About this file

This document is an amendment to a solicitation for the construction of the Department of Public Works Engineering Housing and Maintenance Shop at Camp Santiago Joint Training Center in Salinas, Puerto Rico. The amendment changes the bid opening date from March 22, 2024 to April 9, 2024. It incorporates revised drawings and new specifications for metal composite material wall panels, cantilever rack, and metal canopies. The amendment also includes attachments of soil study results and asbestos and lead studies. Responses to questions submitted via requests for information are provided as well. The scope of work involves providing all labor, materials, equipment, transportation and other incidentals required to complete the general construction as detailed in the statement of work. The agency issuing this solicitation is the Department of the Army National Guard.

View the file

Other files

File Type Posted
OF1419 - Abstract of Offers.pdf PDF
W912LR24B0001 DPW MILCON BID TABULATION-Final.pdf PDF
W912LR24B0001 - Ammendment 003 Modification Summary.pdf PDF
W912LR24B0001 - Ammendment 003 Conform Copy.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 10 56 29.26_Amendment 02_08-Mar-2024.pdf PDF
(Revised) Questions and Answers to RFIs.xlsx XLSX spreadsheet
PRARNG_EHMS_Camp Santiago_DWG A-551_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-630_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG Q-102_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 07 42 13.23_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 10 73 16.13_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG S-503_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-802_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 00 00 00-TOC_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG S-200_Amendment 02_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-572_Amendment 02_08-Mar-2024.pdf PDF
Questions and Answers to RFIs - W912LR-24-B-0001 .xlsx XLSX spreadsheet
PRARNG_EHMS_Camp Santiago_DWG S-200_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 10 73 16.13_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-630_Amendment 01_08-Mar-2024.pdf PDF
W912LR24B0001 - Ammendment 002 (Conform Copy).pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-802_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG S-503_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 07 42 13.23_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-551_Amendment 01_08-Mar-2024.pdf PDF
Geotechnical Report.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 10 56 29.26_Amendment 01_08-Mar-2024.pdf PDF
Lead Based Paint Inspection Report DPW Buildings 38 56 57.pdf PDF
PRARNG_EHMS_Camp Santiago_SPEC 00 00 00-TOC_Amendment 01_08-Mar-2024.pdf PDF
LEAD-BASED PAINT INSPECTION REPORT BLDGs 50 54 55 58.pdf PDF
Asbesto Reports DPW Buildings.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG Q-102_Amendment 01_08-Mar-2024.pdf PDF
PRARNG_EHMS_Camp Santiago_DWG A-572_Amendment 01_08-Mar-2024.pdf PDF
DPW - Pre Proposal Conference Minutes.pdf PDF
W912LR24B0001 - Ammendment 0001.pdf PDF
DPW Site Visit Attendance List 30JAN24.pdf PDF
Site Visit Project Description DPW.pptx PPTX presentation
Pre-Proposal Site Visit Slides - DPW 30JAN24 (003).pptx - Read-Only.pptx PPTX presentation
Attachment 02 - PRARNG EHMS Camp Santiago SPECS Vol 2 of 2 REV 19-July-2023.pdf PDF
Attachement 07 - Municipality of Salinas - Const Tax Exemption.pdf PDF
Attachment 05 - PRARNG Master Plan EA Final Feb 2021.pdf PDF
W912LR-24-B-0001 DPW Solicitation.pdf PDF
Attachement 06 - PRARNG EHMS Camp Santiago DRAWINGS Final 19 July 2023.pdf PDF
Attachment 01 - PRARNG EHMS Camp Santiago SPECS Vol 1 of 2 REV 19-July-2023.pdf PDF
Attachment 04 - PR-EA Master Plan FONSI Final Signed Feb 2021.pdf PDF
Attachment 03 - Environmental Considerations-PCL Legal Translate Final.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0012007181

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project No. 431850; Project Title: Engineering Housing and Maintenance Shop. Camp Santiago, Salinas, PR-This amendment is issued to:

See section 00 20 00 located in the Supplemental Instruction of the SF1442.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Mar-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912LR24B0001

X 9B. DATED (SEE ITEM 11)

09-Jan-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Mar-2024

CODE

USPFO PR 156 MISSION SUPPORT CONTRACTING

200 JOSE A TONY SANTANA AVE

CAROLINA PR 00979-1514

W50S93 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912LR24B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 22-Mar-2024 03:00 PM to 09-Apr-2024 02:00 PM.

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

The following have been added by full text:

CONTINUATION SHEET

Modification Description

Project No. 431850; Project Title: Engineering Housing and Maintenance Shop. Camp Santiago, Salinas, PR-This amendment is issued to:

1.Change the bid opening date from 22 March 2024 to 9 April 2024.

2.Incorporate revised drawings sheets to include:

Revised Sheet A‐551 – Dated 8 March 2024

Revised Sheet A‐571 ‐ Dated 8 March 2024

Revised Sheet A‐630 ‐ Dated 8 March 2024

Revised Sheet A‐802 ‐ Dated 8 March 2024

Revised Sheet Q‐102 ‐ Dated 8 March 2024

Revised Sheet S‐200 ‐ Dated 8 March 2024

Revised Sheet S‐503 ‐ Dated 8 March 2024 3.Revised specifications to include: Revised Spec 00 00 00 – Table of Contents - Dated 8 March 2024, New Spec 07 42 13.23 – Metal Composite Material Wall Panels ‐ Dated 8 March 2024

New Spec 10 56 29.26 – Cantilever Rack ‐ Dated 8 March 2024

New Spec 10 73 16.13 – Metal Canopies ‐ Dated 8 March 2024 4.Incorporate soil study attachment into the solicitation.

5.Incorporate asbestos and lead studies attachment into the solicitation.

6.Upload questions and answers to RFIs in the attachments.

All other terms and conditions remain unchanged.

(End of Summary of Changes)