AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide the follow ing:
1. Revised portions of the solicitation
2. The titles and as-built draw ings (for trailers)
3. Changes to Specifications section
4. Responses to RFI's
5. Proposal submission date is extended to 30 June 2016.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 47
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Jun-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ-16-R-0007
X 9B. DATED (SEE ITEM 11)
05-Feb-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Jun-2016
CODE
US ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ‐16‐R‐0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 24-Jun-2016 04:30 PM to 30-Jun-2016 12:00 AM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
AMENDMENT 8
Solicitation Revisions
Revised Sections and Paragraphs of the Solicitation are as follows:
1. In accordance with Clause 52.208-9, the following items are required to be obtained from the required sources stated therein. In addition, Contractors are also responsible for ensuring all product features adhere to the specifications of the solicitation. The Contractor shall immediately notify the Contracting Officer if a mandatory source does not meet the specifications, in accordance with clause requirements.
Section 08 71 00 = Door Hardware
2.7 = Mortise Locks
2.9 = Exit Devices
2.13 = Cylinders
2.16 = Door Closers
Section 10 28 13 = Toilet Accessories
2.2.4 = Paper towel dispenser
2.2.6 = Shower curtain
2.2.8 = Soap dispenser
2.2.10 = Hand sanitizer dispenser
2.2.13 = Toilet tissue dispenser
Section 12 48 12 = Entrance Floor Mats and Frames
2.1 Entrance floor mats
2. Trailer as-builts are also provided but are for informational purposes only. The Government does not warranty their accuracy.
3. The section of the solicitation entitled “Instructions and Evaluation”, is amended in accordance with the specified changes included with this amendment under the same heading.
4. The previous specification section 13 42 00 has been deleted in its entirety and replaced with the attached.
5. The previous bid schedule is deleted in its entirety and replaced with the attached.
RFI’s
1. Swingspace Modular Trailer phase, please confirm onsite work is to only occur between 7/5/16 and 8/1/16?
Response: Swingspace trailer on-site work has been removed from the contract. See attached amendment.
2. Please provide documentation related to existing trailers that are to be assigned to the contractor, to include what right, title and interest J&J Contractors, Inc. has in the trailers, and any inspection documentation and/or certificates of occupancy and compliance. Confirm that the continued use of the trailers will be at no cost to the Primary School contractor and that the existing trailers are free of defects deemed to be detrimental to their continued use. Please also indicate whether the existing trailers meet the requirements for electrical power, provisions for data and communications wiring, and air conditioning/heating.
Response: See attached amended specification section 13 42 00.
3. Specification section 07 21 13 - 3.5.2 indicates under slab insulation is to extend 3’ horizontally under the slab and turn up at slab edge for the thickness of the slab. The numerous details on drawings A-501 through A-508 indicate a horizontal dimension of 2’ and do not show the insulation to turn up at the slab edge.
Response: Provide 2” Insulation 24” horizontal/vertical. Refer to structural foundation/footing elevation for insulation heights. See detail 8/A501 for reference. See attached amendment for revision to Spec Section 07 21 13 BOARD AND BLOCK INSULATION.
4. The same details on drawings A-501 through A-508 indicate insulation extending 2’ horizontally and vertically interior to the building up the foundation wall and under the slab. The exterior of the foundation walls indicate vertical insulation but does not indicate to what depth.
Response: Provide 2” Insulation 24” horizontal/vertical. Refer to structural foundation/footing elevation for insulation heights. See detail 8/A501 for reference. See attached amendment for revision to Spec Section 07 21 13 BOARD AND BLOCK INSULATION.
5. There appears to be (2) different E-401 Drawings issued in the documents provided that are different Drawings. Please clarify which E-401 is to be used for bidding purposes.
Response: See attached amended drawings.
6. Can you tell us who the manufacturer and/or vendor is for the existing Modular Classrooms?
Response: The original 31 trailers installed for the Middle School were manufactured by NRB Inc, Modular Building Systems of Grimsby, Ontario Canada.
The 6 additional trailers installed for the Primary School classrooms were manufactured by Miller Structures Inc. of Bennington, Vermont.
The vendor subcontractor to the Middle School Contractor is Vanguard (152 Sylvan St. Fl 3, Danvers, MA 01923)
7. Will the Primary School contractor be responsible for leasing the 31 existing and 6 new trailer facilities until 27 June 2016? Please provide the name of the company and a contact person for the trailer company that is supplying the existing Middle School
Swing space trailer facility.
Response: Title and ownership of all trailers to be transferred to the Contractor from the middle school contractor at no cost. However, all operations and maintenance (O&M) costs will become the responsibility of the Primary School Contractor upon transfer of ownership of all trailers on midnight September 30, 2016. See amended specification section 13 42 00.
8. Per specification section 10 14 01 2.1.1, post and panel type signs are to be present in drawings. However, no post and panel signs can be found in the drawings. Please provide quantity, dimension, and graphics of post and panel signs if they are to be included in drawings.
Response: Exterior post and panel signage is not required. See attached amendment for revisions to Section 10 14 01 EXTERIOR SIGNAGE.
9. Per specification section 10 14 01 2.2 exterior signs are to be illuminated. Please specify which exterior signs should be illuminated.
Response: Exterior illuminated signage is not required. See attached amendment for revisions to Section 10 14 01 EXTERIOR SIGNAGE.
10. Reference spec. sections 05 12 00 1.7.7.2 a. & c. Please waive the requirements for
AISC ACSE (advanced certified steel erector) and the AISC Sophisticated Paint
Endorsements P1, P2, P3 & SSPC QP3 paint requirements. There are very few ACSE in this area of the country there-by limiting competitive bidding. Also, there are no
AISC P1, P2, P3 or SSPC QP3 certified fabricators in this area.
Response: See amended specification 05 12 00. We have determined not to waive the AISC paint requirements.
11. Spec section 06 20 00 paragraph 2.8.5.1 states Plam casework to be custom grade, spec section 06.41.16 paragraph 1.5.1 states Plam cabinets to be Premium grade. Please advise.
Response: Provide premium grade for millwork items. See attached amendment revising Section
06 20 00 FINISH CARPENTRY.
12. Section 032000 makes reference to “Synthetic Fiber reinforcement”. We cannot discern where this might be used or if it applies to this project.
Response: Synthetic Fiber reinforcement is not required for this project. Contractor can choose to use it if they want.
13. RFI - Doors Frames and Hardware:
The Type SSF Frames are they to be stainless steel frames or cold rolled hollow metal frames?
Response: Provide frame types per drawing A-611 Door/Frame Schedule.
14. Ref. Section 07 45 00
Paragraph 2.3D “FRCP Reveal”, calls for “custom fabricated trim, as indicated on architectural drawings.” The details on typical wall construction drawing A.501 show no reveal trim. Please provide locations of reveal trim or confirm this is not a requirement for the Hanscom AFB Primary School project.
Response: Refer to drawing A201 ELEVATION - Exterior Assembly Legend and Drawing A- 541 RAIN SCREEN DETAILS, Detail - FRCP Met. Reveal
15. The ceiling mount fire alarm/MNS devices shown on the drawings are a device that do not exist. These are only made in a wall mounted device, but not a ceiling mount. Please provide a ceiling mounted fire alarm device for the fire alarm system.
Response: Refer to Drawings FA-001 - Mass Notification Symbol Legend, FA-111, FA-121, and FA-601 for device/mounting types.
16. On sheet L – 203 it shows a ADA Accessible Table to the right of the two benches. It isn’t labeled.
Should we provide this?
Response: Yes, Contractor to relocate table from the temporary school.
17. Site plan ES-102 references panelboard PL1, panelboard PL1 says it is located in site enclosure, site enclosure does not show panelboard PL1. Please clarify the location of panelboard PL1 as several pole fixtures and option #13 are related to this panelboard.
