night.
1.11.18 Test Pits
Test pits for the purpose of locating underground pipeline or structures in advance of the construction shall be excavated and backfilled by the Contractor at the direction of the Contracting Officer. Test pits shall be backfilled immediately after their purpose has been satisfied and the surface restored and maintained in a manner satisfactory to the Contracting Officer.
1.11.19 Interference with and Protection of Streets
The Contractor shall not close or obstruct any portion of a street, road, or private way without obtaining permits therefor from the proper authorities. If any street, road, or private way shall be rendered unsafe by the Contractor's operations, he shall make such repairs or provide such temporary ways or guards as shall be acceptable to the proper authorities.
Streets, roads, private ways, and walks not closed shall be maintained passable and safe by the Contractor, who shall assume and have full responsibility for the adequacy and safety of provisions made therefore.
The Contractor shall, at least 24 hours in advance, notify the Police and Fire Departments in writing, with a copy to the Contracting Officer, if the closure of a street or road is necessary. The Contractor shall cooperate with the Local Officials and/or State Police as required in the establishment of alternate routes and shall provide adequate detour signs plainly marked, and well lighted, in order to minimize confusion.
1.12 PROGRESS REPORTS AND PROGRESS PHOTOGRAPHS
The Contractor shall produce and submit a written biweekly progress report, including progress photographs, to document, organize, and summarize the construction progress made during the previous two week period. The report shall include a narrative describing all work completed during the previous two weeks. Photographs, a minimum size of 3-inches by 5-inches, shall accompany the narrative in sufficient quantity to document all significant work items. The reports shall also incude a narrative of work planned to be completed during the next two week work period. The narrative of planned work shall be coordinated with the two week look ahead schedule.
Areas outside of the limits of work which are subject to possible impact by the Contractor's operations during the following two weeks, or which may be subject to damages from other future Contractor activities, shall also be photo-documented by the report. The written narrative, together with the photographs, shall constitute a recurring "Progress Report", which shall be submitted to the Contracting Officer for approval.
1.13 CARE AND PROTECTION OF PROPERTY
The Contractor shall be responsible for the preservation of all public and private property, and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such
SECTION 01 11 00 Page 13 property shall be restored by the Contractor, at his expense, to a condition similar or equal to that existing before the damage was done, or he shall make good the damage in other manner acceptable to the Contracting Officer.
1.14 INTERFERENCE WITH EXISTING WORKS
A. The Contractor shall at all times conduct his operations so as to interfere as little as possible with existing works. The Contractor shall develop a program, in cooperation with the Contracting Officer and interested officials, which shall provide for the construction and putting into service of the new works in the most orderly manner possible. This program shall be adhered to except as deviations therefrom are expressly permitted. All work of connecting with, cutting into, and reconstructing existing pipes or structures shall be planned to interfere with the existing facilities for the shortest possible time when the demands best permit such interference, even though it may be necessary to work outside of normal working hours to meet these requirements. Before starting work which will interfere with the operation of existing facilities, the Contractor shall do all possible preparatory work and shall see that all tools, materials, and equipment are made ready and at hand.
B. The Contractor shall have no claim for additional compensation by reason of delay or inconvenience in adapting his operations to meet the above requirements.
1.15 MAINTAINING FLOWS
The Contractor shall at his own cost, provide all the flow of drains and water courses interrupted during the progress of the work, and shall immediately cart away and remove all offensive matter. The entire procedure of maintaining existing flow shall be fully discussed with the Contracting Officer well in advance of the interruption of any flow.
1.16 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND
UTILITIES
A. The Contractor shall assume full responsibility for the protection of all buildings, structures, and utilities, public or private, including poles, signs, services to buildings, utilities in the street, gas pipes, water pipes, hydrants, sewers, drains, and electric and telephone cables, whether or not they are shown on the contract drawings. The Contractor shall carefully support and protect all such structures and utilities from injury of any kind. Any damage resulting from the Contractor's operations shall be repaired by him at his expense.
B. The Contractor shall bear full responsibility for obtaining all locations of underground structures and utilities (including existing water services, drain lines, and sewers). Services to buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by the Contractor.
C. Protection and temporary removal and replacement of existing utilities and structures as described in this Section shall be a part of the work under the Contract.
D. If, in the opinion of the Contracting Officer, permanent relocation of a utility is required, he may direct the Contractor, in writing, to perform the work. Work so ordered will be paid at the Contract unit prices, if
SECTION 01 11 00 Page 14 applicable, or as extra work under Article 11 of the Supplementary Conditions. If relocation of a privately owned utility is required, the Contracting Offcier will notify the Utility to perform the work as expeditiously as possible. The Contractor shall fully cooperate with the Contracting Officer and Utility, and shall have no claim for delay due to such relocation. The Contractor shall notify all utility companies in writing at least 72 hours (excluding Saturdays, Sundays, and Legal holidays) before excavating in any public way. Contractor shall also notify Dig Safe, 800-922-4455 at least 72 hours prior to start of work.
E. The Contractor shall coordinate the removal and replacement of traffic loops and signals, if required for the performance of the work, at no additional cost to the Government.
