VOLUME 3 OF 3
RFP NO. W912PL-12-R-0008
U.S. ARMY CORPS
OF ENGINEERS
LOS ANGELES DISTRICT
FORT IRWIN REPLACEMENT HOSPITAL,
FORT IRWIN, SAN BERNARDINO COUNTY,
CALIFORNIA
VOLUME 1 of 3 – BID DOCUMENTS (DIVISION 00) and TECHNICAL SPECIFICATIONS (DIVISION 01 thru
DIVISION 08
VOLUME 2 of 3 – TECHNICAL SPECIFICATIONS (DIVISION 09 thru
DIVISION 23
VOLUME 3 of 3 – TECHNICAL SPECIFICATIONS (DIVISION 26 thru
DIVISION 48
Construction Solicitation and Specifications
FULL & OPEN COMPETITION
DECEMBER 2011
FORT IRWIN HOSPITAL REPLACEMENT 1786
PROJECT TABLE OF CONTENTS
Project Table of Contents 1
VOLUME 1 of 3
COVER SHEET
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 00 10 SF 1442 AND PRICING SCHEDULE
00 01 00 INSTRUCTIONS TO OFFERORS
00 01 10 PROPOSAL SUBMISSION REQUIREMENTS,SELECTION
PROCEDURES AND BASIS OF AWARD
00 06 00 REPRESENTATIONS & CERTIFICATIONS
00 07 00 CONTRACT CLAUSES
00 08 00 SPECIAL CONTRACT CLAUSES
00 08 50 GENERAL WAGE DECISION
00 01 15 LIST OF DRAWINGS
Project Table of Contents 2
VOLUME 1 of 3 (CONT.)
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 LEED(TM) DOCUMENTATION
01 35 16.00 50 CUTTING AND PATCHING PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 QUALITY CONTROL
01 45 00.10 QUALITY CONTROL SYSTEM (QCS)
01 45 35 SPECIAL INSPECTION FOR SEISMIC-RESISTING SYSTEMS
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 58 00 PROJECT IDENTIFICATION
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 31 00.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE
03 45 00 PRECAST ARCHITECTURAL CONCRETE
03 49 00.00 50 GLASS-FIBER-REINFORCED-CONCRETE
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 43 13.00 50 SLOTTED CHANNEL EQUIPMENT SUPPORT FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
05 59 13.00 50 TRELLIS FRAMING SYSTEM
Project Table of Contents 3
05 73 00.00 50 DECORATIVE METAL RAILINGS
05 75 00.00 50 DECORATIVE FORMED METAL
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 61 16 SOLID SURFACING FABRICATIONS
06 64 00.00 50 PLASTIC PANELING FABRICATIONS
06 71 33 FIBERGLASS REINFORCED PLASTIC (FRP) LADDERS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 08 00.00 50 COMMISSIONING OF BUILDING ENVELOPE
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 16 13.00 50 POLYMER MODIFIED CEMENT WATERPROOFING
07 16 16.00 50 CRYSTALLINE WATERPROOFING
07 17 00 BENTONITE WATERPROOFING
07 21 00.00 50 THERMAL INSULATION (SPRAY-APPLIED)
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 13.00 50 SELF-ADHERED AIR AND VAPOR BARRIER MEMBRANE
07 42 13 METAL WALL PANELS
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 54 23.00 50 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
07 55 00 PROTECTED MEMBRANE ROOFING (PMR)
07 60 00 FLASHING AND SHEET METAL
07 72 00.00 50 ROOF ACCESSORIES
07 81 00 SPRAY-APPLIED FIREPROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
07 95 00.00 50 EXPANSION CONTROL
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 13.00 50 ACCESS DOORS AND FRAMES
08 32 13.00 50 ALUMINUM SLIDING SYSTEMS
08 33 13.00 50 COILING COUNTER DOORS
08 33 23 OVERHEAD COILING DOORS
08 34 59 VAULT DOORS AND DAY GATES
08 35 13.26 50 HORIZONTAL SLIDING, ACCORDION-TYPE FIRE DOORS
08 36 13 SECTIONAL OVERHEAD DOORS
08 42 29.23 50 SLIDING AUTOMATIC ENTRANCE DOORS
08 42 43.00 50 ICU/CCU ENTRANCES
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 44 23.00 50 FIRE RATED GLAZED STEEL CURTAIN WALL SYSTEM
08 51 13 ALUMINUM WINDOWS
08 56 59.00 50 SERVICE WINDOW UNITS
Project Table of Contents 4
08 62 00.01 50 UNIT SKYLIGHTS
08 63 00.00 50 METAL-FRAMED SKYLIGHTS
08 71 00 DOOR HARDWARE
08 71 13.00 50 AUTOMATIC DOOR OPERATORS
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
Project Table of Contents 5
VOLUME 2 of 3
DIVISION 09 - FINISHES
09 06 90 COLOR SCHEDULE
09 22 00 METAL SUPPORT ASSEMBLIES
09 23 00 GYPSUM PLASTERING
09 24 23 STUCCO
09 29 00 GYPSUM BOARD
09 30 00 TILING
09 51 00 ACOUSTICAL CEILINGS
09 54 23.00 50 LINEAR METAL CEILINGS
09 65 00 RESILIENT FLOORING
09 65 66 RESILIENT ATHLETIC FLOORING
09 66 23.00 50 RESINOUS TERRAZZO FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 68 00 CARPET
09 69 13 RIGID GRID ACCESS FLOORING
09 78 13.00 50 MODULAR WALL PANEL SYSTEM
09 90 00 PAINTS AND COATINGS