Response: Panel PL1 is existing and is located in an exterior enclosure adjacent the existing Transformer TPL1 as indicated on plans ES101 and ES102 in the NNW corner of the temporary school site.
18. Panel PL1 shows up on E-702 one line. Please clarify if this an existing panel or is required to be installed new per this project.
Response: Panel PL1 is existing and is located in an exterior enclosure adjacent the existing Transformer TPL1 as indicated on plans ES101 and ES102 in the NNW corner of the temporary school site.
19. Please clarify where the path lighting will be required to tie into if existing PL1 panel is removed from the scope of work.
Response: Panel PL1 will remain to serve the remote parking lot lighting after the removal of the temporary trailers.
20. Please clarify if ductbanks in temp trailor area are existing or are required to be new as Drawing ES-102 references Duct "A" and "B". If required please clarify where ductbank "B" is to terminate.
Response: The electrical service including ductbanks are existing to remain (see amendment).
Ductbank B terminates at the Trailer service panels.
21. Please clarify what the dotted lines in different coloration mean on the site electrical drawings. As the Legend does not provide a clear delineation.
Response: Not sure exactly which lines are being referred to, but in general, dashed lines on electrical site plan indicate underground utilities while the darker lines indicate new work and lighter lines indicate existing.
22. Detail 6/L-500 in the landscape drawings shows a circular bench with backrest. Please provide a basis of design for this item.
Response: Provide bench in conformance with Spec Section 12 93 00.
23. Per specification section 10 26 13 2.5.1, type 302 or 304 stainless steel corner guards are to be provided. However, per drawing I-002 stainless steel corner guards (CG1) are to be type 430.
Please clarify which stainless steel type corner guard is to be provided.
Response: Provide SST Corner guards in type 304, see attached amendment.
24. Per specification 10 28 13 2.2.9, soap holders (TA-25) are to be included in toilet accessory package, however no soap holders appear in drawings including A-702 through A-704. Please clarify.
Response: Soap holder TA-25 is not used. Provide soap dispenser TA-13 per drawings A-702, A-703 and A-704. See attached amendment.
25. Per specification 10 28 13 2.2.12, towel pins (TA-16) are to be included in toilet accessory package, however no towel pins appear in drawings including A-702 through A-704. Please clarify.
Response: Towel pins are not used (see attached for deleted paragraph 2.2.12).
26. Per drawings A-702 through A-704, robe hooks (TA-26) are to be included in toilet accessory package, however there is no specification section for robe rooks. Please clarify.
Response: Provide a standard robe hook.
27. Are the Modular Classroom Trailers to be removed from the site after the completion of the Primary School? If so, by whom?
Response: Modular classroom temporary trailers are to be removed from the site after the Government vacates these. See amended specification section 13 42 00.
28. Drawing A922, Item #2, under “Modular Trailers” states “interior space of existing trailers to be refurbished for use by Primary School.” Please provide the specific scope for “refurbished”.
Response: The requirement to refurbish the existing trailers has been removed from this contract. The trailers are currently being refurbished under the Middle School contract. See attached amended specification section 14 32 00.
29. Assumptions from our Steel Supplier:
a. All structural steel unprimed due to spray-on-fireproofing with a surface preparation SP-3;
b. Steel at Gym Roof and Commons Monitor will be shop primed with rust inhibitive primer with a surface preparation SP-3
c. Daylight monitor and cooling tower will be galvanized
d. Canopy on S-311 will be primer galvanized
Response:
a. Steel prep shall be based on drawing A-006 Fireproofing Plans. Note, steel above 20’-0” not required to be fireproofed.
b. Steel prep shall be based on drawing A-006 Fireproofing Plans. Note, steel above 20’-0” not required to be fireproofed
c. Day light Monitor Steel prep shall be based on drawing A-006 Fireproofing Plan. Note, steel above 20’-0 not required to be fireproofed. All structural steel directly exposed to the weather shall be hot dipped galvanized.
d. Yes, finish coat shall match the Middle school.