1.17 INSPECTION OF WORK AWAY FROM THE SITE
If work to be done away from the construction site is to be inspected on behalf of the Contracting Officer during its fabrication, manufacture, or testing, or before shipment, the Contractor shall give notice to the Contracting Officer of the place and time where such fabrication, manufacture, testing, or shipping is to be done. Such notice shall be in writing and delivered to the Contracting Officer in ample time so that the necessary arrangements for the inspection can be made.
1.18 COOPERATION WITHIN THIS CONTRACT
A. All firms or persons authorized to perform any work under this Contract shall cooperate with General Contractor and his Subcontractors or trades, and shall assist in incorporating the work of other trades where necessary or required.
B. Cutting and patching, drilling and fitting shall be carried out where required by the trade or subcontractor having jurisdiction, unless otherwise indicated herein or recommended by the Contracting Officer.
1.19 CLEANUP AND DISPOSAL OF EXCESS MATERIAL
A. During the course of the work, the Contractor shall keep the site of his operations in as clean and as neat a condition as is possible. He shall dispose of all residue resulting from the construction work and, at the conclusion of the work, he shall remove and haul away any surplus excavation, broken pavement, lumber, equipment, temporary structures, and any other refuse remaining from the construction operations, and shall leave the entire site of the work in a neat and orderly condition.
B. In order to prevent environmental pollution arising from the construction activities related to the performance of this Contract, the Contractor and his subcontractors shall comply with all applicable Federal, State, and local laws, and regulations concerning waste material disposal, as well as the specific requirements stated in this Section and elsewhere in the Specifications.
C. The Contractor is advised that the disposal of excess excavated material in wetlands, stream corridors, and plains is strictly prohibited even if the permission of the property owner is obtained. Any violation of this restriction by the Contractor or any person employed by him will be brought to the immediate attention of the responsible regulatory agencies, with a request that appropriate action be taken against the offending parties. Therefore, the Contractor will be required to remove the fill at
SECTION 01 11 00 Page 15 his own expense and restore the area impacted.
1.20 LOCATION OF UNDERGROUND FACILITIES
Obtain necessary digging permits prior to start of excavation. Verify the elevations and horizontal location of existing piping, utilities, and any type of underground obstruction in locations to be impacted by the construction work of this project, using test pits where necessary. Verify elevations before installing new work.
1.20.1 Notification Prior to Excavation
For excavation work in Connecticut, call "Caal-Before-You-Dig" at 1-800-922-4455. Notification shall not be earlier than 30 days prior, nor later than 3 days prior, to the planned excavation.
1.21 BURIED UTILITY WARNING AND IDENTIFICATION TAPE
Provide warning tape manufactured specifically for warning and identification of buried piping.Provide tape in rolls, 6 inches minimum width, color coded for the utility involved with warning and identification imprinted in bold black letters continuously and repeatedly over entire tape length. Warning and identification shall be CAUTION BURIED UTILITY PIPING BELOW or similar language. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material. Bury tape with the printed side up at a depth as indicated in the contract drawings.
1.22 PROTECTION AGAINST ELECTROLYSIS
Where dissimilar metals are used in conjunction with each other, suitable insulation shall be provided between adjoining surfaces so as to eliminate direct contact and any resultant electrolysis. The insulation shall be bituminous impregnated felt, heavy bituminous coatings, nonmetallic separators or washers, or other acceptable materials.
1.23 CULTURAL RESOURCES
Compliance with the requirements of the National Historic Preservation Act (NHPA) and the Connecticut State Historic Preservation Office (SHPO).
1. During the life of this contract, the Contractor is herewith required to immediately notify the Contracting Officer in the event that any articles such as “charcoal”, “bone”, “shell”, “cultural objects – fire cracked stones or stone flaking material” or any other such related items of historical significance are discovered.
2. No further Work may proceed in the area in question until the EPA determines that the Work is not reasonably expected to adversely affect the discovered Cultural Resources.
See Section 01 57 20 ENVIRONMENTAL PROTECTION for additional requirements.
1.24 MISCELLANEOUS PROVISIONS
1.24.1 Green Remediation
The Contractor shall incorporate EPA Green Remediation practices whenever practical, in accordance with:
SECTION 01 11 00 Page 16 http://www2.epa.gov/superfund/superfund-green-remediation The Contractor shall identify and submit the Green Remediation practices to be used during completion of the work.
1.25 EPA OFF-SITE RULE
A. Section 121(d)(3) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) applies to any CERCLA response action involving the off-site transfer of any hazardous substance, pollutant or contaminant (CERCLA wastes). That section requires that CERCLA wastes may only be placed in a facility operating in compliance with the Resource Conservation and Recovery Act (RCRA) or other applicable Federal or State requirements. That section further prohibits the transfer of CERCLA wastes to a land disposal facility that is releasing contaminants into the environment, and requires that any releases from other waste management units must be controlled. These principles are interpreted in the Off-Site Rule (OSR), set forth in the National Contingency Plan (NCP), at 40 CFR 300.440. The purpose of the OSR is to avoid having CERCLA wastes from response actions authorized or funded under CERCLA contribute to present or future environmental problems by directing these wastes to management units determined to be environmentally sound (preamble to final OSR, 58 FR 49200, 49201, Sept. 22, 1993).