09 97 23.00 50 POTABLE WATER TANK COATING SYSTEM
DIVISION 10 - SPECIALTIES
10 10 00 VISUAL COMMUNICATIONS SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 14 02 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 21 23.16 CUBICLE TRACK AND HARDWARE
10 22 13 WIRE MESH PARTITIONS
10 22 26.33 FOLDING PANEL PARTITIONS
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOILET ACCESSORIES
10 44 00.00 50 FIRE EXTINGUISHERS AND CABINETS
10 51 29.00 50 PHENOLIC LOCKERS
10 71 13.00 50 EXTERIOR SUN CONTROL DEVICES
10 73 26.00 50 WALKWAY COVER SYSTEM
10 90 00.00 50 MISCELLANEOUS SPECIALTIES
DIVISION 11 - EQUIPMENT
11 05 40 COMMON WORK RESULTS FOR FOODSERVICE EQUIPMENT
11 06 40.13 FOODSERVICE EQUIPMENT SCHEDULE
11 13 10 DOCK LEVELERS
11 41 11 REFRIGERATED AND FROZEN FOOD STORAGE EQUIPMENT
11 42 00 FOOD PREPARATION EQUIPMENT
11 44 00 FOOD COOKING EQUIPMENT
11 46 00 FOOD DISPENSING EQUIPMENT
11 47 00 ICE MACHINES
11 48 00 CLEANING AND DISPOSAL EQUIPMENT
11 52 10.00 50 SIMULATED WATER FEATURE
11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS
11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT
11 71 00 WARMING CABINETS, STERILIZERS, AND ASSOCIATED EQUIPMENT
11 72 13 MEDICAL EQUIPMENT, MISCELLANEOUS
Project Table of Contents 6
VOLUME 2 of 3 (CONT.)
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 35 70 MEDICAL AND DENTAL CASEWORK
12 48 16.00 50 WALK-OFF MAT
12 93 00 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 21 48 PREFABRICATED AUDIOMETRIC ROOMS
13 34 23.00 50 FABRICATED STRUCTURES
13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL AND PLUMBING EQUIPMENT
13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
13 49 19 X-RAY SHIELDING
DIVISION 14 - CONVEYING EQUIPMENT
14 24 00 HYDRAULIC ELEVATORS
14 92 00 PNEUMATIC-TUBE SYSTEM
DIVISION 21 - FIRE SUPPRESSION
21 08 00.00 50 COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
21 12 00 STANDPIPE SYSTEMS
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 21 03.00 10 WET CHEMICAL FIRE EXTINGUISHING SYSTEM
21 22 00.00 40 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 70 PLUMBING, HEALTHCARE FACILITIES
22 08 00.00 50 COMMISSIONING OF PLUMBING SYSTEMS
22 33 30.00 10 SOLAR WATER HEATING EQUIPMENT
22 60 70 GAS AND VACUUM SYSTEMS FOR HEALTHCARE FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST
SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48 VIBRATION CONTROLS FOR HVAC AND PLUMBING PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 08 00.00 50 COMMISSIONING OF HVAC
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 52 46.00 20 LOW PRESSURE WATER HEATING BOILERS
23 57 10.00 10 FORCED HOT WATER HEATING SYSTEMS USING WATER AND STEAM
HEAT EXCHANGERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED AND CONDENSER WATER PIPING SYSTEMS
23 65 00 COOLING TOWERS
23 81 23.00 20 COMPUTER ROOM AIR CONDITIONING UNITS
Project Table of Contents 7
VOLUME 3 of 3
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 01.00 50 COMMISSIONING OF ELECTRICAL SYSTEMS
26 09 13 POWER MONITORING SYSTEM
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 23 00 SWITCHBOARDS AND SWITCHGEAR
26 27 30.00 50 ELECTRIC VEHICLE CHARGING STATIONS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 32 15.00 50 DIESEL-GENERATOR SETS AND PARALLELING SWITCHGEAR
26 32 33.00 10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM ABOVE 15 KVA
CAPACITY
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 01.00 10 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 54 21.00 10 HELIPAD LIGHTING AND VISUAL NAVIGATION AIDS
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 33 99.99 10 INTRABUILDING RADIO ENHANCEMENT SYSTEM
27 41 16.00 50 INTERACTIVE TELEVISION (ITV) SYSTEM
27 51 16 RADIO AND PUBLIC ADDRESS SYSTEMS
27 51 23.10 EMERGENCY CALL STATION SYSTEM
27 52 23.00 50 NURSE CALL (NC) SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 20 01.00 50 ELECTRONIC SECURITY SYSTEM (ESS)
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 31 16 SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL
31 63 29 DRILLED CONCRETE PIERS AND SHAFTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSE
32 12 10 BITUMINOUS TACK COAT
32 12 17 HOT MIX BITUMINOUS PAVEMENT
Project Table of Contents 8
VOLUME 3 of 3 (CONT.)
32 13 11 CONCRETE PAVEMENT FOR HELICOPTER PADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS, PARKING
LOTS, AND SITE FACILITIES
32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS
32 16 13.00 50 INTEGRALLY COLORED CONCRETE SIDEWALKS AND CURBS AND
GUTTERS
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 16 15 CONCRETE BLOCK PAVEMENTS
32 17 24.00 10 PAVEMENT MARKINGS
32 31 30.00 22 ORNAMENTAL ALUMINUM PICKET FENCE AND GATES
32 84 23 UNDERGROUND SPRINKLER SYSTEMS
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 WATER DISTRIBUTION
33 13 00 DISINFECTING OF WATER UTILITY SYSTEM
33 16 16.00 50 UNDERGROUND WATER UTILITY STORAGE TANKS
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
33 52 10 SERVICE PIPING, FUEL SYSTEMS
33 56 10.01 FACTORY-FABRICATED SEWAGE CONTAINMENT TANKS
33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS
33 58 00 LEAK DETECTION FOR FUELING SYSTEMS
33 61 00 PREFABRICATED UNDERGROUND HEATING/COOLING DISTRIBUTION
SYSTEM
33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 34 - TRANSPORTATION
34 71 13.19 DROP ARM GATE AND ACCESS CONTROL SYSTEM
DIVISION 48 - ELECTRICAL POWER GENERATION
48 14 00.00 50 PHOTOVOLTAIC ENERGY EQUIPMENT
-- End of Project Table of Contents --
SECTION 26 00 00.00 20
BASIC ELECTRICAL MATERIALS AND METHODS
07/06
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D 709 (2001; R 2007) Laminated Thermosetting Materials
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2007; TIA 2007-1; TIA 2007-2; TIA 2007-3;
TIA 2007-4; TIA 2007-5) National Electrical Safety Code
IEEE Std 100 (2000) The Authoritative Dictionary of IEEE Standards Terms
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250 (2008) Enclosures for Electrical Equipment (1000 Volts Maximum)
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2011) National Electrical Code
1.2 RELATED REQUIREMENTS
This section applies to certain sections of Division 11, EQUIPMENT, Division 13, SPECIAL CONSTRUCTION, and Division 14, CONVEYING EQUIPMENT and Divisions 22 and 23, PLUMBING and HEATING VENTILATING AND AIR CONDITIONING.
This section applies to all sections of Division 26 and 33, ELECTRICAL and UTILITIES, of this project specification unless specified otherwise in the individual sections. This section has been incorporated into, and thus, does not apply to, and is not referenced in the following sections.
Section 26 23 00 SWITCHBOARDS AND SWITCHGEAR Section 26 51 00 INTERIOR LIGHTING Section 26 56 00 EXTERIOR LIGHTING Section 27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM Section 33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND Section 33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT
1.3 DEFINITIONS
a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE Std 100.
SECTION 26 00 00.00 20 Page 1
b. The technical sections referred to herein are those specification sections that describe products, installation procedures, and equipment operations and that refer to this section for detailed description of submittal types.
c. The technical paragraphs referred to herein are those paragraphs in PART 2 - PRODUCTS and PART 3 - EXECUTION of the technical sections that describe products, systems, installation procedures, equipment, and test methods.
1.4 ELECTRICAL CHARACTERISTICS
Electrical characteristics for this project shall be 12.47 kV primary, three phase, 60 Hz, and 480 volts secondary, three phase, four wire. Final connections to the power distribution system at the existing substations shall be made by the Southern California Edison (SCE).
1.5 ADDITIONAL SUBMITTALS INFORMATION
Submittals required in other sections that refer to this section must conform to the following additional requirements as applicable.
1.5.1 Shop Drawings (SD-02)
Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Wiring diagrams shall identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Drawings shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices.
1.5.2 Product Data (SD-03)
Submittal shall include performance and characteristic curves.
1.6 QUALITY ASSURANCE
1.6.1 Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Equipment, materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.
1.6.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been on sale on
SECTION 26 00 00.00 20 Page 2 the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in the technical section.
1.6.2.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.6.2.2 Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site shall not be used, unless specified otherwise.
1.7 WARRANTY
The equipment items shall be supported by service organizations which are reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.