30. Can you please provide an erosion and sedimentation control specification along with construction details for the sediment & erosion controls plans?
Response: See Sheet C-501 and C-502 for erosion and sedimentation plans.
31. Can you please provide manufacturers and models for the site furnishings specification section 129300?
Response: Please provide site furnishings that meet the requirements of the plans and specifications.
32. Drawing L-200 shows "modular play structures" that will be relocated upon completion of the new primary school. Please confirm that the one year warranty for playground equipment will begin to run upon their initial use at the temporary school, and will not otherwise be subject to the warranty for temporary facilities under Section 13 42 00 (the total time of use of the temporary facility).
Response: See attached revised drawings. Playground equipment is no longer to be relocated from the temporary trailer facility to the new Primary School.
33. Drawing T-601 Temporary Trailer Riser Diagram calls for 2 Fibers & a CAT3 50 Pair, but I can't find anything showing an existing pipe run or anything requiring an additional pipe run on any contract drawings? This info will be needed to determine lengths of Fiber & CAT3 as well as cost for additional pipe work if necessary.
Response: See attached amended drawing.
34. We see there are metal letters applied to the canopy, but could not find a detail. The section reference on the elevation drawing says section 11 on A401. However we could only find sections 1 thru 10; no 11. We can price these as dimensional letters stud mounted to a solid surface. If they are suspended from the leading edge of the canopy that is another story.
Response: Refer to Detail 3/A-408 canopy details.
35. The specs refer to panel and post exterior signs, some with internal illumination. We could not find anything in the documents indicating these.
Response: Exterior post and panel signage is not required. Exterior illuminated signage is not required. See attached amendment for revisions to Section 10 14 01 EXTERIOR SIGNAGE.
36. While reviewing the construction documents for New Hanscom AFB Primary School, I noticed there isn’t a list of approved manufacturers for visual display boards. Can you provide that list?
Response: Please provide visual display boards that meet the requirements of the plans and specifications.
37. Who will be responsible for the commissioning portion of the above mentioned project?
Response: As stated in Section 01 91 13, the Contractor shall provide the Commissioning Firm and the Commissioning Agent.
38. Drawing A922, Item #2, under “Modular Trailers” states “interior space of existing trailers to be refurbished for use by Primary School.” Please provide the specific scope for “refurbished”.
Response: Refurbishing of existing trailers has been removed from the scope of this contract, see attached amended specification section 13 42 00.
39. Please clarify if we are responsible for only six new panelboards coming from existing trailer panelboards.
Response: All modifications related to the temporary trailers have been deleted from the project including work to provide 6 new panelboards. Sheet E-702 is deleted as part of this amendment.
40. Do we need to carry the 6.25% Massachusetts sales tax on all material purchased for this project?
Response: See Clause 52.229-3(h). The Government will furnish evidence appropriate to establish exemption from any Federal, State, or local tax when the Contractor requests such evidence and a reasonable basis exists to sustain the exemption. Additionally, Contractors are also responsible for the applicability and reporting of any Federal, State or local tax requirements.
41. Can you clarify the technical factor requirements on a "summary section" and how it relates to the key point bullets? Is it your intent to have an upfront summary for each technical factor in bullet form and then lead into the written narratives? The RFP states that we should "reference supporting narrative in the Section and subsequent Sections where relevant." Are these references related to the bullets?
Is this what you're looking for in each section?
Technical Section I Factor I: Technical Experience
* Past project 1 summary. See p. 6
* Past project 2 summary. See p. 8
* Past project 3 summary. See p. 11
Response: See Amendment 8, amended sections L & M below.
