About this file

This document contains a past experience information sheet and details of a revised one-step design-bid-build multiple award task order contract solicitation for construction projects in Romania. The past experience information sheet requests information on five relevant past projects completed within the last six years in the European Union or United Kingdom, including location, completion date, final cost over $5 million, percentage of completion, customer, and construction category. Offerors must identify their role as prime contractor, subcontractor, joint venture, or key subcontractor for each project and provide additional explanation for subcontractor or joint venture work. The revised solicitation seeks contractors for new facility construction and real property repair and maintenance task orders in Romania under an indefinite-delivery, indefinite-quantity contract structure. It was changed from the previous pre-solicitation to only include design-bid-build and remove design-build.

View the file

Other files

File Type Posted
B.08.02 W912GB21R0002-Amnd 0006.pdf PDF
B.08.02 W912GB21R0002-Amnd 0005.pdf PDF
Amend 0005_Attachment 9 - 100 Final_EDI Apron Romania_PRICE SCHEDULE.xlsx XLSX spreadsheet
Amend 0005_Attachment 8b - 100 Final_EDI Apron Romania_Construction Drawings_Issued for Construction.pdf PDF
Amend 0005_Attachment 8a - 100 Final_EDI Apron Romania_Specifications_EN.pdf PDF
B.08.02 W912GB21R0002 Amnd 0004.pdf PDF
Attach 5 BankLetterAssurance-rev 12Nov2020.docx DOCX document
B.08.02 W912GB21R0002-Amnd 0003.pdf PDF
Attach 9 Seed Project Aircraft Parking Apron Price Schedule (Euros revised 12NOV2020).xlsx XLSX spreadsheet
Attach 3 PastExpOverviewSheet (revised).docx DOCX document
RO MATOC PPC Slide Deck 29OCT (FINAL).pdf PDF
B.08.02 W912GB21R0002-Amnd 0002.pdf PDF
FY21 Romania MATOC PPC ROSTER (BY COMPANY NAME) 29OCT2020.pdf PDF
Attach 8b - 100- Final_EDI Apron Romania_Construction Drawings.pdf PDF
B.08.02 W912GB21R0002-Amnd 01 Drawings.pdf PDF
Attach 9 - 100- Final_EDI Apron Romania_PRICE SCHEDULE.xlsx XLSX spreadsheet
Attach 8a - 100- Final_EDI Apron Romania_Specifications_EN.pdf PDF
Attach 10 Bonds and other financial protections.pdf PDF
B.08.02 W912GB21R0002-Solicitation -26Oct2020.pdf PDF
Attach 7 Letter of Commitment Sample.docx DOCX document
Attach 4 PPQ.DOCX DOCX document
Attach 1 - Spec Binder.pdf PDF
Attach 5 BankLetterAssuranceSample_final.docx DOCX document
Attach 6 BankLetterGuaranteeSample_final.docx DOCX document
Attach 2 Past ExpInfoSheet.docx DOCX document
Attach 3 Past ExpOverviewSheet.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fiscal Year 2021 DBB Romania MATOC W912GB21R0002 (revised-Amnd 0002)

PAST EXPERIENCE INFORMATION SHEET

PROJECT NO. _____, Page 1 (project number is taken from column 1 on Attachment: Experience Overview Sheet) Must have a total of 5 projects, more than 5 will not be evaluated; less than 5 may result in a lower rating Project Name and Location (City, Country):

Past Experience:

1. The location work was performed in the European Union/United Kingdom (construction projects in Romania considered more relevant): ___________________________________

2. The day, month, and year work was completed; must be completed within last six (6) years of the date of this solicitation: _______________

3. The final cost of this project, shall be over ($5,000,000): $_________________________

4. Is this project more than 50% complete by the date of this solicitation? ____ Yes ____ No If “No” explain percentage of completion, if not 50% complete for any reason, rating may be lower

5. Who was the customer/end user of the project? _________________________

6. Do not provide a listing of existing or previous contracts, but rather provide detailed information of construction work for projects in at least one of the following categories, but work in more than one category may receive a higher rating:

a. New Construction

b. Renovations of buildings

c. Vertical Construction

d. Horizontal Construction

e. Military or commercial airfield/airbase Construction

(Continue typing if required to provide more information)

PAST EXPERIENCE INFORMATION SHEET

PROJECT NO. _____ Page 2

Offeror: A contractor and/or company submitting a proposal for this solicitation.

Prime Contractor: A contractor that self-performed at least 20% of the work, and managed all other work for the project.

Sub Contractor: A contractor that performed part of the project work, but did not manage the entire project.

Joint Venture: More than one contractor with a legal binding agreement to work together.

Key Subcontractor: A contractor that has signed a letter of commitment to perform work for the duration of the contract for the Offeror, and the Offeror is allowed to take credit for the Key Subcontractor’s experience the project.

7. Mark one of these selections:

Work was completed as the ____ Prime ____ Subcontractor ___ Joint Venture __ Key Subcontractor

a. No additional information is required for work performed as the Prime other than what is on Page 1 of this form.

b. If work was as a Joint Venture, explain the relationship of the company, which company performed the work, and how the work performed and the relationship provides an added benefit for experience.

c. If work was performed as a Key Subcontractor, explain how the work performed as a Key Subcontractor provides an added benefit for experience:

d. If work was as a Subcontractor, explain how the work performed as a Subcontractor is a benefit for experience such as, responsible for the work performed and managed the portion of work performed including submittals:

e. Ensure you provide a letter signed by both the Offeror and the Key Subcontractor in order to take credit for the project work. Besides the signed letter, no additional information is required other than what is on Page 1 of this form.