APPX 1- Infection Control Guidelines 111W-07.pdf

PDF 80 KB Posted

Attached to
Patient Lift for the VA Hospital
Solicitation number
W912P7-11-B-0006
Issued by

About this file

APPX 1

View the file

Other files

File Type Posted
Bid abstract W912P7-11-B-0006 - UNOFFICIAL.pdf PDF
QA Responses VA Patient Lifts —
SF30 Amendment 0004.pdf PDF
Revised Section B - Pricing Schedule.pdf PDF
Amendment 0003.pdf PDF
QA Responses VA Patient Lifts —
Summary of Docs required in the IFB —
QA Responses VA Patient Lifts —
Typical Installation Sketch 8-30-11.pdf PDF
B203-GB FloorPlan Updated.pdf PDF
FAR 52-228-16.pdf PDF
W912P7-11-B-0006 8-26 —
W912P7-11-B-0006 8-26 —
W912P7-11-B-0006 8-26 —
Amendment 0002.pdf PDF
B203-2A FloorPlan Updated.pdf PDF
B200-2A139 RadiologyFloor Ceiling.pdf PDF
B203-3B —
B200-2A105 Floor Ceiling.pdf PDF
B200-ED Floor.pdf PDF
B200-ED OverflowCeiling.pdf PDF
B203-2B —
B203-3B —
B200-ED OverflowFloor.pdf PDF
B203-3B —
CurtainTrackBobbin.JPG JPG image
B203 Section —
B203-2B —
B200-ED Duct Plan —
B203-2B —
B200-ED Ceiling.pdf PDF
B203-2B61 2B67 Cameras.pdf PDF
Amendment 0001 VA Patient Lift - Drawings.pdf PDF
QA Responses VA Patient Lifts —
W912P7-11-B-0006 8-19.pdf PDF
A2.1 FLOOR PLAN.pdf PDF
SF-203-03AR-THIRD FLOOR.pdf PDF
APPX 2 - Patient Safety Alert Design-Installation Checklist.pdf PDF
SF-200-02AR-Second Floor.pdf PDF
APPX 4 - Investigation Request Worksheet.pdf PDF
APPX 3 - Utility Shutdown —
SF-203-01AR-FIRST FLOOR.pdf PDF
SF-203-02AR-SECOND FLOOR PLAN.pdf PDF
SF-200-01AR-FIRST FLOOR.pdf PDF
SF-200-0GAR-Ground Floor.pdf PDF
SF-203-0GAR-GROUND FLOOR.pdf PDF
SF-200-03AR-Third Floor.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS MEDICAL CENTER

San Francisco, California

Medical Center Memorandum No. 111W-07 August 1, 2007 111W/PCJ:mm

SUBJ: INFECTION CONTROL GUIDELINES FOR CONSTRUCTION AND RENOVATION

1. PURPOSE: To prevent the acquisition of nosocomial infections in patients, and to decrease the risk of exposures of employees, visitors, and contractors to infectious hazards during medical center (including community-based outpatient clinics and vet centers) renovation or construction activities.

2. POLICY:

a. All proposed renovation or construction projects shall be evaluated using the Matrix of Precautions for Construction and Renovation (Attachment A). Renovation and construction projects include any project that involves an alteration to the physical environment in such a way as to impact patients, visitors and/or employees, and will include painting.

1) Projects meeting the minimum requirements of Type C or D, as referenced in the above mentioned Matrix, will be reviewed with Infection Control during planning and implementation phases. Projects meeting Type A or B if they are in patient care areas must also be reviewed with Infection Control during planning and implement-tation phases.

2) For all projects requiring the implementation of Class II, III or IV infection control precautions, a signed Infection Control Construction Permit (Attachment B) shall be issued prior to start of construction. Class I requires a permit if the work is being done in a patient care area.

b. Infection Control will participate in meetings and is a member of the weekly Construction

Safety RoundsTeam.

c. All construction workers, including subcontractors and in-house construction personnel, must follow the infection control procedures as described in this guideline.

3. RESPONSIBILITY:

a. The Infection Control practitioners and the Chair of the Infection Control Committee are responsible for updating this policy as necessary, and for the overall implementation of this policy.

b. The Chief, Project Section, Engineering Service, is responsible for appointing Project

Engineers for projects awarded to outside contractors.

MCM 111W-07

c. The Chief, Facilities Section, Engineering Service is responsible for appointing Project Coordinators for in-house construction projects.

d. Project Engineers, (e.g., architects, engineers, in-house coordinators) are responsible for portions of this policy as listed below.

e. The Safety Officer is responsible for portions of this policy as listed below, and ensuring that this policy is adhered to. The Safety Officer has the right to stop any construction project which presents an imminent danger to patients, staff, or visitors. The Infection Control Practitioner will recommend to the Safety Officer or the Chief of Engineering stopping any construction project which presents a specific infection control related violation that could cause deleterious effects to patients, staff or visitors.

f. Infection Control Staff are responsible for portions of this policy as listed below.

g. Contractors are responsible for adhering to their mandated responsibilities as listed below.

4. DEFINITIONS:

a. Construction Project: any construction job which requires moving/breaking of walls, digging of a trench greater than two feet deep, impairment of egress or fire alarm systems, erection of barriers, abatement of hazardous materials, or installation/removal of capital equipment.

b. Pre-Construction Briefing: a meeting to review plans, policies, & procedures, attended by the appropriate Engineering Service, EH&S Staff, contractors, and Project Coordinators, at which time requirements relating to Permit Required Confined Space entry, Lock-Out/Tag-Out, Hot Work Permits, and other safety related issues are reviewed.

c. Project Engineer: A person who serves as the VA focal point for the contractor, and the point of contact for a specific construction project, whose responsibilities include, but are not limited to: completing the Infection Control Permit after performing the EOC Risk Assessment Matrix of Precautions (Attachment A), ordering/purchasing for the project, approval of change orders, daily inspection of sites, providing oversight on the contractors work, coordination with water, electrical, HVAC and gas turn offs.

d. Construction Barrier. Fencing, walls, partitions, or other types of barriers, while temporary in nature must be installed so that they are substantial, and able to effectively secure the construction area from unauthorized access. All construction areas must be posted with appropriate signage and be locked.

5. PROCEDURES:

a. Planning Phase.

1) Infection Control (IC) will attend pre-construction briefings and evaluate the construction or renovation during the design phase of the project. During this time IC will identify specific Infection Control issues that will need to be addressed, prior to the implementation phase of the project.

2) Infection Control will be involved in the planning phases for all type A (only in patient care areas), B, C or D renovation and new construction projects specific to, but not limited to the following major components (schematic design):

a) Number and placement of isolation rooms.

b) Air handling systems.

c) Number and placement of hand washing facilities.

d) Staff and patient traffic patterns for the duration of the project.

e) Relocation decisions regarding patient care areas, storage areas, etc.

f) Water supply and plumbing.

g) Construction waste containment, transport and disposal.

h) Selection and installation of medical equipment as it relates to infection control.

i) Selection of finishes and surfaces that can be effectively cleaned.

j) Accommodation of personal protective equipment (accessibility, security, sanitation, etc.).

k) Storage applicable to APIC Guidelines.

b. Construction Phase.

1) Medical Waste:

a) Hospital staff shall remove any medical waste, including sharps containers, from areas to be renovated or constructed BEFORE the start of the project.

b) Infection Control shall be notified immediately if unexpected medical waste or other infection control issues are encountered.

2) Construction Barriers:

a) Construction or renovation sites must be separated from patient-care areas and critical areas such as SPD and Pharmacy by barriers that keep the dirt and dust inside the work-site. In these areas, anterooms that are entered/exited through will be incorporated to further reduce the spread of dust or debris.

b) The integrity of the barriers must assure a complete seal of the construction area from adjacent areas.

c) Rigid construction barriers or plastic sheeting (4 or 6 mil thickness) shall be used, depending on the location of the project, adjacent uses, and duration of the project. It will be the determination of the Project Coordinator as to the most appropriate type of barrier that will be established, after consultation with the Infection Control Practitioner.

d) Walls will be sealed at the full perimeter to reduce the possibility for dust collection and spread.