1.8 POSTED OPERATING INSTRUCTIONS
Provide for each system and principal item of equipment as specified in the technical sections for use by operation and maintenance personnel. The operating instructions shall include the following:
a. Wiring diagrams, control diagrams, and control sequence for each principal system and item of equipment.
b. Start up, proper adjustment, operating, lubrication, and shutdown procedures.
c. Safety precautions.
d. The procedure in the event of equipment failure.
e. Other items of instruction as recommended by the manufacturer of each system or item of equipment.
Print or engrave operating instructions and frame under glass or in approved laminated plastic. Post instructions where directed. For operating instructions exposed to the weather, provide weather-resistant materials or weatherproof enclosures. Operating instructions shall not fade when exposed to sunlight and shall be secured to prevent easy removal or peeling.
1.9 MANUFACTURER'S NAMEPLATE
Each item of equipment shall have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.
SECTION 26 00 00.00 20 Page 3
1.10 FIELD FABRICATED NAMEPLATES
ASTM D 709. Provide laminated plastic nameplates for each equipment enclosure, relay, switch, and device; as specified in the technical sections or as indicated on the drawings. Nameplates shall be melamine plastic, 0.125 inch thick, white with colors as indicated. Surface shall be matte finish. Corners shall be square. Accurately align lettering and engrave into the core. Minimum size of nameplates shall be one by 2.5 inches. Lettering shall be a minimum of 0.25 inch high normal block style.
1.11 ELECTRICAL REQUIREMENTS
Electrical installations shall conform to IEEE C2, NFPA 70, and requirements specified herein.
1.12 INSTRUCTION TO GOVERNMENT PERSONNEL
Where specified in the technical sections, furnish the services of competent instructors to give full instruction to designated Government personnel in the adjustment, operation, and maintenance of the specified systems and equipment, including pertinent safety requirements as required.
Instructors shall be thoroughly familiar with all parts of the installation and shall be trained in operating theory as well as practical operation and maintenance work. Instruction shall be given during the first regular work week after the equipment or system has been accepted and turned over to the Government for regular operation. The number of man-days (8 hours per day) of instruction furnished shall be as specified in the individual section.
When more than 4 man-days of instruction are specified, use approximately half of the time for classroom instruction. Use other time for instruction with equipment or system. When significant changes or modifications in the equipment or system are made under the terms of the contract, provide additional instructions to acquaint the operating personnel with the changes or modifications.
1.13 COORDINATION
Coordinate the electrical requirements of all miscellaneous equipment, medical equipment, modular furniture systems and mechanical equipment with the actual equipment being supplied for the project prior to rough-in.
Notify the contracting officer of any discrepancies between the contract drawings and the actual equipment being supplied. Where the electrical characteristics of the supplied equipment deviate from the values as specified on the contract documents, the equipment supplier shall bare the cost of any associated electrical changed required to supply the equipment.
PART 2 PRODUCTS
2.1 FACTORY APPLIED FINISH
Electrical equipment shall have factory-applied painting systems which shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance test and the additional requirements specified in the technical sections.
PART 3 EXECUTION
3.1 FIELD APPLIED PAINTING
Painting shall be as specified in Section 09 90 00 PAINTS AND COATINGS.
SECTION 26 00 00.00 20 Page 4
3.2 FIELD FABRICATED NAMEPLATE MOUNTING
Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.
3.3 WARNING SIGN MOUNTING
Provide the number of signs required to be readable from each accessible side, but space the signs a maximum of 30 feet apart.
3.4 CONSTRUCTION WASTE MANAGEMENT
Comply with the Waste Management Plan specified in Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT for additional requirements.
-- End of Section --
SECTION 26 00 00.00 20 Page 5
SECTION 26 05 48.00 10
SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
10/07
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 325 (2005) Steel Construction Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-310-04 (2007; Change 1) Seismic Design for Buildings
UNDERWRITERS LABORATORIES (UL)
UL 1598 (2008; R 2006 thru 2010) Luminaires
1.2 SYSTEM DESCRIPTION
1.2.1 General Requirements
The requirements for seismic protection measures described in this section shall be applied to the electrical equipment and systems listed below.
Structural requirements shall be in accordance with Section 13 48 00
SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT.
1.2.2 Electrical Equipments
Electrical equipment shall include the following items to the extent required on the drawings or in other Sections of these specifications:
Control Panels Switchgear Light Fixtures Motor Control Centers Switchboards (Floor Mounted) PV Panels and associated equipment Cable Tray Automatic Transfer Switches UPS Units Transformers Freestanding Equipment Cabinets and Racks
1.2.3 Electrical Systems
Electrical systems shall be installed as required on the drawings and other sections of these specifications and shall be seismically protected in accordance with this specification.
SECTION 26 05 48.00 10 Page 1
1.2.4 Contractor Designed Bracing
The Contractor shall design the bracing in accordance with UFC 3-310-04 and additional data furnished by the Contracting Officer. Resistance to lateral forces induced by earthquakes shall be accomplished without consideration of friction resulting from gravity loads. UFC 3-310-04 uses parameters for the building, not for the equipment in the building;
therefore, corresponding adjustments to the formulas shall be required.
Loadings determined using UFC 3-310-04 are based on strength design;
therefore, AISC 325 shall be used for the design. The bracing for the following electrical equipment and systems shall be developed by the Contractor.
1.3 EQUIPMENT REQUIREMENTS
1.3.1 Rigidly Mounted Equipment
The following specific items of equipment: to be furnished under this contract shall be constructed and assembled to withstand the seismic forces specified in UFC 3-310-04. Each item of rigid electrical equipment shall be entirely located and rigidly attached on one side only of a building expansion joint. Piping, electrical conduit, etc., which cross the expansion joint shall be provided with flexible joints that are capable of accommodating displacements equal to the full width of the joint in both orthogonal directions.
Engine-Generators Transformers Switch Boards and Switch Gears Motor Control Centers Free Standing Electric Motors Battery Racks Cable Tray Automatic Transfer Switches UPS Units Freestanding Equipment Cabinets and Racks
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Lighting Fixtures in Buildings Equipment Requirements
Detail drawings along with catalog cuts, templates, and erection and installation details, as appropriate, for the items listed.
Submittals shall be complete in detail; shall indicate thickness, type, grade, class of metal, and dimensions; and shall show construction details, reinforcement, anchorage, and installation with relation to the building construction.
SD-03 Product Data
SECTION 26 05 48.00 10 Page 2
Lighting Fixtures in Buildings; G, RO
SD-05 Design Data
Equipment Requirements; G, RO
Submit design calculations with the detail drawings. Calculations shall be signed and sealed by qualified structural Professional Engineer responsible for their preparation, and shall verify the capability of structural members to which bracing is attached for carrying the load from the brace.
Contractor Designed Bracing; G, RO
Submit design calculations with the Drawings. Calculations shall be signed and sealed by qualified Structural Engineer responsible for their preparation. Calculations shall verify the capability of structural members to which bracing is attached for carrying the load from the brace.
PART 2 PRODUCTS
2.1 LIGHTING FIXTURE SUPPORTS
Lighting fixtures and supports shall conform to UL 1598.
2.2 SWAY BRACING MATERIALS
Sway bracing materials (e.g. rods, plates, angles, etc.) shall be as specified in Section 13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS
EQUIPMENT.
PART 3 EXECUTION
3.1 SWAY BRACES FOR CONDUIT
Conduit shall be braced as for an equivalent weight pipe in accordance with Section 13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT.
3.2 LIGHTING FIXTURES IN BUILDINGS
Lighting fixtures and supports shall conform to the following:
3.2.1 Pendant Fixtures
Pendant fixtures shall conform to the requirements of UFC 3-310-04, and shall be sway braced as required.
3.2.2 Ceiling Attached Fixtures
3.2.2.1 Recessed Fluorescent Fixtures
Recessed fluorescent individual or continuous-row mounted fixtures shall be supported by a seismic-resistant suspended ceiling support system built in accordance with Section 09 51 00 ACOUSTICAL CEILINGS. Seismic protection for the fixtures shall conform to the requirements of UFC 3-310-04.
Recessed lighting fixtures not over 56 pounds in weight may be supported by and attached directly to the ceiling system runners using screws or bolts, SECTION 26 05 48.00 10 Page 3 number and size as required by the seismic design, and shall have at least two slack #12 safety wires attached to diagonal corners of the fixture. If the fixture weighs more than 56 pounds, it must be supported by four taut #12 suspension wires attached directly to the structure above. Fixture accessories, including louvers, diffusers, and lenses shall have lock or screw attachments.
3.2.2.2 Surface-Mounted Fluorescent Fixtures
Surface-mounted fluorescent individual or continuous-row fixtures shall be attached to a seismic-resistant ceiling support system built in accordance with Section 09 51 00 ACOUSTICAL CEILINGS. Seismic protection for the fixtures shall conform to the requirements of UFC 3-310-04.
3.2.3 Assembly Mounted on Outlet Box
A supporting assembly, that is intended to be mounted on an outlet box, shall be designed to accommodate mounting features on 4 inch boxes, plaster rings, and fixture studs.
3.2.4 Wall-Mounted Emergency Light Unit
Attachments for wall-mounted emergency light units shall be designed and secured for the worst expected seismic disturbance at the site.
3.2.5 Lateral Force
Structural requirements for light fixture bracing shall be in accordance with Section 13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT.
3.3 CONSTRUCTION WASTE MANAGEMENT
Comply with the Waste Management Plan specified in Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT for additional requirements.
SECTION 26 05 48.00 10 Page 4
SECTION 26 08 01.00 50
COMMISSIONING OF ELECTRICAL SYSTEMS
02/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED (2002; R 2007) Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC), Version 2009
1.2 SUMMARY
This project will have selected building systems commissioned. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS. A Commissioning Agent (CA) appointed by the Government will direct the commissioning process.
1.2.1 This Section Includes
Requirements for commissioning the Electrical systems, sub-systems and equipment. This Section supplements the general requirements specified in Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS.
