REQUEST_FOR_INFORMATION_0007_.pdf

PDF 61 KB Posted

Attached to
Repair Fire Station Bldg. 300 and add to Fire Station Bldg. 300
Solicitation number
W912PQ-15-B-0001
Issued by

About this file

Request for Infomation 0007

View the file

Other files

File Type Posted
2015_01_06_16_08_36.pdf PDF
OF_1419A_Page_2.pdf PDF
OF_1419A_Page_3.pdf PDF
OF_1419.pdf PDF
REQUEST_FOR_INFORMATION_0009.pdf PDF
Gabreski_Airport_Geotechnical_Report_Final_2013-08-07.pdf PDF
REQUEST_FOR_INFORMATION_0008.pdf PDF
RFI__0006.pdf PDF
RFI_0005.pdf PDF
RFI_0004.pdf PDF
ARFS088000.NY11.pdf PDF
RFI_0003_Response.pdf PDF
69623_A-602-rev1.pdf PDF
REQUEST_FOR_INFORMATION_0002.pdf PDF
2014_12_15_12_11_24.pdf PDF
Pre-Bid_Slides_Fire_Station.pptx PPTX presentation
ARFS085113_NY11.pdf PDF
Request_For_Information_(RFI)_0001_Response.pdf PDF
SOLICITATION_AMENDMENT_0002.pdf PDF
CONTRACTOR_REQUEST_FORM_(Master).xlsx XLSX spreadsheet
SOLICITATION_AMENDMENT_0001.pdf PDF
Change_Order_1.pdf PDF
100__IFB_VOL_1_-_SPECS_-_Rev_120214.pdf PDF
100__IFB_VOL_2_-_SPECS_-_Rev_120214.pdf PDF
W912PQ-15-B-0001.pdf PDF
69623-IFB-DRAWING_SET_-_Rev_120214.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

29 December 2014

Q17-Which spec section, 085113 or 084113, applies to window types indicated on A-602.

A17: Spec section 085113 ALUMINUM WINDOWS applies to window types W1, W2, W3, and W4. Spec section 084113 ALUMINUM FRAMED ENTRANCES AND STOREFRONTS applies to Doors 101 and 102 and Window type W5. Window Type W5 is an integral transom with door 101 and should be treated as a single combined aluminum framed storefront entrance system.

Q18- At the top of W1 window units - what do the darkened muntins indicate?

A18: These divided muntins are to be simulated divided lites with spacer bars.

Q19- Existing storefront window at the base are "green painted finish, glazed with blast-resistant insulated reflective glass". The current specifications do not indicate this. Please advise.

A19: The current drawings and specifications do require laminated ‘blast-resistant’

ATFP compliant insulated glazing. The BCE and Contracting Officer is to confirm / select the desired finish color(s). The specifications require to ‘match base standard’.