B.08 Amendment One 21R4003 4.21.21.pdf

PDF 771 KB Posted

Attached to
Veterans Affairs, Parking Expansion, Columbia, SC
Solicitation number
W912HP21R4003
Issued by

About this file

This document is an amendment to a solicitation for the Veterans Affairs Parking Expansion project in Columbia, South Carolina. The amendment makes several changes to the solicitation, including deleting testing requirements from specification 01 81 13, clarifying that testing requirements are defined in specification 01 45 29, revising the daily liquidated damages assessment to $2,565, and changing the descriptions of CLINs 0005 and 0006 to designate them as alternates D and E. Proposals are due no later than 2:00 PM EST on May 3, 2021. The agency issuing this solicitation is the Department of the Army Corps of Engineers Engineering District Charleston.

View the file

Other files

File Type Posted
D.03 Award Notice 21C4000 8.30.21.pdf PDF
B.08 Memorandum Amendment 0005 21R4003 5.20.21.pdf PDF
B.08 Amendment 0005 21R4003 5.20.21.pdf PDF
A.02 Amendment 0005 09 54 23 - Linear Metal Ceilings 21R4003 5.20.21.pdf PDF
B.08 Memorandum Amendment Four 21R4003 5.13.21.pdf PDF
07 24 00 - Exterior Insulation and Finish Systems.pdf PDF
00 01 10 - TOC.pdf PDF
2021-04-19 - Structural Revised Sheets.pdf PDF
2021-04-19 - General and Architectural Revised Sheets.pdf PDF
00 01 15 - List of Drawings.pdf PDF
B.08 Amendment Four 21R4003 5.13.21.pdf PDF
07_84_00_-_Firestopping..pdf PDF
AE601 Signage Schedule Stripping and Details.pdf PDF
Rev 4 SB101 - FOUNDATION PLAN.pdf PDF
Revised Bid Schedule page 5 of 79.pdf PDF
2017.1058.02 - 21.04.23-VA COLUMBIA - GARAGE ADDITION - Revision 2 (002).pdf PDF
Parking Garage Project Device and Conduit Plan.pdf PDF
B.08 Final Amendment Three 21R4003 5.6.21.pdf PDF
B.08 Amendment Two 21R4003 4.29.21.pdf PDF
A.02 Amendment One Attachement Spec Revision 21R4003 4.21.21.pdf PDF
B.08 Site Visit Sign In Sheet 21R4003 4.21.21.pdf PDF
A.02 UFGS4288 21R4003 4.1.21.xlsx XLSX spreadsheet
A.02 17.1058.02 - RTA SPECIFICATIONS - VOL II 21R4003 4.1.21.pdf PDF
A.02 17.1058.02 - RTA SPECIFICATIONS - VOL I with Div1 Rev 021021 4.1.21.pdf PDF
A.02 UFGS4288 21R4003 4.1.21.txt TXT text file
B.08 VA Columbia Parking Expansion Solicitation 21R4003 4.1.21.pdf PDF
A.02 17.1058.02 - RTA CD DRAWINGS Revised 21R4003 4.1.21.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

See SF 30, Block 14 Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Apr-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HP21R4003

X 9B. DATED (SEE ITEM 11)

01-Apr-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Apr-2021

CODE

PROGRAMS & PROJECT MGMT DIV

69-A HAGOOD AVENUE

CHARLESTON SC 29403-5107

W912HP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HP21R4003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 1 CHANGES

The purpose of this amendment is to:

1. Delete the requirements of specification 01 81 13 Part 3.1.4 a and b.

2. 01 45 35 Special Inspections is not included in the Division 01 Specs. 01 45 29 Testing

Laboratory Services is included in the Division 01 Spec Package and defines the testing required by this RFP. Additionally, the other Technical Spec Sections may include Special Inspection and Testing requirements. Addendum will be issued as follows: ‘All references to 01 45 35 will be changed to 01 45 29’.

3. SECTION 01 00 00 GENERAL REQUIREMENTS (Page One) has been revised to reflect a daily liquidated damages assessment of $2, 565.00 (See attachment).

4. Revise the description for CLINS 0005 and 0006.

5. Incorporate the Site Visit Sign In Sheet. (See attachment).

SECTION 00 10 00 - SOLICITATION

CLIN 0005

The CLIN extended description has changed from:

ADD 4 STOP ELEVATOR IN STAIR TOWER 1 WHICH IS LOCATED BETWEEN GRID LINES 6 AND 8.

THIS INCLUDES ALL NECESSARY APPURTENANCES (INCLUDING BUT NOT LIMITED TO: LIGHTING, DRAINAGE, SECURITY CAMERAS, FALL DETERRENT, EMERGENCY SYSTEMS, SIGNAGE AND

WAYFINDING, HAND AND GUARDS RAILS) TO MAKE THE GARAGE COMPLETE WITHIN THIS AREA.

To:

ADD ALTERNATE D: ADD 4 STOP ELEVATOR IN STAIR TOWER 1 WHICH IS LOCATED BETWEEN

GRID LINES 6 AND 8. THIS INCLUDES ALL NECESSARY APPURTENANCES (INCLUDING BUT NOT

LIMITED TO: LIGHTING, DRAINAGE, SECURITY CAMERAS, FALL DETERRENT, EMERGENCY

SYSTEMS, SIGNAGE AND WAYFINDING, HAND AND GUARDS RAILS) TO MAKE THE GARAGE

COMPLETE WITHIN THIS AREA. THE BASE BID PLUS ADD ALTERNATE A, B AND C GARAGE AREA

IS SHOWN ON THE SHEET FOR CONTINUITY AND CONNECTION UNDERSTANDING ONLY. SEE ALT.

AS SHOWN ON SHEETS (SF301, AE152, MM104, PP105CD, EA104CD) AND ALL ASSOCIATED DETAILS.

CONTRACT TIME SHALL BE 28 CALENDAR DAYS FOR THIS ALTERNATE.

CLIN 0006

W912HP21R4003

The CLIN extended description has changed from:

SEE ALT. AS SHOWN ON SHEETS (SF301, AE152, MM104, PP105CD, EA104CD) AND ALL ASSOCIATED

DETAILS. CONTRACT TIME SHALL BE 28 CALENDAR DAYS FOR THIS ALTERNATE. SEE ALT. AS

SHOWN ON SHEETS (SF301, AE152, MM104, PP105CD, EA104CD) AND ALL ASSOCIATED DETAILS.

CONTRACT TIME SHALL BE 28 CALENDAR DAYS FOR THIS ALTERNATE.

To:

ADD ALTERNATE E: ADDITIONAL LANDSCAPE DESIGN AS SHOWN ON SHEET LP102 AND ALL

ASSOCIATED DETAILS. CONTRACT TIME SHALL BE 7 CALENDAR DAYS FOR THIS ALTERNATE.

(End of Summary of Changes)