INSTRUCTIONS AND EVALUATION
A. PROPOSAL SUBMISSION (Section L)
b. File Packaging. The sentence “All price breakdown information to aide in the price evaluation shall be submitted in Microsoft Office Excel Read/Write format and viewable in Microsoft Excel 2007,” is deleted in its entirety.
c. Content Requirement (Amendment 2, Pages 8-9):
(i) VOLUME I The volume shall be organized into the following sections:
(1) Technical Section 1 – Factors 1. The offeror’s Technical Experience. The proposal shall bulletize key points and reference supporting narrative in the Section and subsequent Sections where relevant. Each Section shall be separated with a tab. The following is provided as an example:
• KEY POINT #1
• KEY POINT #2
• KEY POINT #3
(2) Technical Section 2 – Factor 2. This factor evaluates the offeror’s Management Plan.
The proposal shall bulletize key points. Each Section shall be separated with a tab. The following is provided as an example:
• KEY POINT #1
• KEY POINT #2
• KEY POINT #3
Is deleted in its entirety and replaced as shown below:
(i) VOLUME I The volume shall be organized into the following sections:
Technical Section 1 – Factor 1.
Factor 1. Provide at least two (2), and no more than five (5) projects, physically or substantially completed within the last ten (10) years demonstrating construction of new school buildings, and specialty spaces such as cafeteria, classrooms, gymnasium, science laboratories, and administrative space, completed within the last ten (10) years. Projects exceeding the limit of five will not be evaluated.
Projects must demonstrate experience with all of the following activities. Offerors that submit single projects that individually demonstrate all of the following activities may be more highly rated:
• Construction on Active School Campus – Show experience constructing a building on an active school campus, with students, bus traffic, and operating classrooms within close proximity to the construction area;
• Demolition of structures in constricted areas where the abatement of hazardous materials such as asbestos and lead was necessary prior to beginning structure demolition;
• Connecting to existing structure(s) and utilities;
• Participating in the construction of LEED-certified projects (silver or better) and in those that achieved LEED certification.
Descriptions of each project shall also include:
a. Location of project.
b. A detailed description of the project; i.e., size of building (sq. ft), cost of the project, types of construction, and dates of contract performance.
NOTE: “Physically complete” means 100% completion and the work in the field is done. “Substantially complete” means Beneficial Occupancy has occurred.
Factor 2 is revised as follows:
The Offeror must submit a Management Plan that effectively demonstrates the Offeror’s approach and ability to manage the work and sub-contractors, resulting in a quality project. The work has one
(1) major milestone which must be achieved: the completion of the newly constructed Primary School within 800 calendar days after Notice to Proceed. This must be accomplished without disrupting school activities (such as parking, traffic, academic or extra-curricular). For purposes of preparing a proposal, the Offeror shall assume access to the site will be made available on/about 17 October 2016.
The Management Plan is to include a narrative of the Offeror’s approach to on- and off-site administration in executing the scope of work, including: a schedule; organizational chart(s); a quality control narrative; and the key personnel responsible for the effort.
The management plan shall show how the newly constructed primary school will be completed by 900 calendar days from the Notice to Proceed. In addition, offerors shall present their plan for managing their schedule, consistent with their graphical schedule required below. For purposes of preparing a proposal, the Offeror shall assume: a Notice to Proceed of 15 September 2016; also assume substantial completion on calendar day 800, and that Government vacates the temporary trailers on calendar day 860, at which point the contractor may begin removal or demolition of temporary trailers. The aforementioned dates are for Proposal preparation purposes only.
Schedule
The Offeror shall submit a graphical representation of the schedule for construction.
The schedule shall show features of work and a critical path, and include: Takeover of Operation and Maintenance (O & M) of temporary trailers; superstructure construction complete; permanent power complete; building systems commissioning complete; project completion (Notice to Proceed plus 900 calendar days); quality control turnover inspection requirements; and any other Offeror-proposed milestones.
Organizational Chart(s)
The Offeror shall submit organizational chart(s) for the project which includes the key prime contractor personnel (as described in the Key Personnel section below), Project Executive(s), any additional Offeror personnel proposed, and any subcontractor disciplines (with company names, where available) proposed to be used on this project with their assigned roles. Offeror’s personnel are to be identified by name and position, while the sub-contractor corporate firm names and discipline are to be identified on the organizational chart(s). Personnel and firms shall be identified by name, position/discipline and physical location during the course of the work. The organizational chart(s) shall clearly indicate reporting and communication lines.
Quality Control Narrative
The Offeror shall submit a Quality Control Narrative which discusses the offeror’s approach to ensuring the quality of the work, not only on primary school but work involved with the temporary classrooms. This Narrative is to include all quality control processes involved with the planning and completion of the work from selecting qualified sub-contractors up to acceptance and physical completion of the work.
Key Personnel
The Key Personnel are defined as: Project Manager, Site Superintendent, Site Safety and Health Officer, Contract Quality Control Manager and Commissioning Agent. Each of the Key Personnel positions shall be held by separate personnel. The Offeror shall provide the resumes of their key personnel. Résumés, using the format in, or containing the information requested in the appended Key Personnel Qualifications Summary, shall be provided for all Key Personnel, including name, employee’s position title and description, education, and qualifying academic, design, construction, Professional Registration and Government experience.
Discipline Registration * Relevant Experience Required (years)*
Project Manager -- 8 Site Superintendent -- 10 Site Safety and Health Officer OSHA 30 5 Contract Quality Control Supervisor -- 8 Commissioning Specialist -- 10
*Contractor to provide Personnel Qualifications to support qualification. Résumés, using the appended format in, or containing the respective information requested in Appendix D, shall be provided for all Key Personnel, including name, employee’s position description, education, and qualifying academic, design, construction, Professional Registration and Government experience.
To receive a rating of “Acceptable”, Key personnel must meet the relevant experience requirement above. Relevant Experience is considered to be experience on projects of the same size, scope, price and complexity.
AMENDMENT 2, FACTOR 1, TECHNICAL EXPERIENCE, (Section M) is revised as follows.
D. FACTORS TO BE EVALUATED
FACTOR 1 – TECHNICAL EXPERIENCE (Amendment 2, Page 11)
Delete “Provide at least two (2), and no more than five (5) projects completed within the last ten
(10) years demonstrating experience with all of the following activities.”
Also delete second bullet, “Providing Temporary Space – Show experience providing temporary space (temporary modular classroom facilities, office space, working areas) including the provision of all necessary utilities, access and parking which are similar to this Hanscom Air Force Base (HAFB) Primary School (PS) project Temporary Space in size and scope;”
Evaluation Criteria for Factor 1:
Evaluation Criteria is revised as shown in bold type below: Factor 1 will be evaluated and rated using an adjectival, combined technical/risk rating, in accordance with Table 1, in the Evaluation Approach Section below. The combined technical/risk rating includes consideration of risk in conjunction with the strengths, weaknesses, and deficiencies in determining technical ratings. Factor 1 will be evaluated first, on whether the Offeror’s past projects are relevant and recent to the work under the RFP. Relevancy will be determined by similarity of projects completed (physically or substantially completed) within the past ten (10) years that are similar to this solicitation in size, scope, price, and complexity. Documentation that demonstrates completion (physically or substantially complete) of at least (2) projects similar in size, scope, price, and complexity to this Hanscom Primary School project and collectively address the four activities above will be considered to have met the minimum requirements of the RFP.
FACTOR 2 –MANAGEMENT PLAN (Amendment 2, Factor 2, pages 11-12) is deleted in its entirety and replaced with the following:
The Offeror must submit a Management Plan that effectively demonstrates the Offeror’s approach and ability to manage the work and sub-contractors, resulting in a quality project. The management plan must demonstrate the following:
The Offeror’s Management Plan will be evaluated on sequencing of activities to maximize efficiency, The schedule must demonstrate a reasonable and realistic approach to the work and duration of the tasks (to include the critical path and relationships between activities).
An organizational chart that clearly depicts a qualified on-site team supported by appropriate resources off-site and a description that clearly defines an organizational approach to managing this contract and responsibilities of key personnel;
A quality control narrative that is complete, concise, and relevant.
Key personnel must meet the relevant experience requirement above. Relevant experience is considered to be experience on projects of the same size, scope, price and complexity.
Evaluation Criteria, Factor 2, (Amendment 2, page 13) remains the same.
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
AMENDMENT 0008 OF SOLICITATION
1.1 CHANGES TO SOLICITATION OFFER AND AWARD
1.2 CHANGES TO SPECIFICATIONS
1.2.1 Revised and Reissued Specification Sections
1.2.2 Narrative Changes to the Specifications
1.3 CHANGES TO CONTRACT DRAWINGS
1.3.1 Revised and Reissued Contract Drawings
1.3.2 Deleted Drawings
-- End of Section Table of Contents --
AMENDMENT 0008 OF SOLICITATION
1.1 CHANGES TO SOLICITATION OFFER AND AWARD
1. Bid Schedule; Delete Bid Schedule (from Amendment 3) and replace with revised Bid Schedule (dated June 2016) attached.
1.2 CHANGES TO SPECIFICATIONS
1.2.1 Revised and Reissued Specification Sections
1. Section 13 42 00; delete this specification section in its entirety and replace with new Section 13 42 00, dated June 2016, copy attached.
1.2.2 Narrative Changes to the Specifications
1. Section 01 00 00 GENERAL REQUIREMENTS, Subpart 1.7.4.B.1; Delete subparagraphs a through f in their entirety.
2. Section 01 00 00 GENERAL REQUIREMENTS, Subpart 1.7.4.B.1; Change subparagraph i to read: ‘‘i. Upon the determination of substantial completion of the new school by the Contracting Officer, the Contractor shall allow 60 days for the Government to vacate the Swingspace trailer facility prior to beginning removal and disposal or demolition of the temporary trailer facility and restoration of the site. For proposal preparation purposes, assume that substantial completion will occur no later than 800 calendar days after notice to proceed.’’
3. Section 01 22 00 MEASUREMENT AND PAYMENT, Subpart 1.2, subparagraph a;
replace subparagraph a with the following:
‘‘a. Item 0001: Construction of Primary School Including Removal and Disposal, or Demolition, of all Temporary Trailers and Restoration of the Sites
All costs for labor, equipment, and materials for construction of the Primary School, complete, in accordance with the contract drawings and specifications, with the exception of the work included in Optional Bid Items 0002 through 0016 below. This item includes excavation and off-site disposal of unsatisfactory soils, replacement of unsatisfactory soil with satisfactory fill materials or engineered fill from off-site, and removal and disposal of asbestos containing materials (cement panels, window glazing compound and courtyard window glazing compound, exterior windows caulking, exterior doors caulking, courtyard windows caulking, floor tile mastic, mud pipe fittings, and in-slab cement ventilation ducts). This item also includes removal and disposal, or demolition, of the existing temporary trailers, associated playground areas and equipment, and associated utilities and restoration of the site as shown on the contract drawings.’’
4. Section 01 22 00 MEASUREMENT AND PAYMENT, Subpart 1.2, subparagraph n;
replace subparagraph n with the following:
‘‘n. Item 0014: Playground Equipment at New Primary School
All costs for labor, equipment, and materials for furnishing and installing new playground equipment at the new Primary School as indicated on the contract drawings and in the specifications.’’
5. Section 05 12 00 STRUCTURAL STEEL, Subpart 1.7.7.2; in subparagraph a, replace ‘‘ASCE’’ with ‘‘CSE’’.
6. Section 06 20 00 FINISH CARPENTRY, Subpart 2.8.4.1; replace ‘‘Custom grade’’ with ‘‘Premium grade’’.
7. Section 07 21 13 BOARD AND BLOCK INSULATION, Subpart 3.5.2; replace the wording of this subparagraph with the following:
Provide insulation horizontally under slab on grade for a distance of 2 feet from the edge of slab. Install insulation on top of vapor retarder.
