QA Responses VA Patient Lifts

69 KB Posted

Attached to
Patient Lift for the VA Hospital
Solicitation number
W912P7-11-B-0006
Issued by

Text of this file

VA Patient Lift AS OF: 6 September 2011 Page 1 of 8

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-11-B-0006

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.

No. RFP Section Question Response

What is the project cost range? Low and high ends?

High end $1,290,000

As of 10:15am 8/24/11 2 Will CADD files be provided to the contractor?

Once awarded, the VA will provide Architectural CADD files of the floor plans. All other files will be pdf only.

As of 10:15am 8/24/11 As of 9:30am 8/31/11

1.6.F

Will a contractor be allowed to store material on site?

No on-site storage allowed. No conex/storage container. Contractors will only be allowed to store material within whatever room they’re currently working, and may stage material a day or two in advance of moving to the next room of work, pending Government approval.

As of 10:15am 8/24/11 4 When do you plan to start construction? The Government plans to start construction in late October/early November.

As of 10:15am 8/24/11 5 Will an offeror be allowed to look at the interstitial space?

The Government will post sample photos of the interstitial space above select rooms, as well as RCPs for the ED and wings 2B and 3B, which should be substantially accurate. Proposals should assume obstruction and conflict with a straight shot.

As of 10:30am 8/24/11 As of 9:30am 8/31/11

Is there a difference in measurement from floor to finished ceiling between the patient bed area and bathrooms?

Yes. Floor-to-ceiling in the patient bed area is approximately 9ft and in the bathrooms it’s approximately 8ft.

As of 10:30am 8/24/11

AS OF: 6 September 2011 Page 2 of 8

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-11-B-0006

For rooms that share an adjoining bathroom, will a patient be required to pass from one bedroom through the bathroom and into the adjoining bedroom?

No, however, if the installation includes that, it will be acceptable.

As of 11:00am 8/24/11

In the ASU pre-Op area, there are 9 beds and only 6 lifts?

Correct. Only 6 lifts will be installed. Five lifts on one side and one lift on the other side (same side as the nursing station).

As of 11:15am 8/24/11

9 1.1.A

In one part of the RFP [Location List] you ask for hoist with scale module, but in another part [General Requirements] you ask for hoist with all modules [scale, service, and carelift management]; please confirm which is correct.

Only the scale module will be required.

As of 9:34am 8/29/11

10 1.5.U, 1.5.O

Please advise what you mean by “Above Ceiling Permit” – apparently a Contractor is required to have this?

An above ceiling permit is not required. A Hot Work Permit will be required for wielding, brazing, etc.

As of 9:34am 8/29/11

11 1.1.A.c

Will the facility be acquiring the tracks or will vendor be required to purchase curtain tracks as part of contract?

The contractor needs to provide all new privacy curtain tracks that need to be installed to assure patient privacy after their patient lift installation.

Read Section 1.1.A.c.

As of 10:07am 8/29/11

12 Does the contract require lateral or transverse railings?

See sketches on Typical Installation dated 8/30/2011

As of 1:11pm 8/29/11

Can you please tell me if this solicitation is set aside for small businesses or SDVO’s only? Are you accepting “Open Market” pricing or Contracted pricing only?

This solicitation is set aside for ALL small businesses. Yes – open market pricing is acceptable.

As of 12:00pm 8/30/11

1.1.A

There is some conflict between the drawings and the room list provided (for example, requesting the track to extend in the bathroom but having no bathroom on the drawings. Echo labs 211 & 215.

Correct. There are no bathrooms in the Echo Labs. We are working to revise the Lift Location List and other data associated with it in the solicitation, as well as any discrepancies between an actual room number and the floor plan.

As of 12:00pm 8/30/11 15 I don't see any indication of room layout requirements (XY or Straight).

See sketches on Typical Installation dated 8/30/2011.

AS OF: 6 September 2011 Page 3 of 8

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-11-B-0006

As of 12:00pm 8/30/11 16 The number of lifts per track can't exceed one. However, there are several requests to have two lifts. Please advise.

Only the double bed patient rooms have this requirement. Each lift should have its own track system, but one joint track leading into the bathroom (where required). This also applies to the Quad room 3B-22.

As of 12:00pm 8/30/11 17 The first set of drawings posted with the solicitation were dated later than the drawings posted in the first amendment.

Which are more accurate?

For B-203 2B and 3B area only, use the floor plans dated 2006. For all other areas of B203 2nd Floor and 3rd Floor, use the 2008 set.

Can a vendor provide two motors per lift to meet the 600lb requirement?

The Government needs to maintain the 600 pound capacity of the patient lift.

The SF VAMC does not have an objection if two motors have to be used to achieve the 600 pound capability.

18 As of 12:00pm 8/30/11

What are the bonding requirements for subject project?

Per FAR 52.228-16 we will be requiring a performance and payment bond. Will be added via amendment.

As of 1:20pm 8/30/11

Sprinkler heads in each room; how far down out of the ceiling do the heads protrude?

Some sprinkler heads are flush with ceiling tiles and some are not. Contractor will be responsible to relocate sprinkler heads as needed.

As of 12:00pm 9/1/11

What type of systems are they expecting in the patient rooms – Straight Rail or Traverse? 2 motors are listed for the double rooms and 4 motors are listed for the Quad room – are they expecting to have a single system over each bed that transfers to the bathrooms?

See sketches on Typical Installation dated 8/30/2011.

For the double bed patient rooms and Quad room, each bed should have its own system, but one joint track leading into the bathroom (where required).

AS OF: 6 September 2011 Page 4 of 8

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-11-B-0006

1.1.A.a

Define what is meant by constant charge?

Is motor required to be charging all along the rail system or can the motor be parked in one location for charging?

