Q A_Dated_02Aug13.pdf

PDF 20 KB Posted

Attached to
TFI-F-22 Combat Aircraft Parking Apron (KNMD069216) and TFI-F-22 Combat Apron Addition (KNMD119001)
Solicitation number
W912J6-13-R-0004
Issued by

View the file

Other files

File Type Posted
Q A_Dated_16Aug13.pdf PDF
Amend__7-W912J613R0004-0007.pdf PDF
Q A_Dated_13Aug13_1130_hrs.pdf PDF
Q A_Dated_13Aug13_1030_hrs.pdf PDF
Q A_Dated_13Aug13_0900_hrs.pdf PDF
W912J613R0004-0006.pdf PDF
BID_SCHEDULE_13AUG13.pdf PDF
Q A_Dated_09Aug13_0900_hrs.pdf PDF
Adden0004-REVISED_Asbestos_Report.pdf PDF
W912J613R0004-0005.pdf PDF
Adden0004-REVISED_LBP_Report.pdf PDF
REVISED_EXHIBIT_F_W912J613R0004.pdf PDF
REVISED_EXHIBIT_H.pdf PDF
Q A_Dated_08Aug13_0900hrs.pdf PDF
Q A_Dated_08Aug13.pdf PDF
Vol_1_KNMD119001_Drawing_G002_ADD_002.pdf PDF
W912J6-13-R-0004-0004.pdf PDF
KNMD119001_SPECS-Add_003.pdf PDF
SPECS-Addendum0002_KNMD119001.pdf PDF
Q A_Dated_05Aug13.pdf PDF
W912J613R0004-0003.pdf PDF
Vol_1_KNMD119001_Drawing-Add_002.pdf PDF
W912J613R0004-0002.pdf PDF
KNMD069216 119001_ASBESTOS_REPORT.pdf PDF
KNMD069216 119001_SOIL_SAMPLING_REPORT.pdf PDF
KNMD069216 119001_LEAD_SCREENING_REPORT.pdf PDF
PrePropMinutes01Aug13-W912J613R0004.pdf PDF
PreProp_Sign_In_Sheet_01Aug13.pdf PDF
Non-disclosure_certificate__contractor.docx DOCX document
Q A_Dated_01Aug13.pdf PDF
W912J613R0004-0001.pdf PDF
Vol_3_AF_DWG_8443128_Sheet_S1-Add-001.pdf PDF
Vol_1_KNMD119001_Drawing-Add_001.pdf PDF
Q A_Dated_31Jul13.pdf PDF
Q A_Dated_26Jul13.pdf PDF
Q A_Dated_16Jul13.pdf PDF
EXHIBIT_H_TEP_Calc_W912J613R0004.docx DOCX document
EXHIBIT_C_W912J613R0004.doc DOC document
EXHIBIT_F_W912J613R0004.docx DOCX document
EXHIBIT_D_and_E__W912J613R0004.doc DOC document
Exhibit_J_W912J613R0004.doc DOC document
Exhibit_I_TEP_SAMPLE_W912J613R0004.docx DOCX document
EXHIBIT_G_-SB_Participation_Plan_W912J613R0004.docx DOCX document
W912J613R0004.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS RELATED TO:

SOLICITATION W912J6-13-R-0004

Dated 02 Aug 13

Make Sure You Have the Latest Version of this Web Page “Refresh” or “Reload”

Dated 16 Jul 13

Q1. How do I access the files/documents for the Project?

A1. See, Sections 4.4, 4.5 & 4.7 of the FBO Vendor Guide available for download in PDF format via the Federal Business Opportunities / FBO Home Page. See also, Section 00100 of the Solicitation.

Additionally, to view and/or download Export Controlled Materials, a company must be certified (via an approved DD Form 2345) by the Joint Certification Program (JCP) administered by the DLA Logistic Information Service (DLIS). This certification establishes that a company is a U.S. or Canadian contractor eligible to receive unclassified technical data that is under the control of the U.S. Department of Defense (DoD) or the Canadian Department of National Defense (DND). Questions about this program or DD Form 2345 should be addressed to U.S./Canada Joint Certification Office, DLA Logistics Information Services (DLIS), Federal Center, 74 Washington Avenue North, Battle Creek, MI 49017-3084. The Joint Certification Office may be contacted by telephone at: 1-(800) 352-3572; or email: jcp-admin@.dla.mil.

Q2. I am trying to access the [export controlled] packages and have a number as assigned on DD Form 2345 but cannot get the packages to open. Our DD 2345 Number is ####### expiration ##/##/2015.

A2. The U.S./Canada Joint Certification Program (JCP) office reported to this office that once a company is certified with the JCP office (normally 7 to 12 business days), the company should contact FBO to have them add their JCP number to their FBO account. The FBO help desk (Federal Service Desk) reported to this office that companies need to make sure that they are registered and login as a Vendor to FBO. When the Vendor click's to open an export controlled package/document, they should be asked for their MPIN. After entering the MPIN, the export controlled package/document should be viewable/downloadable by Vendors that have gone through the JCP process. If a Vendor still has problems, the Vendor should check to make sure that their CCR registration and MPIN are valid and up-to-date. If problems still persist, the Vendor may call the FBO help desk at 866-606-8220, selection option 2 for FBO issues, and ask for troubleshooting assistance.

Dated 26 Jul 13

Q3. Would the Government consider a micropile foundation solution for this project?

A3. A micorpile foundation solution is currently under consideration. Addendum to be forthcoming.

Dated 31 Jul 13

Q4. Spec section 03 30 04.00 2.1.2 (Aggregates), Spec Spection 32 13 11 2.2.1.1.a (Alkai-Silica Rectivty) & Section 00110 - Technical Proposal Requirements 3.4.2.3.2.

Please reconsider the testing requirement ASTM C1260 and replace with ASTM C1293 “Standard Test Method for Determination of Length Change of Concrete Due to Alkali-Silica Reaction” and ASTM C227 mailto:jcp-admin@.dla.mil

“Standard Test Method for Potential Alkali Reactivity of Cement-Aggregate Combinations (Mortar-Bar Method)”. On several recent NavFac projects these alternate tests have been accepted.

A4. No, this replacement is not acceptable. Offeror must provide per the specifications as issued.

Q5. Section 00110 – Technical Proposal Requirements 3.4.2.3.3 – Resume for Safety Manager/Represenative. Please advise if you want a resume for the Site Safety Health Office who will be on-site or the Corporate Safety Manager who will appoint the Site Safety Health Officer.

A5. Provide resume for Safety Officer who will be on the project site.

Q6. Section 00110 – Volume 2 Part 2 Past Performance 3.4.3.10. Due to the larger number of requests that are made for Past Performance Questinnaires can we submit previously completed PPQ’s where the form is the same of similar to Exhibit C?

A6. Yes previously completed PPQ’s may be submitted as long as the PPQ is dated and completed within the previous six (6) months. If providing a previously completed PPQ, include the form directly behind the Exhibit A it applies to. Additionally, “Final” Perfromance Ealuation (Construction) (aslo referred to as CCASS Evaluation) issued for a project may be included in lieu of sending out reference package for the project. If provided include the form directly behind the Exhibit A it applies to.

Dated 01 Aug 13

Q7. According to Section 00110-2.2 it states Contractors will need to execute a disclosure agreement with pertinent language required to be included. Is this a disclosure agreement that is supplied by the Government or should the language be included in the verbiage of the standard proposal? If so where would the Government prefer the language to be seen?

A7. In accordance with Section 00110 Paragraph 2.2, offerors must contact the companies listed in Paragraph 2.1 to effect execution of a disclosure agreement. If your firm has a standard or corporate disclosure agreement that it utilizes your firm may choose to request execution of that document. A sample agreement has been posted with the Q&A document dated 01 Aug 13 for those firms that wish to execute an agreement but do not have a corporate or standard agreement. Copies of the executed agreement should be included as attachments in Volume 1 of your proposal.