8. Section 10 14 01 EXTERIOR SIGNAGE; Delete Subpart 2.1 in its entirety including all subparagraphs.
9. Section 10 14 01 EXTERIOR SIGNAGE; Delete Subpart 2.2 in its entirety.
10. Section 10 14 02 INTERIOR SIGNAGE, Subpart 2.2; Delete subparagraph a in its entirety.
11. Section 10 26 13 WALL AND CORNER GUARDS, Subpart 2.5.1; replace “Type 302 or 304” with “Type 304”.
12. Section 10 28 13 TOILET ACCESSORIES, Subpart 2.2.8; change title of subpart from “Soap Dispenser (SD)” to “Soap Dispenser (TA-13)”.
13. Section 10 28 13 TOILET ACCESSORIES; Delete Subpart 2.2.9 in its entirety.
14. Section 10 28 13 TOILET ACCESSORIES; Delete Subpart 2.2.12 in its entirety.
1.3 CHANGES TO CONTRACT DRAWINGS
1.3.1 Revised and Reissued Contract Drawings
1. The following drawings are revised as indicated and reissued: G-001, C- 501, L-201, L-202, L-203, L-204, A-003, A-004, A-922, ES-101, M-701, and T- 501.
1.3.2 Deleted Contract Drawings
1. The following drawings are deleted: L-200, L-300, A-921, E-401, and E-702.
The following have been modified:
BID SCHEDULE
BIDDING SCHEDULE (Revised June 2016)
Refer to Section 01 22 00 MEASUREMENT AND PAYMENT.
Item Unit Number Description Quantity Unit Price Amount
Base Bid
0001 Construction of Primary School Including Removal and Disposal, or Demolition, of all Temporary Trailers and Restoration of the Site 1 Job Job $
TOTAL BASE BID $
Optional Bid Items
0002 Telescopic Stands (Option #01) 1 Job Job $
0003 Vegetated Roof Assembly at Outdoor Learning Area 2H14 and above Info Center Annex (Option #02)
Job
0004 LED Lighting (Option #03) 1 Job Job $
0005 Exterior Covered Walkway (Option #04) 1 Job Job $
0006 Energy Dashboard (Option #05) 1 Job Job $
0007 Solar Hot Water System (Option #06) 1 Job Job $
0008 Additional Landscape Features (Option #07)
0009 Radiant Floor Heating (Option #08) 1 Job Job $
0010 Courtyard Snowmelt System (Option #09) 1 Job Job $
0011 Additional Operable Partitions
- Solid (Option #10)
0012 Additional Operable Partitions
- Glazed (Option #11)
0013 Classroom Millwork (Option #12) 1 Job Job $
0014 Playground Equipment at New Primary School (Option #13)
0015 Vegetated Roof Assembly at Outdoor Learning Areas C02, 2I14 and 2G12 (Option #14)
W912WJ-16-R-0007
0016 Operable Window Vents (Option #16) 1 Job Job $
TOTAL AMOUNT, OPTIONAL BID ITEMS $
TOTAL AMOUNT, BASE AND OPTIONAL BID ITEMS $
Note 1: Bidders must bid all items. The work will be awarded as a whole to one bidder. Offers will be evaluated and the low bidder determined by the Total Estimated Amount for Line Items 0001 through 0016, including the Base Bid and all of the Optional Items. The minimum work awarded will be the Base Bid work.
Note 2: Line Item Numbers 0002 through 0016 above are Optional Line Items that may, at the option of the Government, be exercised at any time up to 90 days after receipt by the Contractor of the Notice to Proceed. If any or all Optional Items are awarded, no additional calendar days will be added to the project duration.
Note 3: All work shall be completed within the time period specified in Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS, Subpart
"COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR
52.211-10".
-- End of Bidding Schedule --
-- End of Document --
SECTION 00700 - CONTRACT CLAUSES
The following have been added by reference:
52.246-20 Warranty Of Services MAY 2001
(End of Summary of Changes)