1.2.2 Commissioning Activities
a. The commissioning activities have been developed to support the United States Green Building Council (USGBC) LEED™ rating program and to support delivery of project performance in accordance with the Contract Documents.
(1) Commissioning activities and documentation for the LEED™ section on "Energy and Atmosphere" prerequisite of "Fundamental Building Systems Commissioning".
(2) Commissioning activities and documentation for the LEED™ section on "Energy and Atmosphere" requirements for the "Enhanced Building System Commissioning" credit.
(3) Activities and documentation for the LEED™ section on "Measurement and Verification" requirements for the Measurement and Verification credit.
1.2.3 Related Sections
Refer to Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
SECTION 26 08 01.00 50 Page 1
1.3 DEFINITIONS
Refer to Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.4 COMMISSIONED SYSTEMS
a. Commissioning of a system or systems specified in this Division 26 is part of the construction process. Documentation and testing of these systems, as well as training of User's Operation and Maintenance personnel, is required in cooperation with and the Commissioning Agent.
b. The following Electrical systems will be commissioned:
(1) Automatic Transfer Switches (Test with associated generator).
(2) Diesel-Generator Sets and Paralleling Switchgear.
(3) Lighting controls (Control system hardware and software, scene settings, zone settings, occupancy sensor interface, and unoccupied cycle control).
(4) Uninterruptible Power Supply Systems and UPS Power Distribution systems (Battery chargers, static and dynamic power generators - i.e. inverters, MG sets, metering and controls, system power displays, and distribution panel circuit breakers).
5. Solar Photovoltaic System (i.e. solar panels, inverters and control system).
6. Helipad Lighting and Visual Navigation Aids.
1.5 SUBMITTALS
a. The commissioning process requires review of selected Submittals.
The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the Contracting Officer prior to forwarding to the Contractor. Refer to Section 01 33 00 SUBMITTAL PROCEDURES for further details.
b. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 13.00 50
GENERAL COMMISSIONING REQUIREMENTS.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 SYSTEMS READINESS CHECKLISTS
The Contractor shall complete Systems Readiness Checklists to verify systems, sub-systems, and equipment installation is complete and systems are ready for Systems Functional Testing. The Commissioning Agent will prepare Systems Readiness Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the Contracting Officer and to the Commissioning Agent for review. The Commissioning Agent may spot-check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and re-submission. If the Commissioning Agent determines
SECTION 26 08 01.00 50 Page 2 that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and re-submission. Refer to Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for System Readiness Checklists, Equipment Startup Reports, and other commissioning documents.
3.2 CONTRACTOR'S TESTS
Contractor tests as required by other sections of Division 26 shall be scheduled and documented. The Commissioning Agent will witness selected Contractor tests. Contractor tests shall be completed prior to scheduling Systems Functional Performance Testing. Prior to scheduling the System Functional performance test, the Contractor shall complete the field testing of the generators with a reactive load bank.
3.3 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the Contracting Officer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will direct and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS, for additional details.
3.4 TRAINING OF OWNER PERSONNEL
Training of User's operation and maintenance personnel is required in cooperation with the Contracting Officer and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. The instruction shall be scheduled in coordination with Contracting Officer after submission and approval of formal training plans. Refer to Section 01 91 13.00 50 GENERAL COMMISSIONING REQUIREMENTS and Division 26 Sections for additional Contractor training requirements.
SECTION 26 08 01.00 50 Page 3
SECTION 26 09 13
POWER MONITORING SYSTEM
11/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C37.90.1 (2002) Standard for Surge Withstand Capability (SWC) Tests for Relays and Relay Systems Associated with Electric Power Apparatus
IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits
IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 61000-4-5 (2005; Errata 2009) Electromagnetic Compatibility (EMC) - Part 4-5: Testing and Measurement Techniques; Surge Immunity Test
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250 (2008) Enclosures for Electrical Equipment (1000 Volts Maximum)
NEMA C12.1 (2008) Electric Meters; Code for Electricity Metering
NEMA C62.61 (1993) Gas Tube Surge Arresters on Wire Line Telephone Circuits
NEMA ICS 1 (2000; R 2005; R 2008) Standard for Industrial Control and Systems: General Requirements
NEMA WC 74 (2006) Standard for 5-46 kV Shielded Power Cable for use in the Transmission and Distribution of Electric Energy
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-232-F (1997; R 2002) Interface Between Data
SECTION 26 09 13 Page 1
Terminal Equipment and Data Circuit-Terminating Equipment Employing Serial Binary Data Interchange
TIA-485-A (1998; R 2003) Electrical Characteristics of Generators and Receivers for Use in Balanced Digital Multipoint System
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
47 CFR 15 Radio Frequency Devices
1.1.1 Related Sections
Section 26 23 00 SWITCHBOARDS AND SWITCHGEAR.
Section 26 27 30.00 50 ELECTRIC VEHICLE CHARGING STATIONS.
Section 26 32 15.00 50 DIESEL-GENERATOR SETS AND PARALLELING SWITCHGEAR.