3) Environmental Controls:

a) Negative air pressure will be maintained within the construction zone with no disruption of the air systems of the adjacent areas, depending on project location.

b) Constant negative pressure, as required within the construction zone, should be monitored with an alarmed air pressure differential monitor. There should be no recirculation of air, and ventilation filters will be changed as needed.

c) Dust producing debris will be removed in covered carts using specified traffic patterns daily. If window chutes are used, containers will be covered to control dust.

d) "Sticky" or walk-off mats shall be utilized immediately outside Type C and D construction zones to remove dust and soil from shoes, cart wheels, etc. as personnel exit the area. The mats must be large enough to cover the entire exit and are changed/vacuumed whenever necessary. Dampened carpet can also be used if it is maintained properly with intermittent vacuuming and wetting.

e) Exterior window seals must be assured to minimize infiltration of outside excavation debris. Windows will remain closed during the construction /renovation process which is necessary to maintain negative pressure.

f) When using demolition chutes, chute opening must be closed when not in use.

The chute and damper should be sprayed with water, as necessary, to maintain dust control.

g) Control, collection and disposal must be provided for any drain liquid or sludge encountered when demolishing plumbing.

4) Traffic Control:

a) Designated entry and exit procedures will be defined (in conjunction with any necessary Interim Life Safety Measures) for each construction project where applicable. A single designated entry/exit door will be assigned to each construction site with multiple doors to decrease additional dust migration.

b) All egress pathways will be free of debris.

c) To prevent entry of unauthorized personnel in the construction zone, doors will be locked and signage posted.

d) Only designated elevators will be used for construction activities during scheduled times. In buildings with only one elevator, construction debris may be transported via elevator if there are no passengers and the debris is in a covered container.

5) Cleaning:

a) The construction zone entry areas shall be maintained in a clean and sanitary manner to minimize dust generation. The responsibility of this process shall be defined within the established contract if an outside contractor is being utilized. It will be the responsibility of the Chief, Facilities Section, if the construction or renovation is being performed by in-house personnel.

b) The Environmental Management Service will be responsible for routine cleaning of areas adjacent to the construction area and disinfecting the construction area before patients are accepted into the area.

6) Contract Personnel Requirements:

a) Workers in the construction area shall attempt to remove loose soil and debris from clothing and hair prior to exiting the construction zone.

b) Personnel entering sterile/invasive procedure areas will be provided with a disposable jump suit, head covering, and shoe covers, which must be removed prior to exiting the work area.

(1) Tools and equipment must be damp-wiped prior to entry and exit from a sterile and invasive procedure areas.

(2) Should tools and equipment become soiled with blood and body fluids, they will be disinfected with an approved germicide.

(c) Contractors shall receive training on the Bloodborne Pathogen Standard and the

TB Exposure Control Plan before beginning work.

7) Environmental Monitoring: Infection Control, in conjunction with Project/Facilities Sections and Environmental Health and Safety, will plan for environmental monitoring as appropriate for the project.

8) Compliance Monitoring: Medical Center staff (i.e., Project Engineer, Safety Officer, Infection Control) and the contractor (or designee) will conduct compliance monitoring as necessary. The following parameters will be monitored:

a) Air handling.

b) Integrity of barrier walls.

c) Control of dust migration into adjacent areas.

d) Dress code.

e) Environmental control.

f) Noise.

g) Traffic control.

h) Personal protective equipment.

i) Water supply.

c. Completion Phase:

1) After completion of construction, ventilation will meet specifications as mandated by regulatory bodies.

2) The area will be thoroughly cleaned and disinfected before being placed into service.

3) Water supply lines will be flushed before placing newly renovated or constructed areas into service. Infection Control shall be notified prior to flushing.

6. REFERENCES:

Olmsted, R. APIC Infection Control and Applied Epidemiology: Principles and Practices, Mosby Year Book, Inc. 1996

Center for Disease Control and Prevention Healthcare Infection Control Practice Advisory Committee (HICPAC) Draft Guideline for Environmental Infection Control in Healthcare Facilities 2004

APIC State of the Art Report: The Role of Infection Control during Construction in Health Care Facilities- AJIC April 2000

7. RESCISSION: None

Sheila M. Cullen Medical Center Director

Attachments

A - Matrix of Precautions for Construction and Renovation B - Infection Control Construction Permit

VA Medical Center San Francisco

Environment of Care Risk Assessment Matrix of Precautions for Construction & Renovation

Step One:

Using the following table, identify the Type of Construction Project Activity (Type A-D)

TYPE A

Inspection and Non-Invasive Activities.

Includes, but is not limited to:

removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet painting (but not sanding) wall covering, electrical trim work, minor plumbing, and activities which do not generate dust or require cuffing of walls or access to ceilings other than for visual inspection.

TYPE B

Small scale, short duration activities which create minimal dust Includes, but is not limited to:

installation of telephone and computer cabling access to chase spaces cutting of walls or ceiling where dust migration can be controlled.

TYPE C

Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies Includes, but is not limited to:

sanding of walls for painting or wall covering removal of floor coverings, ceiling tiles and casework new wall construction minor duct work or electrical work above ceilings major cabling activities any activity that cannot be completed within a single work shift.

TYPE D

Large scale demolition and construction projects Includes, but is not limited to:

activities which require more than 30 calendar days to complete requires modification or removal of a complete electrical or HVAC system new construction extensive or total (gut) renovation of existing building space.

Attachment A to

Step Two:

Using the following table, identify the Patient Risk Groups that will be affected. If more than one risk group will be affected, select the higher risk group:

Low Risk Medium Risk High Risk Highest Risk Office areas Corridors and stairs Elevators Auditoriums and classrooms/ conference rooms

PICU, Day Hospital, SADH

Hoptel Quarterway Methadone Clinic Nuclear Medicine Physical Therapy/

Occupational Therapy

Bldg. 200 Lobby

MRI

Canteen areas Lab medicine

TCU

E&A, Emergency

Room Cardiology GI Clinic Radiology Podiatry Dermatology Clinic Respiratory Therapy Bldg. 203 Lobby Dental Service Pharmacy –

Inpatient & Outpatient

Inpatient Wards

NHCU

Oncology & Infusion Center

Infectious Disease Clinic

Cardiac Cath Lab

SPD

ICU

Dialysis Bronch Lab Isolation Rooms Operating Rooms Minor Procedures Interventional

Radiology

ASU

PACU

Step Three: Match the

Patient Risk Group (Low, Medium, High, Highest) with the planned….

Construction Project Type (A, B, C, D) on the following matrix, to find the….

Class of Precautions (I, II, III or IV) or level of infection control activities required (found on the following page).

IC Matrix - Class of Precautions: Construction Project by Patient Risk

C o n s t r u c t i o n P r o j e c t T y p e Patient Risk Group Type A Type B Type C Type D LOW Risk I II II III / IV MEDIUM Risk I II III IV HIGH Risk I II III / IV IV HIGHEST Risk II III /IV III / IV IV Note: Signed Infection Control Construction Permit shall be obtained prior to start of work for all projects requiring infection control precautions of any kind.

Description of Required Infection Control Precautions by Class

During Construction Project Upon Completion of Project

C L

A

SS

I

1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace a ceiling tile displaced for visual inspection upon completion of inspection.

C

LA

II

1. Provide active means to prevent airborne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents.

5. Place dust mat at entrance and exit of work area.

6. Remove or isolate HVAC system in areas where work is being performed.

1. Wipe work surfaces with disinfectant.

2. Contain construction waste before transport in tightly covered containers.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Remove isolation of HVAC system in areas where work is being performed.

C

LA

SS

II

I

1. Remove or Isolate HVAC system in area where work is being done to prevent contamination of duct system.

2. Complete all critical barriers (i.e. sheetrock, plywood, plastic) to seal area from non-work area before construction begins.

3. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

4. Contain construction waste before transport in tightly covered containers.

5. Cover transport receptacles or carts. Tape covering unless solid lid.

1. Do not remove barriers from work area until completed project is inspected by the VAMC Safety Officer and Engineering Service.

2. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

3. Vacuum work area with HEPA filtered vacuums.

4. Wet mop area to remove any dust film.

5. Remove isolation of HVAC system in areas where work is being performed.

C L

A

IV

Perform all of the work activities listed for CLASS III in addition to the following precautions listed below.

1. Seal holes, pipes, conduits, and penetrations with appropriate sealant material.

2. Require all personnel to wear cloth or disposable coveralls, masks and shoe covers that are removed and discarded each time they leave the work site.

1. Do not remove barriers from work area until completed project is inspected by the VAMC Safety Officer and Engineering Service.

2. Remove barrier material carefully to minimize spreading of dirt and debris associated with construction.

3. Cover transport receptacles or carts. Tape covering unless solid lid.

4. Contain construction waste before transport in tightly covered containers.

5. Vacuum work area with HEPA filtered vacuums.

6. Wet mop area with disinfectant.

7. Remove isolation of HVAC system in areas where work is being performed.

`VA Medical Center, San Francisco Infection Control Construction Permit

Project Name: Location of Construction:

Project Number: Contractor:

Project Engineer: Construction Start Date:

Phone No: x Construction Completion Date:

YES NO CONSTRUCTION ACTIVITY YES NO INFECTION CONTROL RISK

GROUP

TYPE A: Inspection, non-invasive activity

GROUP 1: Low Risk

TYPE B: Small scale; short duration;

moderate to high levels

GROUP 2: Medium Risk

TYPE C: Activity generates moderate to high levels of dust; requires >1 work shift

GROUP 3: Medium/High Risk

TYPE D: Major duration and construction activities requiring consecutive work shifts

GROUP 4: Highest Risk

Class I 1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Minor demolition for remodeling.

4. In patient care areas obtain Infection Control Permit before construction begins.

Class II 1. Obtain Infection Control Permit before construction begins.

2. Provides active means to prevent air-borne dust from dispersing into atmosphere

3. Water mist work surfaces to control dust while cutting.

4. Seal unused doors with duct tape.

5. Block off and seal air vents.

6. Wipe surfaces with disinfectant.

Class III 1. Obtain Infection Control Permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.

5. Remove barriers from work area only after completed project is thoroughly cleaned by EMS.

6. Vacuum work with HEPA filtered vacuums.

7. Wet mop with disinfectant.

8. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

9. Contain construction waste before transport in tightly covered containers.

10. Cover transport receptacles or carts.

Date:

Initials:

Class IV 1. Obtain Infection Control Permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative pressure within work site utilizing HEPA equipped air filtration units.

5. Seal holes, pipes, conduits, and punctures properly.

6. Construct ante-room and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or have personnel wear cloth or paper coveralls that are removed each time they leave work site.

7. Remove barriers from work area only after completed project is thoroughly cleaned by EMS.

8. Vacuum work with HEPA filtered vacuums.

7. Wet mop with disinfectant.

9. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

10. Contain construction waste before transport in tightly covered containers.

11. Cover transport receptacles or carts.

Initial:

Additional Requirements:

Initial:

Exceptions/additions to this permit are noted by attached memorandum

Permit Requested By: 138D Permit Authorized by: 111W Date: Date:

Attachment B to

SUBJ: INFECTION CONTROL GUIDELINES FOR CONSTRUCTION AND RENOVATION
MCM 111W-07
Small scale, short duration activities which create minimal dust
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies
Large scale demolition and construction projects
Low Risk
Construction Project Type
Type B
During Construction Project

Upon Completion of Project

IC Matrix - Class of Precautions: Construction Project by Patient Risk
Description of Required Infection Control Precautions by Class
`VA Medical Center, San Francisco
Infection Control Construction Permit