7_Specification Book Final Submission 040909.pdf

PDF 4 MB Posted

Attached to
MAINE National Guard Multiple Award Task Order Contract Federal contract opportunity
Solicitation number
W912JD11R0001
Issued by
Department of the Army Maine Army National Guard

About this file

7_Specifications

View the file

Other files for this federal contract opportunity

Other files attached to MAINE National Guard Multiple Award Task Order Contract, newest first.
File Type Posted
List of Awarded Multiple Award Task Order Contracts.docx DOCX document
MATOC Mail Addresses.doc DOC document
Amendment 006.doc DOC document
RFI_LOG__Updated 3Dec10_MATOC_-_W912JD-10-R-0001 .xls XLS spreadsheet
Amendment 0005.doc DOC document
RFI_LOG__Updated 24Nov10_MATOC_-_W912JD-10-R-0001 .xls XLS spreadsheet
P-9 Existing OH Door.pdf PDF
EXHIBIT C Updated 19 Nov 10.doc DOC document
Amendment 0004.doc DOC document
RFI_LOG_ Updated_19Nov10_MATOC_W912JD-10-R-0001 111910.xls XLS spreadsheet
102800 - Toilet Accessories.pdf PDF
Amendment 003.doc DOC document
List of Task Orders Awarded under Current MATOC.pdf PDF
EXHIBIT C Updated 12 Nov 10.doc DOC document
Exhibit G RFI Request Form.pdf PDF
Amendment 002_ 12 Nov 10.doc DOC document
Maine - MATOC - Pre-Pro Conf - Notes.doc DOC document
Pre-Proposal Sign In Sheet.pdf PDF
MATOC PREPROPSAL SLIDE 1110.ppt PPT presentation
Amendment 001 4 Nov 10.doc DOC document
RFI LOG - MATOC - W912JD-10-R-0001.xls XLS spreadsheet
EXHIBIT A updated 4 Nov 10.doc DOC document
Exhibit E-1 Prototiypical updated 4 Nov 10.doc DOC document
3_Structural_Drawings.pdf PDF
EXHIBIT B.pdf PDF
EXHIBIT D.pdf PDF
EXHIBIT A.pdf PDF
4_Architectural_Drawings.pdf PDF
6_Electrical_Drawings.pdf PDF
Mr. David W McPhail -Source Selection Participation Agreement.pdf PDF
1_General_Drawings.pdf PDF
5_Mechanical_Drawings.pdf PDF
Exhibit E-1 Prototiypical.pdf PDF
EXHIBIT C.pdf PDF
EXHIBIT G.doc DOC document
MATOC TASK ORDER Solicitation W912JD-11-R-0001.pdf PDF
2_Civil_Drawings.pdf PDF
Exhibit F.pdf PDF
Exhibit E Prototiypical.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

S P E C I F I C A T I O N S

BUILDING 9, ADDITION AND ALTERATION

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

Project No. VVRK082002 100% Submission Prepared For:

Maine Air National Guard Building #8, Camp Keyes Augusta, ME 04333-0333

April 9, 2009 Prepared By:

BUILDING 9 VVRK082002

ADDITION AND ALTERATION

SOUTH PORTLAND, MAINE

T A B L E O F C O N T E N T S

DIVISION 01 – GENERAL REQUIREMENTS

Section 011000 Summary 012300 Options 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Requirements 014200 References 015000 Temporary Facilities and Controls 016000 Product Requirements 017300 Execution 017419 Construction Waste Management and Disposal 017700 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents 017900 Demonstration and Training 019113 General Commissioning Requirements 019114 General Building Commissioning

DIVISION 02 – EXISTING CONDITIONS

Section 024119 Selective Structure Demolition

DIVISION 03 – CONCRETE

Section 033000 Cast-in-Place Concrete

DIVISION 04 – NOT USED

DIVISION 05 – METALS

Section 051200 Structural Steel Framing 053100 Steel Decking 055100 Metal Stairs

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

Section 061053 Miscellaneous Rough Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

079200 Joint Sealants

CONTENTS PAGE 1

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

DIVISION 08 – OPENINGS

Section 081113 Hollow Metal Doors and Frames 083323 Overhead Coiling Doors 083613 Sectional Doors

DIVISION 09 – FINISHES

Section 091110 Non-Load Bearing Steel Framing 092900 Gypsum Board 093000 Tiling 095113 Acoustical Panel Ceilings 096513 Resilient Base and Accessories 096519 Resilient Tile Flooring 096816 Sheet Carpeting 099123 Interior Painting

DIVISION 10 – 12 NOT USED

DIVISION 13 – SPECIAL CONSTRUCTION

Section 133419 Metal Building Systems

DIVISION 22 – PLUMBING

Section 221116 Domestic Water Piping 221119 Domestic Water Piping Specialties 221313 Facility Sanitary Sewers 221316 Sanitary Waste and Vent Piping 224000 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING

Section 230529 Hangers and Supports for HVAC Piping and Equipment 230593 Testing, Adjusting, and Balancing for HVAC Systems 230700 HVAC and Plumbing Insulation 231126 Facility Liquefied-Petroleum Gas Piping 233113 Metal Ducts 233300 Air Duct Accessories 233713 Diffusers, Registers, and Grilles 237333 Indoor Indirect-Fuel-Fired Heating and Ventilating Units

DIVISION 26 – ELECTRICAL

Section 260500 Common Work Results for Electrical 260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems 260533 Raceway and Boxes for Electrical Systems 260553 Identification for Electrical Systems

CONTENTS PAGE 2

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

260923 Lighting Control Devices 262416 Panelboards 262726 Wiring Devices 262813 Fuses 262816 Enclosed Switches 265100 Interior Lighting

DIVISION 27 – COMMUNICATIONS

Section 271500 Communications Horizontal Cabling

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

Section 283112 Zoned (DC Loop) Fire-Alarm System

DIVISION 31 – EARTHWORK

Section 311000 Site Clearing 312000 Earth Moving

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 321216 Asphalt Paving 329200 Turfs and Grasses

DIVISION 33 – UTILITIES

334600 Subdrainage

END OF SECTION

CONTENTS PAGE 3

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work by Government.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and drawing conventions.

B. Related Section:

1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Government’s facilities.

1.3 PROJECT INFORMATION

A. Project Identification: Building 9, Addition and Alteration, Maine Air National Guard.

1. Project Location: South Portland, Maine

B. Owner: Maine Air National Guard.

C. Architect: Oak Point Associates, 231 Main Street, Biddeford, Maine 04005; 207-283-0193 (phone); 207-283-4283 (fax); A/E Contract No. W912JD-08-D-0001.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

1. The Work consists of selective building demolition; excavation; utilities; paving;

landscaping; concrete foundations; pre-engineered metal building addition; building insulation; doors and frames; roofing; pre-engineered storage mezzanine; interior

SUMMARY 011000 - 1

partitions and finishes; mechanical, plumbing and electrical systems; and associated incidental work.

B. Type of Contract

1. Project will be constructed under a single prime contract.

1.5 WORK BY GOVERNMENT

A. General: Cooperate fully with Government so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Government. Coordinate the Work of this Contract with work performed by the Government.

B. Subsequent Work: Government will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1. Telephone and data systems.

1.6 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to indicated limit(s) of work.

2. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.7 COORDINATION WITH OCCUPANTS

A. Full Government Occupancy: Government will occupy site and existing building(s) during entire construction period. Cooperate with Government during construction operations to

SUMMARY 011000 - 2

minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s day-to-day operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer and approval of authorities having jurisdiction.

2. Notify the Contracting Officer not less than 72 hours in advance of activities that will affect Government’s operations.

1.8 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 0700 to 1630, Monday through Friday, except as otherwise indicated.

1. Weekend Hours: As approved by the Contracting Officer.

2. Early Morning Hours: As approved by the Contracting Officer.

3. Hours for Utility Shutdowns: After 1600 to 0800.

4. Hours for Noise-Producing Activities: 1600 to 0800.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Obtain Contracting Officer’s written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Government occupancy with Contracting Officer.

1. Notify Contracting Officer not less than two days in advance of proposed disruptive operations.

2. Obtain Contracting Officer’s written permission before proceeding with disruptive operations.

E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

F. Controlled Substances: Use of tobacco products and other controlled substances within the existing building is not permitted.

SUMMARY 011000 - 3

G. Employee Identification: Provide identification tags for Contractor personnel working on the Project site. Require personnel to utilize identification tags at all times.

H. Employee Screening: Comply with Government’s requirements regarding drug and background screening of Contractor personnel working on the Project site.

1. Maintain list of approved screened personnel with Contracting Officer.

1.9 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

SUMMARY 011000 - 4

SECTION 012300 - OPTIONS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for options.

1.3 DEFINITIONS

A. Option: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the base bid amount if the Government decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Options described in this Section are part of the Work only if enumerated in the Agreement.

2. The cost or credit for each option is the net addition to or deduction from the Contract Sum to incorporate option into the Work. No other adjustments are made to the Contract Sum.

1.4 PROCEDURES

A. Coordination: Modify or adjust affected adjacent work as necessary to completely integrate work of the option into Project.

1. Include as part of each option, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of option.

B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each option. Indicate if options have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated modifications to options.

C. Execute accepted options under the same conditions as other work of the Contract.

D. Schedule: A schedule of options is included at the end of this Section.

OPTIONS 012300 - 1

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF OPTIONS

A. Option No. 1: Provide mechanical heating system for building addition.

B. Option No. 2: Provide pre-engineered storage mezzanine (to match style and construction type of mezzanine in existing building) for building addition.

C. Option No. 3: Provide interior renovations to administration, locker room and shower facilities on easterly end of existing building.

OPTIONS 012300 - 2

SECTION 012500 - SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Sections:

1. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

2. Divisions 02 through 33 Sections for specific requirements and limitations for substitutions.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Government that are not required in order to meet other Project requirements but may offer advantage to Contractor or Government.

1.4 SUBMITTALS

A. Submittals shall comply with the requirements of the Construction Contract Clauses, Division 01 Section "Submittal Procedures" and the individual sections specifying the work.

B. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use form approved by the Government.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

SUBSTITUTION PROCEDURES 012500 - 1

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or modifications needed to other parts of the Work that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Contracting Officer’s Action: If necessary, Contracting Officer will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Contracting Officer will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Government’s Supplemental Instructions for minor changes in the Work.

b. Use product specified if Contracting Officer does not issue a decision on use of a proposed substitution within time allocated.

SUBSTITUTION PROCEDURES 012500 - 2

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES

A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Contracting Officer will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Contracting Officer will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Contracting Officer.

1. Conditions: Contracting Officer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Contracting Officer will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional

SUBSTITUTION PROCEDURES 012500 - 3

responsibilities Government must assume. Government’s additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Government, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 3 - EXECUTION (Not Used)

SUBSTITUTION PROCEDURES 012500 - 4

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections:

1. Division 01 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.

1.3 MINOR CHANGES IN THE WORK

A. Contracting Officer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on form provided by the Government.

1.4 PROPOSAL REQUESTS

A. Government-Initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Contracting Officer are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and

CONTRACT MODIFICATION PROCEDURES 012600 - 1

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use forms provided by Government.

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Contracting Officer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Division 01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use form approved by Government.

1.5 CHANGE ORDER PROCEDURES

A. On Contracting Officer’s approval of a Proposal Request, Contracting Officer will issue a Change Order for signatures of Contracting Officer and Contractor on form provided by Government.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Contracting Officer may issue a Construction Change Directive on a form provided by the Government. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

CONTRACT MODIFICATION PROCEDURES 012600 - 2

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

CONTRACT MODIFICATION PROCEDURES 012600 - 3

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General project coordination procedures.

2. Administrative and supervisory personnel.

3. Coordination drawings.

4. Requests for Information (RFIs).

5. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Sections:

1. Division 01 Section "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.

2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract.

4. Division 01 Section “General Commissioning Requirements” for coordinating the Work with Government’s commissioning authority.

1.3 DEFINITIONS

A. RFI: Request from Government, Architect, or Contractor seeking information from each other during construction.

1.4 SUBMITTALS

A. Submittals shall comply with the requirements of the Construction Contract Clauses, Division 01 Section "Submittal Procedures" and the individual sections specifying the work.

B. Key Personnel Names: Submit list in accordance with “key personnel” paragraph herein.

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

1.5 COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Provide detailed coordination drawings to establish construction interfaces between the different components and contractors to ensure proper installation of the components.

3. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

4. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Government and any separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and any activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of coordination drawings.

5. Delivery and processing of submittals.

6. Progress meetings.

7. Preinstallation conferences.

8. Project closeout activities.

9. Startup and adjustment of systems.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other Sections for disposition of salvaged materials that are designated as Government’s property.

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings in accordance with requirements in individual Sections, where installation is not completely shown on Shop

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

f. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire protection, fire alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inch diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Review: Contracting Officer will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are the Contractor's responsibility. If the Contracting Officer determines that the coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, the Contracting Officer will so inform the Contractor, who shall make changes as directed and resubmit.

9. Coordination Drawing Prints: Prepare coordination drawing prints in accordance with requirements of Division 01 Section "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files in accordance with the following requirements:

1. File Preparation Format: Same digital data software program, version, and operating system as the original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using format same as file preparation format and Portable Data File (PDF) format.

3. Government will furnish Contractor one set of digital data files of the Drawings for use in preparing coordination digital data files.

a. Government makes no representations as to the accuracy or completeness of digital data files as they relate to the Drawings.

b. Digital Data Software Program: The Drawings are available in AutoCAD 2004.

c. Contractor shall execute a data licensing agreement in the form of an Agreement form approved by the Government and Architect.

1.7 KEY PERSONNEL

A. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and email addresses. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times.

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

MAINE AIR NATIONAL GUARD

SOUTH PORTLAND, MAINE

1.8 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Contracting Officer will return RFIs submitted to Contracting Officer by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Use form approved by Government.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Allow seven working days for Contracting Officer’s response for each RFI. RFIs received by Contracting Officer after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Architect's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

PROJECT MANAGEMENT AND COORDINATION 013100 - 5

2. Contracting Officer’s action may include a request for additional information, in which case Contracting Officer’s time for response will date from time of receipt of additional information.

3. Contracting Officer’s action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Division 01 Section "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Contracting Officer in writing within 10 days of receipt of the RFI response.

E. On receipt of Contracting Officer’s action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Contracting Officer within seven days if Contractor disagrees with response.

F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Contracting Officer’s response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and

Proposal Request, as appropriate.

1.9 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Contracting Officer and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Contracting Officer and Architect, within three days of the meeting.

B. Preconstruction Conference: Contracting Officer will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Contracting Officer and Architect, but no later than 15 days after execution of Notice to Proceed.

1. Conduct the conference to review responsibilities and personnel assignments.

2. Attendees: Authorized representatives of Goverment, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

PROJECT MANAGEMENT AND COORDINATION 013100 - 6

3. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Critical work sequencing and long-lead items.

c. Designation of key personnel and their duties.

d. Lines of communications.

e. Procedures for processing field decisions and Change Orders.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of record documents.

l. Use of the premises and existing building.

m. Work restrictions.

n. Working hours.

o. Government’s occupancy requirements.

p. Responsibility for temporary facilities and controls.

q. Procedures for moisture and mold control.

r. Procedures for disruptions and shutdowns.

s. Construction waste management and recycling.

t. Parking availability.

u. Office, work, and storage areas.

v. Equipment deliveries and priorities.

w. First aid.

x. Security.

y. Progress cleaning.

4. Minutes: Entity responsible for conducting meeting shall record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Contracting Officer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

PROJECT MANAGEMENT AND COORDINATION 013100 - 7

i. Possible conflicts.

j. Compatibility problems.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written recommendations.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Project Closeout Conference: Schedule and conduct a Project closeout conference, at a time convenient to Contracting Officer and Architect, but no later than 30 days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Government, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Submittal of written warranties.

d. Requirements for preparing operations and maintenance data.

e. Requirements for demonstration and training.

f. Preparation of Contractor's punch list.

g. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

h. Submittal procedures.

i. Coordination of separate contracts.

PROJECT MANAGEMENT AND COORDINATION 013100 - 8

j. Government’s partial occupancy requirements.

k. Installation of Government’s furniture, fixtures, and equipment.

l. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting shall record and distribute meeting minutes.

E. Progress Meetings: Conduct progress meetings at monthly intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Government and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Work hours.

10) Hazards and risks.

11) Progress cleaning.

12) Quality and work standards.

13) Status of correction of deficient items.

14) Field observations.

15) Status of RFIs.

16) Status of proposal requests.

17) Pending changes.

18) Status of Change Orders.

19) Pending claims and disputes.

20) Documentation of information for payment requests.

PROJECT MANAGEMENT AND COORDINATION 013100 - 9

4. Minutes: Entity responsible for conducting the meeting shall record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

F. Coordination Meetings: Conduct Project coordination meetings at monthly intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.

1. Attendees: In addition to representatives of Government and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meetings shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous coordination meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to combined Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

b. Schedule Updating: Revise combined Contractor's construction schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.

c. Review present and future needs of each contractor present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .