RFI
| RFI No: | RFI - Question | Amendment Number | Response |
| 001 | advise as to what the specific requirements are to sufficiently demonstrate to the Government that a potential/interested MATOC contractor has the capability to respond to Project On-site Conferences under emergency conditions or 120 minutes? I have read sections SC4.2.1 and 4.2.1.4.1 and 4.2.1.5.1, etc. and cannot identify specific criteria listed in the aforementioned solicitation. | 001 | Please ensure that a member of the team or a local company will be available to respond to the site within 120 minutes, to begin resolving emergency situations. |
| 002 | Exhibit E-1 at B.7 – suggest the % sign be removed after 100 since the calculation multiplied by 1 will not be changed. | 001 | Agree that the % sign should be removed after 100 in the formula in Exhibit E-1 line B7. B.7 should read "Percent Self-performed Work = Line B.6/Line B.5 X 100 = ____________%" |
| 003 | 00110-2.2.1 states six(6) general construction submittals for Exhibit A but Exhibit A states submission of five (5). Please clarify. | 001 | Section 00110 Part 2.2.1 is the current change in effect and therefore Exhibit A Part 1 should be corrected to read "Prepare six (6) Part 1 forms for general construction, and two (2) for design build, if requesting consideration for this option. " |
| 004 | Could you please verify that the work to be done to the data rack in Room 105 is just a removal and reinstall and that there are no new or additional components that will need to be installed? | 001 | Affirmative, remove and reinstall existing components; coordinate with the contracting officer before removing; components damaged by Contractor will be replaced at no additional cost to the Government. |
| 005 | Request a time extension of one week from Nov. 30, 2010 for the submission of the RFP. Thanksgiving week vacations will have a significant impact on obtaining all the information that is required and we will only have one working day after Thanksgiving for the complete compilation of required documentation. | 004 | The required response date/time has been extended from 30-Nov-2010 11:00AM to 10-Dec-2010 11:00AM and the RFI’s cutoff date/time has changed from NLT COB 19 Nov 10 to due NLT COB 26 Nov 2010 4:30PM. If changes are not made on previous documents regarding these dates ensure concerned individuals are made aware of these changes. |
| 006 | There is fiber optic cable being used on this project between the data jacks and the data rack. The specification is not clear as to the exact type of fiber required. Could this clarify? | 002 | Do not install fiber optic cable at this time; this will be installed as part of a future contract. |
| 007 | Proposal Inquiry: Is there to be a sprinkler system installed on this project? There were no fire protection drawings or specifications on the website. Please clarify. | 002 | There is no sprinkler system included in the project at this time. Bid the prototypical project as designed. |
| 008 | The drawings do not indicate the overall height of the existing building (at the roof peak), or the height of the roof eaves. Can this be provided? | 002 | According to existing bldg design, finished floor to eave trim is 16'-0"; exterior ridge height is ~25'-6"; field verify for construction purposes. |
| 009 | Do any of the other wage classifications than “Building” apply to this project? | 002 | "As a general rule, apply a second schedule if more than approximately 20% of the project will involve work of a different character than the major portion of the project ." I do not believe this will be the case in this project. |
| 010 | Will Coordination drawings actually be required for this project – specifically in AutoCAD 2004? | 002 | No, coordination drawings will not be required. Provide shop drawings for applicable sections. |
| 011 | Clarify remote parking for construction personnel since section states only one space will be provided within the project site. | 002 | Additional parking and lay down area will be located on the north side and NNW corner of the building. |
| 012 | Is Pest Control required for this project? | 002 | No, no pest control is required. Ensure site is kept clean of food and other debris that attracts pets. If pests are encountered or suspected, coordinate with COR. |
| 013 | Please clarify extent of security fencing required, if any, for this project. | 002 | No security fencing is required. |
| 014 | Will a temporary partition as described by this section be required if Option 3 is selected? | 002 | Yes, a temporary partition will be required inside the building, as equipment and parts will still be stored and employees will still be working inside. Coordinate with COR during construction for location. |
| 015 | Are standpipes and hoses required for this project? | 002 | NFPA 214 7.6 indicates temporary standpipes are required in buildings that will have them when completed, so this doesn’t apply. |
| 016 | Will a certified survey be required for this project? | 002 | No, a survey will not be required. |
| 017 | May we use the 4:12 as shown on the plans? | 002 | The specification should read ‘verify’ not ‘verified’. The intent is to match the existing pitch (4:12). |
| 018 | If 2.11B is not required will this section apply? | 002 | If the authority having jurisdiction (in this case MEANG) accepts the installers credentials, then inspections aren’t required. |
| 019 | 133419-3.11 Will this section be required? | 002 | If the authority having jurisdiction (in this case MEANG) accepts the installers credentials, then inspections aren’t required. |
| 020 | Since we are suppose to match wall and roof panels, please provide information on the existing. | 005 | Existing roof panels are Kynar CXP type, 24 gage with floating clips and thermal blocks; wall panels are Kynar MAP type, 24 gage. |
| 021 | Since we are suppose to match existing profile of the sectional door, please provide information on the existing. | 005 | See attached material submittal from original construction, "P-9 Existing OH Door". |
| 022 | Note 4: clarify aggregate area of mezzanines to not exceed 1/3 open area below since 1/AE101 shows new mezzanine (Option 2) that exceeds that definition. | 002 | Note 4: clarify aggregate area of mezzanines to not exceed 1/3 open area below since 1/AE101 shows new mezzanine (Option 2) that exceeds that definition. |
| 023 | Shouldn’t doors 203 and 203A be Option 2? | 002 | Yes. |
| 024 | Option 2 -States match existing – need specific information on the existing design. | 006 | The existing mezzanine is manufactured by Equipto. |
| 025 | 1&2/AE101 - Reference on the right side to Option 3 work is listed as Option 1. | 002 | This is a typo. This should be listed as Option 3. |
| 026 | 1&2/AD101 - Reference on the right side to Option 3 is listed as Option 2 | 002 | This is a typo. This should be listed as Option 3. |
| 027 | Please clarify the trades referred to by “Horizontal Disciplines”. | 002 | Earthwork |
| 028 | When you access the wage determination site for the State of Maine it only list the current ME20100001 which is dated 11/05/10. We do not have access to the 09/03/10 wage scale. Suggest this latest wage scale be referenced since all will have access to those wage rates. | 002 | SEE Page 15 in the solicitation: section 1.9.1. Prevailing wage determination information, current at time of issuance of solicitation, is found in the prototypical offering form, Exhibit E. In the event the current prevailing Wage Determination is changed by the Department of Labor prior to closing date of this solicitation it is the offeror’s responsibility to ensure the most recent determination is used in preparing the proposal. An Amendment will not be issued prior to closing to change Wage Determination dates and/or numbers. Applicable wage rates can be found at: http://www.access.gpo.gov/davisbacon/ME.html |
| 029a | Is there a preferred manufacturer for the pre-engineered metal building? Is the 2' OC rib Starshield roof acceptable? | 002 | There is not a preferred manufacturer. Submit for approval similar to existing, and IAW spec section 133419. |
| 029b | Are gutters required on this building, either just over the doors or the entire facility? | 002 | Gutters were not requested/required at the time of design, snow guards were, as shown. |
| 029c | What are the complete dimensions of the air handling unit -2? . | 002 | The unit shown on drawing M101 is drawn to the approximate dimensions of the REZNOR PDH unit indicated in the Air Handling Unit Schedule on drawing M001. However, the specifications allow for the use products by other manufacturers and therefore it is impossible give the exact dimensions of the unit that is to be supplied. The unit needs to be selected to satisfy the performance requirements indicated in the Air Handling Unit Schedule on drawing M001 and in the specifications. |
| 029d | Please verify snow guards are required only above the doors and not along the entire roof. | 002 | Snow guards are required as shown on drawing AE201 to protect members walking between doors. |
| 030 | 1/AE220 - Location shown for cut on AE101 is not correct – this cut on the right is underneath the mezzanine. Cuts on 2/AE201 and 4/AE201 are also not matching. | 004 | Section cut line located on plan for clarity and conforms generally to the section shown |
| 031 | AE701 - Room Finish Schedule: Room 105 – East wall has no finish | 004 | Paint may be omitted from east wall |
| 032 | G002 - Note 11: Please clarify what permits are required for this project. | 004 | See CD101 note 3 |
| 033 | General Cond. - There are no General Conditions included in the specifications therefore no direction on insurance required, etc.. Specifically, is builder’s risk insurance required? | 004 | Builders Risk Insurance is a business decision, usually required by the bonding company or by the General Contractor, as part of its risk management strategies or polices. Coverage is typically during the construction period only, and is intended to terminate when the work has been accepted by the Government. |
The contractor is responsible for the work until it has been accepted by the Government.
| 034 | Please clarify the extent, if any, of painting related to the mechanical or electrical systems. | 004 | Per individual M/E/P requirements | |
| 035 | AE701 - Room Finish Schedule Note 1: reference should be to 11/AE701 | 004 | Correct, reference should be changed "to 11/AE701" | |
| 036 | AE101 - Is the 1 hour rated partition at the expansion needed if Option 2 is not selected? | 004 | No stair if Option is not selected. | |
| 037 | 133419 - This section references no finish painting of steel frame but existing building has the steel painted. Please verify if finish painting is required for the addition. | 004 | The intent is to match existing steel framework in the building. | |
| 038 | 99123 - Does the steel framework of Option 2 mezzanine get finish painted? We assume the steel handrail gets painted yellow. | 004 | The intent is to match existing steel framework in the building to include existing stairs. | |
| 039 | Exhibit D-3B - Clarifying that the Exhibit B’s requested are from those subcontractors we intend to use during our future projects within MATOC and not the prototypical project. | 002 | That is correct Exhibit D-3B - The Exhibit B’s requested are from those subcontractors that you intend to use during future projects within MATOC and not just the prototypical project. | |
| 040 | 00110-2.2.2 - Clarifying that the list of major subcontractors requested relates to the future projects within MATOC and not the prototypical project. | 002 | That is correct "the list of major subcontractors requested relates to the future projects within MATOC and not just the prototypical project." | |
| 041 | 00120-4.2.1.6.4 - Please clarify what you mean by “Subcontractors shall have completed Exhibit B in Volume 2, to be considered”. | 002 | If you are using a specific Subcontractor as part of your Technical proposal then you need to have "Subcontractors complete Exhibit B in Volume 2, to be considered." See page 26 of the solicitation, paragraph 3.8 for further guidance. | |
| 042 | On Exhibit C Package Information and forms: In regards to the returning of the completed questionnaire. The markings on the coversheet indicate it should be marked as (Attention: RFP W92L7-10-R-001 "Source Selection Sensitive Information"). Is this the correct marking? This solicitation number is not the same as the solicitation number on the Solicitation. | 002 | This is a mistake: currently reads “should be marked as (Attention: RFP W92L7-10-R-001“, Should Read “should be marked as (Attention: RFP W912JD-11-R-0001“. | |
| 043 | Exhibit D-4B Please verify that the offeror, if they are being considered for task orders over | |||
| $ 1,000,000, must submit a CPM schedule for the prototypical project. | 004 | That is correct, if the offeror indicates they want to be considered for task orders over $1,000,000 they must submit a CPM schedule for the prototypical project. | ||
| 044a | The specifications did not include a section for toilet accessories. Are toilet accessories being provided by the government or are they to be furnished and installed by the contractor? | 004 | See attached specification section 102800. | |
| 044b | Please provide the dimensions for the quarry and ceramic wall tile. | 004 | QRT is Quartz Tile as spec’d in 096519. CWT is same as CMT (1 X 1) as spec’d in 093000 | |
| 044c | The door and hardware specified for Door 106 appears to be in error. Door 106 should be listed as a “PAIR” of 3070 door leaves within a 6070 hollow metal frame. Please clarify the lockset condition for these doors. | 004 | Door 102 is the only double door. Lockset function F04 as spec’d. Provide manual flush bolts BHMA A156.16 | |
| 044d | Drawing AE101 shows the symbol “FEC”. Please clarify if the contractor is to furnish and install fire extinguishers and cabinets and if so, please provide a specification. | 004 | FEC should read FE and will be furnished by government. Locations shown to coordinate mounting. | |
| 044e | Is the outside wall of the stairwell to the mezzanine to have drywall extending upward full height to maintain a 1-hour rating within the stairwell? | 004 | Exterior wall from the stair does not require a rating. | |
| 044f | Wall Partition Type 1A calls for a 25 gage metal stud. The average height of a Type 1A Wall Type is approximately 22 feet. We recommend the use of a stronger gage stud at these locations. | 004 | Gauges indicated are a minimum. | |
| 044g | Is the intent to have all primary and secondary structural steel members of the pre-engineered building painted? | 004 | Intent is to match existing. | |
| 045a | Is there a BIM requirement for this project? | 004 | There is no BIM requirement for the prototypical project; however, for future Design-Build projects BIM will be seen as beneficial. | |
| 045b | Does the Architect of Record have to be licensed in the State of Maine? | 005 | No requirement, however it will be seen as beneficial | |
| 46 | Do you require full SF 330 qualifications package for the AE that is a team member for this MATOC or only resumes and a two relevant project descriptions that are in SF 330 format? The information normally contained in a complete SF 330 is not necessarily relevant to this procurement (20+ resumes, 10 projects, Section H Additional Information, |
etc.) and additional information required for Section H of the SF330 is not provided in the solicitation. Also, there is not a listing of required AE disciplines to develop the Part D organization chart or Section E Key Personnel resumes.
| Please clarify what the Maine ARNG requires to meet this requirement. | 004 | AS stated in section 2.2.2.2 : "AE(s) for Design Build shall provide a SF 330.". I believe there is enough information on the type of projects we are looking at performing and disciplines required on FBO.gov "List of Task Orders Awarded under Current MATOC" and in the actual solicitation to provide a complete SF 330. The intent is to evaluate the AE services being offered not for a specific project. | ||
| 47 | Regarding Exhibit C, can a CO/COTR fill out one questionnaire for multiple projects, referenced in Exhibit A? | 004 | As Exhibit C page 1 states "Send one cover letter and questionnaire for each contract you want a reference for. " Only 1 project per questionnaire. | |
| 48 | Proposal Inquiry: Drawing CU 101 references propane service notes. Is the contractor responsible for the cost for notes 1 and 3and the owner responsible for the cost for note 2? | 005 | Yes | |
| 49 | Amended Exhibit C now includes the following line on the first page. "You are encouraged to send a questionnaire to other clients of contracts listed in your “List of 10 other projects”. Please indicate if we are being instructed to send past performance questionnaires to an additional 10 clients of contracts. Also please clarify as to where in our proposal we are to include the "List of 10 other projects". | 004 | Thank You; this somehow got inserted from an old document when amendment 002 updated Exhibit C. This line should not be included and I will update Exhibit C again in amendment 004. Also note in amendment 004 the date of 30 Nov 10 is also changed to 10 Dec 10 on Exhibit C.. | |
| 50a | What is the project duration for the SEED Project - Building 9 Alterations? | 005 | See Exhibit E "Prototypical Project Notice of Proposed Project, Proposal Form" PERFORMANCE PERIOD: 180 Days, after receipt of Notice to Proceed. | |
| 50b | there a government estimate for the project dollar value of the SEED Project - Building 9 Alterations? | 005 | See Exhibit E "Prototypical Project Notice of Proposed Project, Proposal Form" MAGNITUDE OF PROJECT: Between $500,000 and $1,000,000. | |
| 51a | Overhead Coiling Doors-specs mention fusible links at 1.4 C2, but that is typical of fire doors. The spec doesn’t mention that these are fire doors. Please confirm | 005 | Coiling doors are not rated. No fusible link required. | |
| 51b | Should the overhead Coiling Doors be insulated? The sectional doors are and are in the same building. Please confirm. | 005 | Insulation not required. | |
| 51c | Both Manual Operation and Electrical are mentioned. It appears they are to manual, please confirm. | 005 | New coiling doors are manual operation; new sectional door is electric. | |
| 52 | Question 1: Does the 180 day Schedule Duration include the base building as well Options 1, 2 and 3 all being built as one total project? Or do we break out separate schedules for the Options? | 006 | All options will be considered as 1 project and included in one Schedule. |