Section 26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION
SWITCH.
1.2 SYSTEM DESCRIPTION
1.2.1 System Requirements
a. Furnish and install a complete Power Monitoring System (PMS), in compliance with Joint Accreditation of Healthcare Organizations (JCAHO) specifications EC.7.40 and NFPA 99, and NFPA 110, as detailed on the drawings and as described in this specification.
The system is defined to include, but not be limited to commercial, off-the-shelf remote devices for monitoring, intelligent electronic devices (IED's), control and protection, device communication interface hardware, inter-communication wiring, personal computer workstations, software, printer, generator controllers, and ancillary equipment.
b. The Contractor shall demonstrate the system is not a prototype and that similar systems have been field installed and successfully operated for at least three years. The PMS vendor shall have full responsibility for insuring that the PMS system performs as specified.
c. The PMS shall utilize Ethernet Local Area Network (LAN)as the high-speed backbone network that supports direct connection of an unlimited number of personal computer workstations anywhere on the network. One computer workstation shall be provided with the PMS and shall be located in the Central Utility Plant.
d. Each Personal Computer Workstation (PCW) connected to the network shall have web based access to the power monitoring system information. Authorized users shall have the ability to view system information and publish documentation for the required monthly JCAHO testing of the emergency power supply system (EPSS).
e. The Power Monitoring System shall be a subsystem of the Generator SCADA system since common data will be shared between the two systems. The Power Monitoring System and the Generator SCADA
SECTION 26 09 13 Page 2 system shall share the same communication system network. The power monitoring system shall also interfere with the facility's local area network.
1.2.2 System Response Times
a. Any new display shall begin to update the workstation monitor within 2 seconds after being requested. Preformatted displays shall be completely presented within 5 seconds after the request.
b. All calculated values shall be updated from the database, when displayed at the workstation, at least every 15 seconds.
c. Digital status indications, when displayed at the workstation, shall be updated within 15 seconds from the IED.
d. Analog values, when displayed at the workstation shall be updated within 15 seconds from the IED.
1.2.3 System Accuracy and Display
The system shall maintain the specified end-to-end accuracy from sensor to all workstation displays, including the effects of transmitters, transducers, and engineering units conversions, for one year for the applications specified and shall report and display changes in sensed values as specified. The system accuracy and display requirements are as follows:
a. Current: with a range for the specific application ± 1.0 percent of reading; display and print to nearest ampere.
b. Voltage: with a range for the specific application ± 1.0 percent of reading; display and print to nearest volt.
c. Power Factor: 1.0 percent of reading; display and print to nearest hundredth.
d. kWh: with a range for the specific application ± 1.0 percent of reading; display and print to nearest kWh.
e. KW: with a range for the specific application ± 1.0 percent of readings.
f. KVA: with a range for the specific application ± 1.0 percent of reading; display and print to nearest KVA.
g. KVAR: with a range for the specific application ± 1.0 percent of reading; display and print to nearest KVAR.
h. Frequency: ± 0.05 Hz; display and print to nearest 0.1 Hz.
i. Total Harmonic Distortion (THD) in percent for current and voltage, each phase.
j. K-Factor (dimensionless ratio based on harmonic content of current waveform).
k. Special application(s) added by the designer, as needed.
SECTION 26 09 13 Page 3
1.2.4 Electrical Transients and Electromagnetic Interference
1.2.4.1 Power Line Surge Protection
Protect workstation equipment connected to ac circuits from power line surges and meet the requirements of IEEE C62.41.1 and IEEE C62.41.2 location category A3, while equipment is operating. In addition, protect all IEDs to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5, test level 4, while the equipment is operating. Fuses shall not be used for surge protection.
1.2.4.2 Sensor Wiring Surge Protection
Protect all digital and analog inputs of all IEDs against surges induced on sensor wiring to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5, test level 4, while the equipment is operating. Fuses shall not be used for surge protection.
1.2.4.3 Communications Channels Surge Protection
Protect communications equipment against surges induced on its communications channels. Protect communication interfaces to all field equipment to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5, test level 4, while the equipment is operating. Fuses shall not be used for surge protection. Metallic cables and conductors which serve as communications channels between buildings shall have surge protection installed at equipment and additional triple electrode gas surge protectors rated for the application installed at each end, within 3 feet of the building cable entrance. Surge protectors shall meet the requirements of NEMA C62.61.
1.2.5 Workstation Equipment Power Source
Power workstation equipment from an uninterruptible power supply (UPS) as shown. The UPS shall provide 15 minutes of normal operation for all connected equipment.
1.2.6 Communications
The Workstation and associated local area network shall be configured to accept a minimum of 32 TIA-232-F or TIA-485-A data communications channels by way of Ethernet gateways. Each communication channel shall support communication with at least 30 IEDs and shall meet the performance requirements as specified.
1.2.7 Expansion Requirements
Provide workstation hardware and software to accommodate a total of 960 IEDs.
1.2.8 Protocols
The workstation equipment shall include software allowing it to communicate with field equipment using any of the following protocols:
a. MODBUS RTU/ASCII.
SECTION 26 09 13 Page 4
1.2.9 General Requirements for Testing
Perform installation testing of the workstation and field equipment, at the site, including adjustments of the completed system as specified. Provide all personnel, test equipment, instrumentation, and supplies necessary to perform all testing. Give written notification to the Government at least 21 days prior to the PVT, and in no case shall notice be given until after the Contractor has received written Government approval of the specific testing procedures.
1.2.10 Test Procedures and Reports
The procedures shall consist of detailed instructions for test setup, execution, and evaluation of test results. Use the test reports to document results of the tests. Deliver reports to the Government within 7 days after completion of test.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
System and Installation Drawings; G, RO
Include the following:
a. Power monitoring system connection and riser diagrams.
b. Layout plans showing equipment locations and cable routing.
c. Field equipment installation drawings including dimensional drawings of any existing enclosures showing equipment cutouts and mounting locations, and indicating adequate clearance from existing wiring and devices in accordance with manufacturer's recommendations.
d. Instrument transformer wiring and installation drawings.
SD-03 Product Data
Data Package; G, RO
Include the following:
a. Catalog data for workstation equipment demonstrating compliance with specified requirements.
b. Catalog data for field equipment indicating outline and mounting dimensions and schematic external wiring arrangement.
c. Catalog data for instrument transformers demonstrating compliance with specified requirements.
d. Manufacturer's standard installation, setup and operation
SECTION 26 09 13 Page 5 guides for workstation equipment and field equipment, and shall include details of the published open protocol for communications.
SD-06 Test Reports
Performance Verification Test (PVT); G, RO
Submit test procedures for the Performance Verification Test (PVT).
The test procedures shall explain in detail, step-by-step actions and expected results to demonstrate compliance with the requirements of this specification.
SD-07 Certificates
Certifications; G, RO
Provide written certifications that system components meet the requirements specified including:
a. 47 CFR 15
b. IEEE C62.41.1 and IEEE C62.41.2
c. NEMA C12.1
d. NEMA C62.61
e. IEEE C37.90.1 or IEC 61000-4-5
Training Courses; G, RO
SD-10 Operation and Maintenance
Operation and Maintenance Manuals; G, RO
SD-11 Closeout Submittals
Lesson plans and training manuals for the training phases, including type of training to be provided and with a list of reference material shall be submitted for approval as specified.
1.4 ENVIRONMENTAL REQUIREMENTS
a. Workstation and associated equipment shall operate without damage or degradation under the following ambient conditions, unless otherwise noted.
(1) Operating Temperature: 60 to 85 degrees F.
(2) Operating Humidity: 20 to 80 percent, non-condensing.
b. All field equipment shall operate without damage or degradation under the following ambient conditions, unless otherwise noted.
(1) Operating Temperature: 32 to 122 degrees F.
(2) Operating Humidity: 10 to 90 percent, non-condensing.
1.5 MAINTENANCE AND SERVICE
1.5.1 General Requirements
Provide all maintenance services required and equipment necessary to
SECTION 26 09 13 Page 6 maintain the entire system operational, as specified, for a period of 1 year after system acceptance. Maintenance shall include preventive maintenance in addition to repairs, replacements, and adjustments and software updates. Written permission shall be obtained from the Government prior to performing any service work or adjustments which have any impact on facility operations.
1.5.2 Description of Work
The adjustment and repair of the system includes all workstation equipment and field equipment including software updates. Perform each manufacturer's required adjustments and all other work necessary for proper operation as specified.
1.5.3 Service Calls
The Government will initiate service calls when the system is not functioning properly. Provide to the Government a telephone number where the service supervisor can be reached at all times. Service personnel shall be at the site within three working days after receiving a request for service. Restore the system to proper operating condition within seven working days after receiving a request for service.
1.5.4 Records and Logs
Keep records and logs of each maintenance and service task, and organize cumulative records for each major component, and for the complete system chronologically. Maintain a continuous log for all devices on a site-by-site basis containing all initial analog span and zero calibration values and testing of all digital points. Complete logs shall be kept and shall be available for inspection onsite, demonstrating that planned and systematic adjustments and repairs have been accomplished for the system.
Provide the Government with a summary report of the maintenance and service performed during each previous month.
1.5.5 System Modifications
Make any recommendations for system modification as part of maintenance and service in writing to the Government. No system modifications, including operating parameters and control settings, shall be made without prior approval of the Government. Incorporate any modifications made to the system into the system documentation including drawings and manuals.
1.5.6 Software
Provide notices of all software updates and verify operation in the system, if the Government chooses to incorporate the update. These updates shall be accomplished in a timely manner, fully coordinated with system operators, and shall be incorporated into the manuals and software documentation. Install and validate the latest released version of the software, upon receiving written approval by the Government.
1.5.7 Telephone Consultation
Provide up to 40 hours per year of telephone consultation to Government…