Yes the intent is for the motor to be charged all along the rail system. However, VA understands and accepts that, where the rail system transits to the branch rail that goes into the bathroom, there will be a loss of electrical continuity and therefore continuous charging will not be possible in the branch rail portion of a track system.

Is concrete slab Pre or Post Tension?

See structural drawings. The floor slabs are concrete poured over re-bars. B-200 was 1960 era construction and B-203 was 1970 era construction.

As of 12:00pm 9/1/11

Additional Drawings Needed to be able to determine the structural viability of how we can attach the systems, locate obstructions, and locate electrical data:

Electrical drawings for all areas which require patient lifts Structural Drawings and details for buildings 200 and 203

Drawings for Building 200

- GA Building Section – specifically for Room GA-169 – Plan, HVAC, RCP, Electrical, Structural -1A Building Section – specifically for Room 1A-132 – Plan, HVAC, RCP, Electrical, Structural -2A Building Section – specifically for Rooms 105, 139, 143 HVAC, RCP, Electrical, Structural -ED Building Section – Electrical, Structural

Drawings for Building 203

- GB building Section – Plan, HVAC, RCP, Electrical, Structural -1A building Section – Plan, HVAC, RCP, Electrical, Structural -2A building Section – Plan, HVAC, RCP, Electrical, Structural

The Government will not post any MEP drawings in the bidding stage. Due to the many successive remodeling in these buildings, the drawings are inaccurate and do not reflect the actual conditions. The buildings are of typical construction of that era - reinforced concrete slab without steel deck underside; all very obvious when the ceiling tiles are removed. If a vendor were to be that concerned, it can elect to use vertical support columns off the floor instead of hanging from above off embedded anchors. All current installations (Guldmann) are top hung, so it can be done.

AS OF: 6 September 2011 Page 5 of 8

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-11-B-0006

Only “bathroom access” is called for in the bid documents. Can you clarify the location within the bathroom that the rail system needs to provide access to?

Toilet, sink, and shower must be accessible using the patient lift.

As of 4:00pm 9/2/11

Can we occupy more than one room at a time during the construction? In other words, can we be patching a bathroom while we are working in the next room on the schedule? We would generally ask for two rooms at a time to minimize impact to patient care but to allow an efficient working environment

No. The VA may release more than one room for installation, but it would be in completely different wings and/or buildings. All bids shall be based on the one-room-at-a-time basis.

As of 4:00pm 9/2/11

Over all patient beds is an X-Y system requested?

The typical layout sketch issued on the solicitation website is to apply to all locations.

The sketch specified X-Y system in all locations.

As of 4:00pm 9/2/11

28 Are there sample lift layout drawings included with the bid specification?

No

As of 4:00pm 9/2/11

Over all gurneys/bays in ED/ASU/Imaging areas is a straight rail system preferred?

No. X-Y system in all locations per the typical layout sketch.

As of 4:00pm 9/2/11

Will a licensed CA Structural Engineer be required to analyze the proposed lift system and support structure to meet VA and OSHPD requirements and provide structural calculations?

Yes

As of 4:00pm 9/2/11

Will the hospital consider a more efficient use of motors (fewer motors) if we can demonstrate that they will be available and accessible for caregiving staff?

No. Bid shall be for the number of motors specified in the solicitation.

As of 4:00pm 9/2/11

AS OF: 6 September 2011 Page 6 of 8

AS OF: 6 September 2011 Page 7 of 8

AS OF: 6 September 2011 Page 8 of 8

Other files

File Type Posted
Bid abstract W912P7-11-B-0006 - UNOFFICIAL.pdf PDF
SF30 Amendment 0004.pdf PDF
Revised Section B - Pricing Schedule.pdf PDF
Amendment 0003.pdf PDF
QA Responses VA Patient Lifts —
Summary of Docs required in the IFB —
QA Responses VA Patient Lifts —
Typical Installation Sketch 8-30-11.pdf PDF
B203-GB FloorPlan Updated.pdf PDF
FAR 52-228-16.pdf PDF
W912P7-11-B-0006 8-26 —
W912P7-11-B-0006 8-26 —
W912P7-11-B-0006 8-26 —
Amendment 0002.pdf PDF
B203-2A FloorPlan Updated.pdf PDF
B200-2A139 RadiologyFloor Ceiling.pdf PDF
B203-3B —
B200-2A105 Floor Ceiling.pdf PDF
B200-ED Floor.pdf PDF
B200-ED OverflowCeiling.pdf PDF
B203-2B —
B203-3B —
B200-ED OverflowFloor.pdf PDF
B203-3B —
CurtainTrackBobbin.JPG JPG image
B203 Section —
B203-2B —
B200-ED Duct Plan —
B203-2B —
B200-ED Ceiling.pdf PDF
B203-2B61 2B67 Cameras.pdf PDF
Amendment 0001 VA Patient Lift - Drawings.pdf PDF
QA Responses VA Patient Lifts —
W912P7-11-B-0006 8-19.pdf PDF
A2.1 FLOOR PLAN.pdf PDF
SF-203-03AR-THIRD FLOOR.pdf PDF
APPX 2 - Patient Safety Alert Design-Installation Checklist.pdf PDF
SF-200-02AR-Second Floor.pdf PDF
APPX 4 - Investigation Request Worksheet.pdf PDF
APPX 3 - Utility Shutdown —
SF-203-01AR-FIRST FLOOR.pdf PDF
SF-203-02AR-SECOND FLOOR PLAN.pdf PDF
SF-200-01AR-FIRST FLOOR.pdf PDF
APPX 1- Infection Control Guidelines 111W-07.pdf PDF
SF-200-0GAR-Ground Floor.pdf PDF
SF-203-0GAR-GROUND FLOOR.pdf PDF
SF-200-03AR-Third Floor.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .