RFI_MS-012_Specs_02_82_33_-_removal_ _disposal_of_ACM.pdf

PDF 45 KB Posted

Attached to
Construct Engineering Housing Maintenance and Vehicle Maintenance Shops
Solicitation number
W912KN-16-R-0009
Issued by

About this file

Ref RFI MS-012 - Spec 02 82 33 Removal and Disposal of ACM

View the file

Other files

File Type Posted
16-R-0009_Amendment_0001.pdf PDF
Maint_Shop_RFI_Log_thru_RFI_034_(28JUN2016).pdf PDF
MS_RFI_Log_(23JUN2016_(1600)).pdf PDF
16-R-0009_Preproposal_-_2nd_site_visit_-_Maint_Shops.pdf PDF
16-R-0009_Preproposal_sign-in_sheet_-_2nd_site_visit_-_Maint_Shops.docx.pdf PDF
MS_RFI_Log_(23JUN2016_(1200)).pdf PDF
MS_RFI_Log_(22JUN2016_(0830)).pdf PDF
RFI_MS-009_C-103_PLAN_REVISION_16_JUN_2016(2).pdf PDF
RFI_MS-012_Asbestos_Survey_Bldg_demo_Sandy_projects.pdf PDF
16-R-0009_EXHIBIT_C.doc DOC document
RFI_Log_-_Maint_Shops_(Autosaved).pdf PDF
RFI_MS-001_Vehicle_Exhaust_System_pdf.pdf PDF
RFI_Log_-_Maint_Shops_(16JUN2016).pdf PDF
16-R-0009_1442-pg_1 2.pdf PDF
16-R-0009_Preproposal_sign-in_sheet.pdf PDF
16-R-0009_Preproposal_conf_minutes.pdf PDF
Whitman_Report_-_Asbestos_Env'l_Insp_Activities_at_Sea_Girt.pdf PDF
EHMS-VMS_Drawings.pdf PDF
16-R-0009_EXHIBIT_B.pdf PDF
EHMS-VMS_Specs_1_of_2.pdf PDF
16-R-0009_EXHIBIT_D.pdf PDF
16-R-0009_EXHIBIT_C.pdf PDF
16-R-0009_1442_Solicitation.pdf PDF
Geotechnical_Investigation_Report_(May_2014)_Sandy_projects.pdf PDF
16-R-0009_EXHIBIT_A.pdf PDF
EHMS-VMS_Specs_2_of_2.pdf PDF
RFI_Template.doc DOC document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW JERSEY ARMY NATIONAL GUARD 30 SEPTEMBER 2014

SUPERSTORM SANDY DISASTER RESPONSE PROJECT ISSUED FOR CONSTRUCTION

EHMS/FMS, SEA GIRT, NEW JERSEY 100% BID-FINALS SUBMISSION

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 1

SECTION 02 82 33 - REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes requirements for Contractor to prepare an asbestos containing material (ACM) removal and disposal plan. After review and approval of the Plan, Contractor is required to per-form removal of asbestos and dispose of legally.

B. Description of Work: The work covered by this section includes the handling and control of as-bestos containing materials and describes some of the resultant procedures and equipment re-quired to protect workers and the environment from contact with airborne asbestos fibers. The work also includes the disposal of asbestos containing materials generated by the work.

Contractor shall observe all existing conditions prior to submitting a bid. The Contractor shall have considered, and included in their bid, all aspects of the existing conditions and their impact, particularly to cost and health and safety of workers and occupants. Failure to visit the site shall not provide relief from performing any work that may be required to complete the work in accordance with the Contract Documents without additional cost. All site visits required by the Contractor shall be scheduled with NJARNG.

Material information and quantities are documented from the following surveys: Asbestos Survey Building Demolition Superstorm Sandy Projects Report by NJDMAVA dated 25 September 2014, and Asbestos Environmental Inspection Activities Report at Sea Girt by Whitman dated December 2012, and is available as supplemental information. The quantities, locations and the extent of work indicated (within the Survey Reports) are the known quantities.

Contractor shall be responsible for abatement of all elements including third party air monitoring and containment clearance. Variations (plus or minus 10 percent) in quantities within the limits of containment for the work area (as defined within the Report) are considered as having no impact on contract sum and contract performance period. Locations of materials different than indicated within the Report but within the limits of containment are considered as having no impact on contract sum and contract performance period.

1.2 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

1. American Industrial Hygiene Association (AIHA)

a. AIHA Z88.6(2006) Respiratory Protection - Respirator Use-Physical Qualifica-tions for Personnel

b. AIHA Z9.2(2006) Fundamentals Governing the Design and Operation of Local

Exhaust Ventilation Systems

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 2

2. ASTM International (ASTM)

a. ASTM C732(2006) Aging Effects of Artificial Weathering on Latex Sealants.

b. ASTM D2794(1993; R 2010) Resistance of Organic Coatings to the Effects of

Rapid Deformation (Impact).

c. ASTM D522(1993a; R 2008) Mandrel Bend Test of Attached Organic Coatings.

d. ASTM E119(2012) Standard Test Methods for Fire Tests of Building Construction and Materials.

e. ASTM E1368(2011) Visual Inspection of Asbestos Abatement Projects.

f. ASTM E1494(1992; R 2010) Encapsulants for Spray- or Trowel-Applied Friable

Asbestos-Containing Building Materials.

g. ASTM E736(2000; R 2011) Cohesion/Adhesion of Sprayed Fire-Resistive. Mate-rials Applied to Structural Members.

h. ASTM E84(2012) Standard Test Method for Surface Burning Characteristics of

Building Materials.

i. ASTM E96/E96M(2010) Standard Test Methods for Water Vapor Transmission of

Materials.

3. U.S. Environmental Protection Agency (EPA)

a. EPA 560/5-85-024(1985) Guidance for Controlling Asbestos-Containing Materials in Buildings (Purple Book).

4. U.S. National Archives And Records Administration (NARA)

a. 29 CFR 1926.103 Respiratory Protection.

b. 29 CFR 1926.1101 Asbestos.

c. 29 CFR 1926.200 Accident Prevention Signs and Tags.

d. 29 CFR 1926.51 Sanitation.

e. 29 CFR 1926.59Hazard Communication.

f. 40 CFR 61-SUBPART A General Provisions.

g. 40 CFR 61-SUBPART M National Emission Standard for Asbestos.

h. 40 CFR 763 Asbestos.

5. Underwriters Laboratories (UL):

a. UL 586(2009) Standard for High-Efficiency Particulate, Air Filter Units.

1.3 DEFINITIONS

A. ACM: Asbestos Containing Materials.

B. Amended Water: Water containing a wetting agent or surfactant with a maximum surface ten-sion of 2.9 Pa 0.00042 psi.

C. Area Sampling: Sampling of asbestos fiber concentrations which approximates the concentra-tions of asbestos in the theoretical breathing zone but is not actually collected in the breathing zone of an employee.

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 3

D. Asbestos: The term asbestos includes chrysotile, amosite, crocidolite, tremolite asbestos, antho-phyllite asbestos, and actinolite asbestos and any of these minerals that has been chemically treated or altered. Materials are considered to contain asbestos if the asbestos content of the material is determined to be at least one percent.

E. Asbestos Control Area: That area where asbestos removal operations are performed which is isolated by physical boundaries which assist in the prevention of the uncontrolled release of as-bestos dust, fibers, or debris.

F. Asbestos Fibers: Those fibers having an aspect ratio of at least 3:1 and longer than 5 microme-ters as determined by National Institute for Occupational Safety and Health (NIOSH) Method 7400.

G. Asbestos Permissible Exposure Limit: 0.1 fibers per cubic centimeter of air as an 8-hour time weighted average measured in the breathing zone as defined by 29 CFR 1926.1101 or other Federal legislation having legal jurisdiction for the protection of workers health.

H. Background: The ambient airborne asbestos concentration in an uncontaminated area as meas-ured prior to any asbestos hazard abatement efforts. Background concentrations for other (con-taminated) areas are measured in similar but asbestos free locations.

I. Contractor: The Contractor is that individual, or entity under contract to perform the herein listed work.

J. Competent Person: A person meeting the requirements for competent person as specified in 29 CFR 1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the au-thority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which meet the criteria of EPA's Model Accreditation Plan (40 CFR 763) for project designer or supervisor, or its equivalent. The competent person shall have a current State of New Jersey asbestos contractors or supervisors license.

K. Encapsulation: The abatement of an asbestos hazard through the appropriate use of chemical encapsulants.

L. Encapsulants: Specific materials in various forms used to chemically or physically entrap asbes-tos fibers in various configurations to prevent these fibers from becoming airborne. There are four types of encapsulants as follows which must comply with performance requirements as specified herein.

1. Removal Encapsulant (can be used as a wetting agent).

2. Bridging Encapsulant (used to provide a tough, durable surface coating to asbestos con-taining material)

3. Penetrating Encapsulant (used to penetrate the asbestos containing material encapsulat-ing all asbestos fibers and preventing fiber release due to routine mechanical damage)

4. Lock-Down Encapsulant (used to seal off or "lock-down" minute asbestos fibers left on surfaces from which asbestos containing material has been removed).

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 4

M. Friable Asbestos Material: One percent asbestos containing material that can be crumbled, pul-verized, or reduced to powder by hand pressure when dry.

N. Glovebag Technique: Those asbestos removal and control techniques put forth in 29 CFR

1926.1101 Appendix G.

O. HEPA Filter Equipment: High efficiency particulate air (HEPA) filtered vacuum and/or exhaust ventilation equipment with a filter system capable of collecting and retaining asbestos fibers.

Filters shall retain 99.97 percent of particles 0.3 microns or larger as indicated in UL 586.

P. Negative Pressure Enclosure (NPE): That engineering control technique described as a negative pressure enclosure in 29 CFR 1926.1101.

Q. Nonfriable Asbestos Material: Material that contains asbestos in which the fibers have been immobilized by a bonding agent, coating, binder, or other material so that the asbestos is well bound and will not normally release asbestos fibers during any appropriate use, handling, stor-age or transportation. It is understood that asbestos fibers may be released under other condi-tions such as demolition, removal, or mishap.

R. Personal Sampling: Air sampling which is performed to determine asbestos fiber concentrations within the breathing zone of a specific employee, as performed in accordance with 29 CFR 1926.1101.

S. Private Qualified Person (PQP): That qualified person hired by the Contractor to perform the herein listed tasks.

T. Qualified Person (QP): A Registered Architect, Professional Engineer, Certified Industrial Hy-gienist, consultant or other qualified person who has successfully completed training and is therefore accredited under a legitimate State Model Accreditation Plan as described in 40 CFR 763 as a Building Inspector, Contractor/Supervisor Abatement Worker, and Asbestos Project Designer; and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent.

The QP must be qualified to perform visual inspections as indicated in ASTM E1368. The QP shall be appropriately licensed in the State of New Jersey.

U. TEM: Refers to Transmission Electron Microscopy.

V. Time Weighted Average (TWA): The TWA is an 8-hour time weighted average airborne con-centration of asbestos fibers.

W. Wetting Agent: A chemical added to water to reduce the water's surface tension thereby increas-ing the water's ability to soak into the material to which it is applied. An equivalent wetting agent must have a surface tension of at most 2.9 Pa 0.00042 psi.

1.4 PRE-DEMOLITION MEETINGS

A. Pre-Demolition Conference: Conduct conference at Project site.

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 5

1.5 ACTION SUBMITTALS

A. Asbestos Hazard Abatement Plan: Prepare Plan for approval by the Government.

1.6 INFORMATIONAL SUBMITTALS

A. Employee Training Reports.

B. Permits, Licenses and Notifications.

C. Asbestos Disposal Quantity Report.

1.7 QUALITY ASSURANCE

A. Private Qualified Person Documentation: Submit the name, address, and telephone number of the Private Qualified Person (PQP) selected to prepare the Asbestos Hazard Abatement Plan, di-rect monitoring and training, and documented evidence that the PQP has successfully completed training in and is accredited and where required is certified as, a Building Inspector, Contrac-tor/Supervisor Abatement Worker, and Asbestos Project Designer as described by 40 CFR 763 and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The PQP shall be appropriately licensed in the State of New Jersey. The PQP and the asbestos con-tractor shall not have an employee/employer relationship or financial relationship which could constitute a conflict of interest. The PQP shall be a first tier subcontractor.

B. Competent Person Documentation: Submit training certification and a current State of New Jer-sey Asbestos Contractor's and Supervisor's License.

C. Worker's License: Submit documentation that requires all workers have a current State of New Jersey Asbestos Workers License.

D. Contractor's License: Contractor shall have current New Jersey asbestos contractor's license.

Submit a copy of the asbestos contractor's license issued by the State of New Jersey.

E. Air Sampling: Air sampling will be performed by NJARNG.

F. Pressure Differential Recordings for Local Exhaust System: Provide a local exhaust system that creates a negative pressure of at least 0.02 inches of water relative to the pressure external to the enclosure and operate it continuously, 24 hours a day, until the temporary enclosure of the as-bestos control area is removed. Submit pressure differential recordings for each work day to the PQP for review and to the Contracting Officer within 24 hours from the end of each work day.

G. Protective Clothing Decontamination Quality Control Records: Provide all records that docu-ment quality control for the decontamination of reusable outer protective clothing.

PART 2 - PRODUCTS

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 6

2.1 SOURCE QUALITY CONTROL

A. Employee Training Reports: Submit certificates, prior to the start of work but after the main abatement submittal, signed by each employee indicating that the employee has received train-ing in the proper handling of materials and wastes that contain asbestos in accordance with 40 CFR 763; understands the health implications and risks involved, including the illnesses possi-ble from exposure to airborne asbestos fibers; understands the use and limits of the respiratory equipment to be used; and understands the results of monitoring of airborne quantities of asbes-tos as related to health and respiratory equipment as indicated in 29 CFR 1926.1101 on an ini-tial and annual basis. Certificates shall be organized by individual worker, not grouped by type of certification. Train all personnel involved in the asbestos control work in accordance with United States Environmental Protection Agency (USEPA) Asbestos Hazard Emergency Re-sponse Act (AHERA) training criteria or State training criteria whichever is more stringent.

The Contractor shall document the training by providing: dates of training, training entity, course outline, names of instructors, and qualifications of instructors upon request by the Con-tracting Officer. Furnish each employee with respirator training and fit testing administered by the PQP as required by 29 CFR 1926.1101. Fully cover engineering and other hazard control techniques and procedures. All asbestos workers shall have a current State of New Jersey as-bestos worker's license.

B. Permits, Licenses, and Notifications: Obtain necessary permits and licenses in conjunction with asbestos removal, encapsulation, hauling, and disposition, and furnish notification of such ac-tions required by Federal, State, regional, and local authorities prior to the start of work. Notify the Contracting Officer and other appropriate Government agencies in writing 20 working days prior to the start of asbestos work as indicated in applicable laws, ordinances, criteria, rules, and regulations. Submit copies of all Notifications to the Contracting Officer.

2.2 ASBESTOS HAZARD ABATEMENT PLAN

A. Submit a detailed plan of the safety precautions such as lockout, tagout, tryout, fall protection, and confined space entry procedures and equipment and work procedures to be used in the re-moval and demolition of materials containing asbestos. The plan, not to be combined with oth-er hazard abatement plans, shall be prepared, signed, and sealed by the PQP. Provide a Table of Contents for each abatement submittal, which shall follow the sequence of requirements in the contract. Such plan shall include but not be limited to the precise personal protective equipment to be used including, but not limited to, respiratory protection, type of whole-body protection and if reusable coveralls are to be employed decontamination methods (operations and quality control plan), the location of asbestos control areas including clean and dirty areas, buffer zones, showers, storage areas, change rooms, removal method, interface of trades involved in the construction, sequencing of asbestos related work, disposal plan, type of wetting agent and asbestos sealer to be used, locations of local exhaust equipment, planned air monitoring strate-gies, and a detailed description of the method to be employed in order to control environmental pollution. The plan shall also include (both fire and medical emergency) response plans. The Asbestos Hazard Abatement Plan must be approved in writing prior to starting any asbestos work. The Contractor, Asbestos Hazard Control Supervisor, and PQP shall meet with the Con-tracting Officer prior to beginning work, to discuss in detail the Asbestos Hazard Abatement Plan, including work procedures and safety precautions. Once approved by the Contracting Of-ficer, the plan will be enforced as if an addition to the specification. Any changes required in

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 7

the specification as a result of the plan shall be identified specifically in the plan to allow for free discussion and approval by the Contracting Officer prior to starting work.

B. Testing Laboratory: Submit the name, address, and telephone number of each testing laboratory selected for the sampling, analysis, and reporting of airborne concentrations of asbestos fibers along with evidence that each laboratory selected holds the appropriate State license and/or permits and certification that each laboratory is American Industrial Hygiene Association (AIHA) accredited and that persons counting the samples have been judged proficient by cur-rent inclusion on the AIHA Asbestos Analysis Registry (AAR) and successful participation of the laboratory in the Proficiency Analytical Testing (PAT) Program. Where analysis to deter-mine asbestos content in bulk materials or transmission electron microscopy is required, submit evidence that the laboratory is accredited by the National Institute of Science and Technology (NIST) under National Voluntary Laboratory Accreditation Program (NVLAP) for asbestos analysis. The testing laboratory firm shall be independent of the asbestos contractor and shall have no employee or employer relationship which could constitute a conflict of interest.

C. Landfill Approval: Submit written evidence that the landfill is for asbestos disposal by the U.S.

Environmental Protection Agency, Region 3, Air Enforcement Section (38W12), and local regulatory agencies. Within 3 working days after delivery, submit detailed delivery tickets, pre-pared, signed, and dated by an agent of the landfill, certifying the amount of asbestos materials delivered to the landfill. Submit a copy of the waste shipment records within 1 day of the ship-ment leaving the project site.

PART 3 - EXECUTION

3.1 EQUIPMENT

A. At all times, provide the Contracting Officer or the Contracting Officer's Representative, with at least two complete sets of personal protective equipment as required for entry to and inspection of the asbestos control area. Provide equivalent training to the Contracting Officer or a desig-nated representative as provided to Contractor employees in the use of the required personal protective equipment. Provide manufacturer's certificate of compliance for all equipment used to contain airborne asbestos fibers.

B. Respirators: Select respirators from those approved by the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services.

1. Respirators for Handling Asbestos: Provide personnel engaged in pre-cleaning, clean-up, handling, removal and demolition of asbestos materials with respiratory protection as indicated in 29 CFR 1926.1101 and 29 CFR 1926.103.

C. Exterior Whole Body Protection: Provide the following:

1. Outer Protective Clothing: Provide personnel exposed to asbestos with disposable "non-breathable," whole body outer protective clothing, head coverings, gloves, and foot coverings. Provide disposable plastic or rubber gloves to protect hands. Cloth gloves

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 8

may be worn inside the plastic or rubber gloves for comfort, but shall not be used alone.

Make sleeves secure at the wrists, make foot coverings secure at the ankles, and make clothing secure at the neck by the use of tape.

2. Personal Decontamination Unit: Provide a temporary, negative pressure unit with a separate decontamination locker room and clean locker room with a shower that com-plies with 29 CFR 1926.51(f)(4)(ii) through (V) in between for personnel required to wear whole body protective clothing. Provide two separate lockers for each asbestos worker, one in each locker room. Keep street clothing and street shoes in the clean locker. HEPA vacuum and remove asbestos contaminated disposable protective cloth-ing while still wearing respirators at the boundary of the asbestos work area and seal in impermeable bags or containers for disposal. Do not wear work clothing between home and work. Locate showers between the decontamination locker room and the clean locker room and require that all employees shower before changing into street clothes. Collect used shower water and filter with approved water filtration equipment to remove asbestos contamination. Dispose of filters and residue as asbestos waste.

Discharge clean water to the sanitary system. Dispose of asbestos contaminated work clothing as asbestos contaminated waste. Decontamination units shall be physically at-tached to the asbestos control area. Build both a personnel decontamination unit and an equipment decontamination unit onto and integral with each asbestos control area.

3. Eye Protection: Provide goggles to personnel engaged in asbestos abatement operations when the use of a full face respirator is not required.

D. Warning Signs and Labels: Provide warning signs at all approaches to asbestos control areas.

Locate signs at such a distance that personnel may read the sign and take the necessary protec-tive steps required before entering the area. Provide labels and affix to all asbestos materials, scrap, waste, debris, and other products contaminated with asbestos.

E. Local Exhaust System: Provide a local exhaust system in the asbestos control area in accord-ance with AIHA Z9.2 and 29 CFR 1926.1101 that will provide at least four air changes per hour inside of the negative pressure enclosure. Local exhaust equipment shall be operated 24 hours per day, until the asbestos control area is removed and shall be leak proof to the filter and equipped with HEPA filters. Maintain a minimum pressure differential in the control area of minus 0.02 inch of water column relative to adjacent, unsealed areas. Provide continuous 24-hour per day monitoring of the pressure differential with a pressure differential automatic re-cording instrument. In no case shall the building ventilation system be used as the local exhaust system for the asbestos control area. Filters on exhaust equipment shall conform to AIHA Z9.2 and UL 586. The local exhaust system shall terminate out of doors and remote from any public access or ventilation system intakes.

F. Tools: Vacuums shall be leak proof to the filter and equipped with HEPA filters. Filters on vacuums shall conform to AIHA Z9.2 and UL 586. Do not use power tools to remove asbestos containing materials unless the tool is equipped with effective, integral HEPA filtered exhaust ventilation systems. Remove all residual asbestos from reusable tools prior to storage or reuse.

G. Rental Equipment: If rental equipment is to be used, furnish written notification to the rental agency concerning the intended use of the equipment and the possibility of asbestos contamina-tion of the equipment.

3.2 WORK PROCEDURE

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 9

A. Perform asbestos related work in accordance with 29 CFR 1926.1101, 40 CFR 61-SUBPART M, and as specified herein. Use wet removal procedures. Personnel shall wear and utilize pro-tective clothing and equipment as specified herein. Eating, smoking, drinking, chewing gum, tobacco, or applying cosmetics shall not be permitted in the asbestos work or control areas.

Personnel of other trades not engaged in the removal and demolition of asbestos containing ma-terial shall not be exposed at any time to airborne concentrations of asbestos unless all the per-sonnel protection and training provisions of this specification are complied with by the trade personnel. Shut down the building heating, ventilating, and air conditioning system, cap the openings to the system, prior to the commencement of asbestos work. Disconnect electrical service when wet removal is performed and provide temporary electrical service with verifiable ground fault circuit interrupter (GFCI) protection prior to the use of any water. If an asbestos fiber release or spill occurs outside of the asbestos control area, stop work immediately, correct the condition to the satisfaction of the Contracting Officer including clearance sampling, prior to resumption of work.

3.3 ASBESTOS CONTROL AREA REQUIREMENTS

A. The construction of a negative pressure enclosure is infeasible for the removal of ACM in the building which is not occupied and will be completely demolished. Use alternate techniques as indicated in 29 CFR 1926.1101. Establish designated limits for the asbestos regulated area with the use of rope or other continuous barriers, and maintain all other requirements for asbestos control areas. The PQP shall conduct personal samples of each worker engaged in asbestos handling (removal, disposal, transport and other associated work) throughout the duration of the project. If the quantity of airborne asbestos fibers monitored at the breathing zone of the work-ers at any time exceeds background or 0.01 fibers per cubic centimeter whichever is greater, stop work, evacuate personnel in adjacent areas or provide personnel with approved protective equipment at the discretion of the Contracting Officer. This sampling may be duplicated by the Government at the discretion of the Contracting Officer. If the air sampling results obtained by the Government differ from those obtained by the Contractor, the Government will determine which results predominate. If adjacent areas are contaminated as determined by the Contracting Officer, clean the contaminated areas, monitor, and visually inspect the area as specified herein.

3.4 REMOVAL PROCEDURES

A. Wet asbestos material with a fine spray of amended water or a specific wetting agent such as light oil during removal, cutting, or other handling so as to reduce the emission of airborne fi-bers. Remove material and immediately place in 6 mil plastic disposal bags. Remove asbestos containing material in a gradual manner, with continuous application of the amended water or wetting agent in such a manner that no asbestos material is disturbed prior to being adequately wetted. Where unusual circumstances prohibit the use of 6 mil plastic bags, submit an alternate proposal for containment of asbestos fibers to the Contracting Officer for approval. For exam-ple, in the case where both piping and insulation are to be removed, the Contractor may elect to wet the insulation, wrap the pipes and insulation in plastic and remove the pipe by sections.

Asbestos containing material shall be containerized while wet. At no time shall asbestos mate-rial be allowed to accumulate or become dry. Lower and otherwise handle asbestos containing material as indicated in 40 CFR 61-SUBPART M.

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 10

B. Sealing Contaminated Items Designated for Disposal: Remove contaminated architectural, me-chanical, and electrical appurtenances such as venetian blinds, full-height partitions, carpeting, duct work, pipes and fittings, radiators, light fixtures, conduit, panels, and other contaminated items designated for removal by completely coating the items with an asbestos lock-down en-capsulant at the demolition site before removing the items from the asbestos control area. These items need not be vacuumed. The asbestos lock-down encapsulant shall be tinted a contrasting color. It shall be spray-applied by airless method. Thoroughness of sealing operation shall be visually gauged by the extent of colored coating on exposed surfaces. Lock-down encapsulants shall comply with the performance requirements specified herein.

C. Exposed Pipe Insulation Edges: Contain edges of asbestos insulation to remain that are exposed by a removal operation. Wet and cut the rough ends true and square with sharp tools and then encapsulate the edges with a 1/4 inch thick layer of non-asbestos containing insulating cement troweled to a smooth hard finish. When cement is dry, lag the end with a layer of non-asbestos lagging cloth, overlapping the existing ends by at least 4 inches. When insulating cement and cloth is an impractical method of sealing a raw edge of asbestos, take appropriate steps to seal the raw edges as approved by the Contracting Officer.

3.5 AIR SAMPLING

A. Air sampling will be performed by NJARNG.

B. Should any of the final samples indicate an unacceptable value, the Contractor shall take appro-priate actions to re-clean the area at the Contractor's expense.

3.6 CLEAN-UP AND DISPOSAL

A. Housekeeping: Essential parts of asbestos dust control are housekeeping and clean-up proce-dures. Maintain surfaces of the asbestos control area free of accumulations of asbestos fibers.

Give meticulous attention to restricting the spread of dust and debris; keep waste from being distributed over the general area. Use HEPA filtered vacuum cleaners. DO NOT BLOW DOWN THE SPACE WITH COMPRESSED AIR. When asbestos removal is complete, all as-bestos waste is removed from the work-site, and final clean-up is completed, the Contracting Officer will attest that the area is safe before the signs can be removed. The Contracting Officer will visually inspect all surfaces within the enclosure for residual material or accumulated dust or debris. The Contracting Officer must agree that the area is safe in writing before unrestricted entry will be permitted. The Government shall have the option to perform monitoring to deter-mine if the areas are safe before entry is permitted.

B. Title to Materials: All waste materials, except as specified otherwise, shall become the property of the Contractor and shall be disposed of as specified in applicable local, State, and Federal regulations and herein.

3.7 DISPOSAL OF ASBESTOS

A. Procedure for Disposal: Collect asbestos waste, asbestos contaminated water, scrap, debris, bags, containers, equipment, and asbestos contaminated clothing which may produce airborne

REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIAL 02 82 33 - 11

concentrations of asbestos fibers and place in sealed fiber-proof, waterproof, non-returnable containers (e.g. double plastic bags 6 mils thick, cartons, drums or cans). Wastes within the containers must be adequately wet in accordance with 40 CFR 61-SUBPART M. Affix a warn-ing and Department of Transportation (DOT) label to each container including the bags or use at least 6 mils thick bags with the approved warnings and DOT labeling preprinted on the bag.

The name of the waste generator and the location at which the waste was generated shall be clearly indicated on the outside of each container. Prevent contamination of the transport vehi-cle (especially if the transport vehicle is a rented truck likely to be used in the future for non-asbestos purposes). These precautions include lining the vehicle cargo area with plastic sheet-ing (similar to work area enclosure) and thorough cleaning of the cargo area after transport and unloading of asbestos debris is complete. Dispose of waste asbestos material at an Environmen-tal Protection Agency (EPA) or State-approved asbestos landfill off Government property. For temporary storage, store sealed impermeable bags in asbestos waste drums or skids. An area for interim storage of asbestos waste-containing drums or skids will be assigned by the Contracting Officer or his authorized representative. Procedure for hauling and disposal shall comply with 40 CFR 61-SUBPART M, State, regional, and local standards. Sealed plastic bags may be dumped from drums into the burial site unless the bags have been broken or damaged. Dam-aged bags shall remain in the drum and the entire contaminated drum shall be buried. Uncon-taminated drums may be recycled. Workers unloading the sealed drums shall wear appropriate respirators and personal protective equipment when handling asbestos materials at the disposal site.

B. Asbestos Disposal Quantity Report: Record and report, to the Contracting Officer, the amount of asbestos containing material removed and released for disposal. Deliver the report for the previous day at the beginning of each day shift with amounts of material removed during the previous day reported in linear meters or square meters linear feet or square feet as described in-itially in this specification and in cubic meters feet for the amount of asbestos containing mate-rial released for disposal.

END OF SECTION 02 82 33

File details come from the government source that posted it. Updated .