B. The OSR establishes the criteria and procedures for determining whether facilities are acceptable for the receipt of CERCLA wastes from response actions authorized or funded under CERCLA. The OSR establishes compliance criteria and release criteria, and establishes a process for determining whether facilities are acceptable based on those criteria. The OSR also establishes procedures for notification of unacceptability, reconsideration of unacceptability determinations, and re-evaluation of unacceptability determinations.
C. Contractor may ship hazardous substances, pollutants, and contaminants from the Site to an off-Site facility only if they comply with Section 121(d)(3) of CERCLA, 42 U.S.C. § 9621(d)(3), and 40 C.F.R. § 300.440.
Contractor will be deemed to be in compliance with CERCLA § 121(d)(3) and 40 C.F.R. § 300.440 regarding a shipment if contractor obtain a prior determination from EPA that the proposed receiving facility for such shipment is acceptable under the criteria of 40 C.F.R. § 300.440(b). All requests shall be made using the EPA Off-Site Compliance Request Form, included as Attachment 3.
D. Contractor may ship Waste Material from the Site to an out-of-state waste management facility only if, prior to any shipment, they provide notice to the appropriate state environmental official in the receiving facility’s state and to the EPA. This notice requirement will not apply to any off-Site shipments when the total quantity of all such shipments does not exceed 10 cubic yards. The notice must include the following information, if available: (1) the name and location of the receiving facility; (2) the type and quantity of Waste Material to be shipped; (3) the schedule for the shipment; and (4) the method of transportation.
Contractor also shall notify the state environmental official referenced above and the EPA of any major changes in the shipment plan, such as a decision to ship the Waste Material to a different out-of-state facility. Contractor shall provide the notice to EPA at least 60 days prior to the date when Waste Material is scheduled to be shipped.
E. Site to an off-Site facility only if they comply with Section 121(d)(3) of CERCLA, 42 U.S.C. § 9621(d)(3), 40 C.F.R. § 300.440, EPA’s Guide to
SECTION 01 11 00 Page 17
Management of Investigation Derived Waste, OSWER 9345.3-03FS (Jan. 1992), and any IDW-specific requirements contained in the Durham Meadows Record of Decision. Wastes shipped off-Site to a laboratory for characterization, and RCRA hazardous wastes that meet the requirements for an exemption from RCRA under 40 CFR § 261.4(e) shipped off-site for treatability studies, are not subject to 40 C.F.R. § 300.440.
F. The property at 201/203 Main Street in Durham, Connecticut, as designated on the drawings, shall be considered the Site, for the purpose of this Contract.
1.26 QUALITY ASSURANCE
a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.
f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.27 CERTIFICATION
Upon completion of all work, including construction and testing, the Contractor shall prepare the CT DPH Certificate of Completed Water or Treatment Works Construction/Installation letter for signature of the Administrative Official of the Public Water System, along with all required documentation. The form letter for certification may be found on the CT DPH website at:
http://www.ct.gov/dph/cwp/view.asp?a=3139&q=387316#CertificationLetter
1.28 GENERAL SAFETY REQUIREMENTS
1.28.1 General
The Contractor shall take all necessary precautions in observing safety
SECTION 01 11 00 Page 18 regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
1.28.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.29 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.30 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 11 00 Page 19
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PROJECT MEETINGS
PART 1 TITLE
1.1 COORDINATION
1.2 SUMMARY
1.3 PRECONSTRUCTION CONFERENCE
1.4 PROGRESS MEETINGS WITH CONTRACTING OFFICER
1.5 CONSTRUCTION FOREMEN’S MEETINGS
1.6 HEALTH AND SAFETY MEETINGS
1.7 TESTING, STARTUP AND COMMISSIONING MEETINGS
SECTION 01 14 00 Page 1
SECTION 01 20 00
PROJECT MEETINGS
PART 1 TITLE
1.1 COORDINATION
A. General Contractor shall establish on-site lines of authority and communications.
1. Schedule and conduct progress meetings.
2. Establish procedures for intra-Project communications.
a. Submittals.
b. Reports and records.
c. Recommendations.
d. Coordination drawings.
e. Schedules.
f. Resolution of conflicts.
3. Interpret Contract Documents.
a. Consult with Contracting Officer to obtain interpretation, as required.
b. Assist in resolution of questions or conflicts which may arise.
c. Forward written interpretations to other Contractors, and to other concerned parties.
4. Assist in obtaining permits and approvals.
a. Building permits and special permits required for Work or temporary facilities.
b. Verify Contractors and Subcontractors have obtained inspections for Work and temporary facilities.
5. Control use of site.
a. Supervise field engineering and site layout.
b. Allocate space for each prime Contractor’s use for field offices, sheds, and Work and storage areas.
c. Allocate field office and storage space, and Work and storage areas, for use of each prime Contractor.
SECTION 01 14 00 Page 2
d.